46/F,
Wan Chai,
Agreement
No. CE 55/2006 (EP)
Inter-reservoirs
Transfer Scheme (IRTS)
-
Water Tunnel between
Environmental Impact Assessment Report
(Final)
Report No.: 240564/02/E
February 09
in association with
ADI Limited
Archaeological
Assessments
Mott MacDonald Hong Kong Ltd
7/F,
Tsim Sha Tsui,
Tel: 2828
5757
Fax: 2827
1823
This document has been prepared for the titled project
or named part thereof and should not be relied upon or used for any other
project without an independent check being carried out as to its suitability
and prior written authority of Mott MacDonald being obtained. Mott MacDonald accepts no responsibility or
liability for the consequence of this document being used for a purpose other
than the purposes for which it was commissioned. Any person using or relying on the document
for such other purpose agrees, and will by such use or reliance be taken to
confirm his agreement to indemnify Mott MacDonald for all loss or damage
resulting therefrom. Mott MacDonald
accepts no responsibility or liability for this document to any party other
than the person by whom it was commissioned.
To the extent that this report is based on information
supplied by other parties, Mott MacDonald accepts no liability for any loss or
damage suffered by the client, whether contractual or tortious, stemming from
any conclusions based on data supplied by parties other than Mott MacDonald and
used by Mott MacDonald in preparing this report.
List of Contents Page
1.2 Purpose and Approach of the EIA Study 1-1
1.3 Structure of this EIA Study Report 1-3
2.1 Project Requirements & Programme 2-1
2.2 The Study Area and Constraints 2-1
2.3 Need for the Project and Consequences of not
Proceeding with the Project 2-2
2.4 Consideration of Different Alignment Options 2-2
2.5 Selection of Preferred Scenario 2-3
2.6 Consideration of Alternative Construction Methods
and Sequence of Work 2-7
2.7 Interface with Planned Projects 2-8
3.2 Relevant Legislations, Standards & Guidelines 3-1
3.3 Study Area and Air Sensitive Uses 3-3
3.4 Background Air Quality 3-3
3.5 Construction Phase Impacts 3-4
3.6 Potential Cumulative Impacts due to Concurrent Works 3-5
3.7 Environmental Monitoring and Audit Requirements 3-6
4.2 Relevant Legislations, Standards & Guidelines 4-1
4.4 Noise Sensitive Uses (Air-borne and Ground-borne) 4-4
4.5 Analysis of Construction Activities and Sources of
Noise Impact 4-5
4.6 Assessment Approach & Methodology 4-5
4.7 Unmitigated Construction Noise Impacts (Airborne) 4-8
4.8 Noise Mitigation Measures 4-9
4.9 Potential Cumulative Impacts due to Concurrent Works 4-9
4.10 Ground-borne Noise Impact 4-10
4.11 Environmental Monitoring and Audit (EM&A)
Requirements 4-11
4.12 Evaluation of Constraints on Planned Noise Sensitive
Development/ Land Uses 4-11
5.2 Relevant Legislations, Standards & Guidelines 5-1
5.4 Water Systems, Catchments and Water Sensitive
Receivers 5-3
5.5 Baseline Water Quality and Water Quality Standards 5-4
5.6 Water Quality Assessment Methodology 5-5
5.7 Identification and Evaluation of Water Quality
Impact during the Construction Phase 5-5
5.8 Project-Related Pollution Sources and Cumulative
Impact Implications 5-8
5.9 Water Quality Impact during the Operational Phase 5-8
5.10 Water Pollution Mitigation and Management 5-8
5.11 Evaluation and Quantification of Residual Impacts 5-11
5.12 Environmental Monitoring and Audit Requirements 5-11
5.13 Conclusion and Recommendations 5-12
6.2 Relevant Legislations, Standards & Guidelines 6-1
6.3 Analysis of Activities & Waste Generation 6-2
6.4 Waste Management Hierarchy 6-2
6.5 Impact Assessment and Evaluation 6-3
6.6 Summary of Estimated Quantities of Wastes that could
be Generated 6-4
6.7 Waste Management Practice during the Construction
Phase 6-6
6.8 Waste Management Practice during the Operational
Phase 6-7
6.9 Environmental Monitoring and Audit Requirements 6-8
6.10 Conclusion and Recommendations 6-8
8.2 Relevant Legislations, Standards & Guidelines 8-1
8.3 Assessment Methodologies 8-2
8.4 Description of Existing Ecological Baseline
Conditions 8-4
8.5 Evaluation of Sites and Species 8-13
8.6 Identification of Potential Impacts 8-22
8.7 Evaluation of Impacts 8-26
8.8 Recommendations on Ecological Impact Mitigation
Measures 8-32
8.9 Environmental Monitoring and Audit Requirements 8-36
9. Landscape
and visual impact 9-1
9.2 Environmental Legislation, Standards and Legislation 9-1
9.3 Landscape and Visual Impact Assessment Methodology 9-2
9.5 Review of Planning and Development Control Framework 9-7
9.6 Landscape and Visual Baseline Study 9-8
9.7 Landscape Impact Assessment 9-16
9.8 Visual Impact Assessment 9-19
9.9 Landscape and Visual Mitigation Measures 9-21
9.10 Residual Environmental Impact 9-25
9.11 Environmental Monitoring and Audit Requirement 9-28
10. Cultural
heritage impact 10-1
10.2 Relevant Legislation and Guidelines 10-1
10.5 Identified Sites of Cultural Heritage within Study
Area 10-4
10.7 Mitigation Recommendations 10-6
11. Implementation
Schedule of Mitigation Measures 11-1
12. Summary
of Findings, Conclusion & Recommendations 12-1
12.3 Construction Noise Impact 12-1
12.4 Water Quality Impact 12-2
12.8 Landscape and Visual Impact 12-4
12.9 Cultural Heritage Impact 12-4
List of Appendices
Appendix A.......... Study Brief
Appendix B.......... Construction Program, Envisaged Activities and Inventory of PME
Appendix C.......... Unmitigated
Construction Noise Impact (Air-borne)
Appendix D.......... (Not Used)
Appendix E.......... Ground-borne
Noise Impact
Appendix F.......... Baseline
Raw Water Quality at Kowloon Byewash and Lower Shing Mun Reservoirs
Appendix G.......... Ecological
Survey Results
Appendix
I........... Preliminary Tree
Survey Schedule
Appendix J........... Catalogue
List of Tables
List of Figures
Figure 1-1 The Proposed Inter-reservoirs
Transfer Scheme (IRTS)
Figure 1-2 Cross-sections of the Project
(Sheet 1 of 5)
Figure 1-3 Cross-sections of the Project
(Sheet 2 of 5)
Figure 1-4 Cross-sections of the Project
(Sheet 3 of 5)
Figure 1-5 Cross-sections of the Project
(Sheet 4 of 5)
Figure 1-6 Cross-sections of the Project
(Sheet 5 of 5)
Figure 2-1 The Project Alignment and
Environmental Constraints
Figure 2-2 Reference and Alternative Tunnel
Alignment and Portals
Figure 2-3 Reference and Alternative
Locations of Intakes
Figure 2-4 Reference and Alternative
Locations of Outfalls
Figure 2-5 The Preferred Scheme
Figure 2-6 Envisaged Site Works near Outfall
End
Figure 2-7 Envisaged Site Works near Intake
End
Figure 3-1 The Study Area and Identified ASRs
(Intake End)
Figure 3-2 The Study Area and Identified ASRs
(Outfall End)
Figure 4-1 The Study Area and Representative
NSRs (Intake End)
Figure 4-2 The Study Area and Representative
NSRs (Outfall End)
Figure 5-1 The Study Area and Water Sensitive
Receivers (Intake End)
Figure 5-2 The Study Area and Water Sensitive
Receivers (Outfall End)
Figure 5-3a-e Longitudinal Geological Profile for
Proposed Water Transfer Tunnel
Figure 5-4 Location of Discharge at Intake
End
Figure 5-5 Location of Discharge at Outfall
End
Figure 7-1 The Preferred Scheme
Figure 8-1 Ecological Survey Locations and
Study Boundary
Figure 8-4 Habitats around the Proposed
Intake at Kowloon Byewash Reservoir
Figure 8-5 Habitats around the Proposed
Outfall at Lower Shing Mun Reservoir
Figure 8-6 Proposed Area for Habitat
Restoration at Kowloon Byewash Reservoir
Figure 8-7 Proposed Area for Habitat
Restoration at Lower Shing Mun Reservoir
Figure 9-1a-b Landscape Resources
Figure 9-2 Landscape Character Areas
Figure 9-3a-b Photographic Record of Site Context
Figure 9-3c-d Photographic Record of LRs and LCAs
Figure 9-4a-b Visual Envelop and Zone of Visual
Influence
Figure 9-6a-b Landscape and Visual Mitigation Plan
Figure 10-1 Locations of Kowloon Byewash
Reservoir Dam and Valve House near the Intake
Figure 10-2 Location of Lower Shing Mun
Reservoir Dam in the vicinity of the Outfall
1.1.1
This Project is named as “West Kowloon Drainage
Improvement – Lai Chi Kok Transfer Scheme - Inter-Reservoirs Transfer Scheme
(“IRTS”) – Water Tunnel between
1.1.2 The main objective of the Project is to serve the dual purpose to substantially reduce stormwater discharge into the drainage system in the Lai Chi Kok area and, at the same time, to channel the overflow into the Lower Shing Mun Reservoir via the proposed IRTS tunnel to generate an average annual raw water yield at about 2.5 million m3.
1.1.3 This Project partly falls within the Kam Shan Country Park and is a designated project (“DP”) under Item Q.1 of Part I, Schedule 2 of the EIAO which specifically encompasses “All projects including new access roads, railways, sewers, sewage treatment facilities, earthworks, dredging works and other building works partly or wholly in an existing or gazetted proposed country park or special area, a conservation area, an existing or gazetted proposed marine park or marine reserve, a site of cultural heritage, and a site of special scientific interest”.
1.1.4 An application (No. ESB-154/2006) for an Environmental Impact Assessment (“EIA”) study brief under section 5(1) of the Environmental Impact Assessment Ordinance (“EIAO”) was submitted by the Water Supplies Department (“WSD”) on 29 September 2006 with a Project Profile (No. PP-298/2006). An EIA Study Brief (No.: ESB-154/2006) was issued by EPD on 9 Nov 2006 for carrying out the EIA which is shown in Appendix A.
1.1.5 Figure 1-1 shows this Project and the general EIA Study Area within 500m of the proposed tunnel alignment and both portals, and Figures 1-2 to 1-6 shows the cross-sections of the project.
1.1.6 Mott MacDonald Hong Kong Limited (formerly Mott Connell Limited) was commissioned by WSD to conduct this EIA under Agreement No. CE 55/2006 (EP). Another engineering consultancy on the same Project was awarded to Black & Veatch Hong Kong Limited under Agreement No. CE54/2006 (WS) to carry out investigation, design and construction (“IDC”) for the Project.
1.2 Purpose and Approach of the EIA Study
1.2.1 The purpose of this EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the project and related activities taking place concurrently. This information will contribute to decisions by the Director of Environmental Protection on: -
· The overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
· The conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
· The acceptability of residual impacts after the proposed mitigation measures is implemented.
1.2.2 This EIA Study has been conducted to achieve a number of more specific objectives listed in Clause 2.1 of the EIA Study Brief. These specific objectives are:
1. to describe the Project and associated works together with the requirements for carrying out the Project;
2. to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment;
3. to provide information on the consideration of alternatives to avoid and minimise the potential adverse environmental impacts on the sensitive uses that may be subject to the adverse environmental impacts of the proposed developments and associated works; to compare the environmental benefits and dis-benefits of each of the different options; to provide reasons for selecting the preferred option(s) and to describe the part of environmental factors played in the selection of the preferred option(s);
4. to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;
5. to identify and quantify any potential losses or damages and other potential impacts on flora, fauna and natural habitats and to propose measures to mitigated these impacts;
6. to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;
7. to identify and assess any adverse impacts on historical buildings/structures and archaeological sites and to propose measures to mitigate these impacts;
8. to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;
9. to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
10. to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;
11. to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;
12. to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and
13. to design and specify the environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.
1.3 Structure of this EIA Study Report
1.3.1 The EIA Report is divided into a total of 13 sections, viz.:
· Section 2 - Project Description
· Section 3 - Air Quality Impact
· Section 5 - Water Quality Impact
· Section 6 - Waste Management
· Section 8 - Ecological Impact
· Section 9 - Landscape & Visual Impact
· Section 10 - Cultural Heritage Impact
· Section 11 - Implementation Schedule of Mitigation Measures
· Section 12 - Summary of Findings, Conclusion & Recommendations
2.1 Project Requirements & Programme
2.1.1 The proposed Project, which this EIA concerns, is shown on Figure 2-1 and comprises the following principal works elements:
1. Construction of a new water tunnel, approximately 2.8 km in length and 3m in diameter, from Kowloon Byewash Reservoir to Lower Shing Mun Reservoir;
2. Construction of an intake structure at Kowloon Byewash Reservoir and an isolation system;
3. Construction of an outfall structure at Lower Shing Mun Reservoir with an energy dissipater; and
4. All associated civil, structural, geotechnical, electrical and mechanical works, including landscaping, permanent and temporary accesses as may be necessary for the completion of the works elements listed above.
2.1.2
The project will only involve underground tunnelling
works beneath the
2.1.3 According to the latest estimate, the Project (reference scheme) is scheduled to commence construction in late 2009 for completion by mid 2012 as shown in Appendix B. However, as a result of adopting an alternative IRTS scheme, the program can be shortened and realise an early completion by early 2012.
2.2 The Study Area and Constraints
2.2.1
Depending on specific requirements of various
disciplines, the EIA Study area is generally defined within 500m of the Project
alignment and both portals. The Project
falls within the
2.2.2 All uses and development within the country park and the WGG require prior consent from the Country and Marine Parks Authority and the Water Supplies Department respectively.
2.2.3 Main environmental constraints of the Project are shown in Figure 2-1 and encompass the following key elements: -
1. Outline Zoning Plan (“OZP”) which shows the environmentally sensitive uses falling within the 500m envelop of the Project;
2. Lower direct water gathering grounds (WGG) where both portals situate;
3.
4. Location of the proposed Intake (work site) within Consultation Zone of the Shek Lei Pui Water Treatment Works – a potentially hazardous installation (PHI).
2.2.4 The associated impacts have been addressed in the Chapters 3-10 of this EIA Report.
2.3 Need for the Project and Consequences of not Proceeding with the Project
2.3.1
The Project is part of the LCKTS and forms an integral
part of the overall flood control strategy for
2.3.2 The Project would help to reduce the scale of the LCKTS and the disturbance caused by the original works in the affected areas. It also contributes to an overall capital cost saving and generates an average additional raw water yield of about 2.5 million m3 a year and promotes sustainability in water conservation.
2.3.3 Without this Project these benefits cannot be realised.
2.4 Consideration of Different Alignment Options
Reference Tunnel Portals and Alignment
2.4.1 The reference tunnel alignment (A-C) as shown in Figure 2-2 was identified during the feasibility study stage and is a rather straight route connecting the two reservoirs. It was selected to avoid running directly underneath the existing reservoirs and measures approximately 2.8km long. The reference tunnel would cross the existing High Island Water Tunnel, which is at a lower level.
2.4.2
The reference intake location (Intake A) is located at
the south-western part of the Kowloon Byewash Reservoirs, which is the lowest
member of the Kowloon Group of Reservoirs.
The reference outfall location (Outfall C) is located at the southern
side of the Lower Shing Mun Reservoir along the
2.4.3 The reference outfall portal has been intended as the launching site for tunnelling works as the direction of drive from outfall to intake allows the tunnel to drain naturally during construction and to reduce the chances of tunnel inundation.
Alternative Tunnel Portals and Alignment
2.4.4 As part of the associated consultancy under Agreement No. CE54/2006 (WS), the IDC consultant has prepared Working Paper No. 1 [i] to evaluate alternative portal locations and tunnel alignments in August 2007. The study involved a comprehensive evaluation of various key factors including: -
· Environmental benefits;
· Geology, hydrogeology and geotechnical engineering;
· Hydraulic performance, cost and programme;
· Tunnel constructability, site formation and landslip preventive works; and
· Operation and maintenance, traffic, utilities, land matter and interface with other planned concurrent projects.
2.4.5 In summary, the evaluation has generated 4 combinations of tunnel alignment viz., tunnel Alignment A-C, B-C, B-D, and A-D as shown in Figure 2-2 with alternative intake and outfall locations shown in Figure 2-3 and Figure 2-4.
2.5 Selection of Preferred Scenario
Preferred Tunnel Portals and Alignment
2.5.1 Amongst the various combinations of options, it was concluded in Working Paper No. 1 that Alignment A-D should be the preferred one after consideration of the programme, constructability, and maintenance, environmental and social impacts to the public and this preferred alignment is shown in Figure 2-5. The work site areas of the Outfall and Intake structure are shown in Figure 2-6 and Figure 2-7.
2.5.2 The preferred alignment concluded in this WP No. 1 is agreeable under this EIA based on the review given in Table 2-1. As the various tunnel alignments are all underground and hence would not make a lot of difference in the environmental impacts. The comparison below has therefore focussed on both portals.
Table 2‑1 Comparison of Environmental Impacts of Various Alternative Portal Locations
Environmental Impacts |
Intake A |
Intake B |
Outfall C |
Outfall D |
Air quality – fugitive dust |
Though Intake A is closer to air sensitive
receivers (ASRs), an adequate separation of 145m can still be maintained and
hence will not cause any unacceptable impact/ nuisances |
Intake B is further away from the ASRs and
hence will cause the least impact/ nuisance |
Outfall C is further away from the ASRs and
hence will cause the least impact/ nuisance |
Though Outfall D is closer to ASRs, an adequate
separation of 200m can still be maintained and hence will not cause any
unacceptable impact/ nuisances |
Construction Noise (air-borne) |
Same comment
as above in terms of airborne construction noise impact. Detailed assessment
in Chapter 4 has demonstrated full compliance for Alignment A-D |
|||
Construction Noise (ground-borne) |
Same comment
as above in terms of ground-borne construction noise impact. Detailed
assessment for AD in Chapter 4 has demonstrated full compliance for Alignment
A-D |
|||
Water quality |
Same for any
of the 4 combinations |
|||
Waste generation |
Length of
tunnel is rank in ascending order as BD (2.6km) < BC (2.7km) < AC
(2.8km) < AD (2.9km). Difference is insignificant |
|||
Hazard to life |
Worksite of Intake A is within 400m of the Shek
Lei Pui WTW |
Worksite of Intake B is further away from the
Shek Lei Pui WTW and hence should be subject to a lower hazard level |
N.A. |
N.A. |
Ecological Impact |
Impact on vegetation could be minimised as most
of the worksite area is proposed on one existing barbecue site. |
Comparing with Intake A, potentially larger
area of vegetation would be affected. |
Disturbance to wildlife and habitats would be
comparatively significant as this outfall is proposed at the core of the
woodland. |
Disturbance to wildlife and surrounding habitats
could be reduced as the outfall is proposed away from the core area of the
woodland. |
Landscape Resources |
LR1: (Moderate
adverse) Loss of small number of trees and existing vegetation surrounding
the proposed work site. LR2: (Moderate
Adverse) Appearance of new intake structure with permanent access road. LR3: (Insubstantial
impact) |
LR1: (Moderate
adverse) Potential loss of a relatively larger number of trees and existing
vegetation surrounding the proposed work site. LR2: (Moderate
Adverse) Receive similar impact as intake A option LR3: (Insubstantial
impact) |
LR1: (Moderate adverse) Potential loss of large number of
trees and existing vegetation surrounding the proposed work site due to the
location of core woodland LR2: (Moderate
Adverse) Appearance of new outfall structure LR3: (Insubstantial
impact) |
LR1: (Moderate
adverse) Loss of small number of trees and existing vegetation surrounding
the proposed work site. LR2: (Moderate
Adverse) Receive similar impact as outfall C option LR3: (Insubstantial
impact) |
Landscape Character
Area |
LCA1: (Moderate
Adverse) Loss of existing trees, alternation of a part of existing picnic
site to permanent access road, alternation of existing topography and
appearance of new intake structure LCA4: (Insubstantial
Impact) No activity in LCA4. |
LCA1: (Moderate
Adverse) Loss of potentially larger number of existing trees compared with
Intake A option, alternation of existing woodland into permanent access road,
alternation of existing topography and appearance of new intake structure LCA4: (Insubstantial
Impact) Similar to Intake A option |
LCA2: (Moderate
Adverse) Loss of existing trees, alternation of existing topography and
appearance of new outfall structure LCA3: (Insubstantial Impact) No activity in LCA3. |
LCA2: (Moderate Adverse)
Similar impact received as Outfall C option LCA3: (Insubstantial Impact) Similar to Outfall Option C |
Visual Impact |
Moderate Adverse
Impact: residents of |
Moderate Adverse
Impact: Visitors in Kam Shan Country Park (T1) due to the appearance of new
intake structure Insubstantial Impact
for other VSRs as proposed structure is further is more distant and not
visible to Residents of No. 8 Caldecott Road former government |
Moderate Adverse
Impact: trail walkers in Lower Shing Mun Reservoir (T2) due to the appearance
of new outfall structure Insubstantial Impact
for other VSRs as proposed structure is more distant and not visible to residents in Lakeview Garden (R1) |
Moderate Adverse
Impact: trail walkers in Lower Shing Mun Reservoir (T2) and residents in
Lakeview Garden (R1) due to the appearance of new outfall structure |
Cultural heritage impact |
Intake A is close to the Grade II Dam and Grade
II Valve House of Kowloon Byewash Reservior. However, the level of vibration
will be controlled at low levels so that impact to the Dam and Valve House
should be acceptable. |
Intake B is close to the Grade I Dam and Grade
I Valve House of Kowloon Reservior. However, the level of vibration will be
controlled at low levels so that impact to the Dam and Valve House should be
acceptable. |
Outfall C is further away from the Graded
structures of the Lower Shing Mun Reservoir (also known as Shing Mun
(Jubilee) Reservior Lower Reservior) than Outfall D. However, the separation
distance is already enough and no adverse impacts are expected |
Compared with Outfall C, Outfall D has a
shorter separation distance to the Graded structures of the Lower Shing Mun
Reservoir (also known as Shing Mun (Jubilee) Reservior Lower Reservior).
However, the separation distance is already enough and no adverse impacts are
expected |
2.6 Consideration of Alternative Construction Methods and Sequence of Work
2.6.1 The IDC consultant has also produced the Working Paper No. 3 [ii] to evaluate various options of construction methods for the water transfer tunnel and both portals. The following are the construction methods proposed and preferred.
Main Tunnel
2.6.2 Drill & Blast (D&B) and TBM are the most commonly used methods for tunnelling, and are feasible excavation technologies for tunnel construction where generally competent rock conditions are encountered. Others less common technologies which do not offer any special benefits, and were therefore not considered further due to limited plant availability and the relatively low efficiency. From an overall engineering point of view, tunnelling by TBM has benefits of a shorter construction programme, minimal over-breaking, and smooth lining, and is intrinsically safer.
Tunnel Portal and TBM Starter Tunnel
2.6.4 The formation of a portal access and starter tunnel/chamber for launching of TBM will be necessary. The use of conventional mechanical sequential excavation & support will be considered. For the same environmental and safety reasons mentioned above, drill and blast is considered not suitable. The alternative to D&B is likely to be a combination of mechanical, pneumatic or hydraulic splitting or expanding grout techniques. These are safe and environmental-friendly rock breaking methods that generate much less vibration. It is considered that these alternative methods are the preferred options, providing a favourable solution to suit site conditions and constraints as for the Project. For purpose of the EIA, the uses of hydraulic breaker and rock drill have been assumed for conservative evaluation of the impacts.
Sequence of Work
2.6.5 The envisaged sequence of work is presented in Appendix B. The design of the construction sequence has been to minimise overlapping so as to reduce cumulative noise impacts in particular.
2.7 Interface with Planned Projects
2.7.1 Planned projects identified include: -
·
PWP Item No. 155CD -
· Agreement No. CE 77/2001 (GE) and 2/2006 (GE) – Slope Upgrading Works with no definite program;
· The Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) – Hong Kong Section likely to commence in 2009.
2.7.2 It is envisaged that given the physical distance separation, the LCK drainage tunnel will unlikely to affect common sensitive receivers of the IRTS. The XRL is all underground with substantial vertical separation with the IRTS tunnel and hence will not affect the similarly.
2.7.3 Although the slope upgrading works could be close to the Intake A, the works would be minor in nature and would unlikely to contribute to significant cumulative impacts on common air and noise sensitive receivers located far from the works areas.
2.8.1 The Project Proponent has consulted the Development and Housing Committee (DHC) of the Sha Tin District Council in October 2005 and August 2006. At the DHC meeting held on 29 August 2006, members supported the IRTS.
2.9.1 In brief, the preferred alignment, i.e. A-D has been adopted for further study under the IDC consultancy and is agreeable from environmental perspective. The construction method recommended for the main tunnel will be by TBM, with mechanical excavation adopted for creation of the launching tunnel and both portals. Blasting is not considered practicable and has been ruled out for this Project. The EIA has been conducted based on these selections for various issues presented in the rest of chapters.
3.1.1
This assessment has been based on the criteria and
guidelines for evaluation and assessment of air quality impact stated in
Annexes 4 and 12 of the EIAO-TM and covered the scope outlined in
3.2 Relevant Legislations, Standards & Guidelines
3.2.1
Table 3‑1 Hong Kong Air Quality Objectives
Pollutant |
Concentration (mg/m3)(1) Averaging Period |
||||
1 Hour(2) |
8 Hours(3) |
24 Hours(3) |
3 Months(4) |
1 Year(4) |
|
|
800 |
- |
350 |
- |
80 |
Total suspended Particulate, TSP |
- |
- |
260 |
- |
80 |
Respirable Suspended Particulates, RSP(5) |
- |
- |
180 |
- |
55 |
Nitrogen Dioxide, NO2 |
300 |
- |
150 |
- |
80 |
Carbon Monoxide, CO |
30,000 |
10,000 |
- |
- |
- |
Photochemical Oxidants, (as ozone (6)) |
240 |
- |
- |
- |
- |
Lead |
- |
- |
- |
1.5 |
- |
Notes:
(1) Measured at 298 K and 101.325 kPa (one atmosphere)
(2) Not to be exceeded more than 3 times per year
(3) Not to be exceeded more than once per year
(4) Arithmetic means
(5) Respirable suspended particulates means suspended particles in air with a nominal aerodynamic diameter of 10mm or less
(6) Photochemical oxidants are determined by measurement of ozone only
3.2.2 For impacts during the construction stage, fugitive dust in particular, Section 1, Annex 4 of EIAO-TM stipulates the hourly average Total Suspended Particulate (“TSP”) concentration of 500 mg/m3 measured at 298 K (25°C) and 101.325 kPa (1 atmosphere) for construction dust impacts. Mitigation measures for construction sites specified in the Air Pollution Control (Construction Dust) Regulation should be followed.
3.2.3 The APCO’s subsidiary regulation Air Pollution Control (Construction Dust) Regulation defines notifiable and regulatory works activities that are subject to construction dust control.
Notifiable Works:
1. Site formation;
2. Reclamation;
3. Demolition of a building;
4. Work carried out in any part of a tunnel that is within 100 m of any exit to the open air;
5. Construction of the foundation of a building;
6. Construction of the superstructure of a building; or
7. Road construction work.
Regulatory Works:
8. Renovation carried out on the outer surface of the external wall or the upper surface of the roof of a building;
9. Road opening or resurfacing work;
10. Slope stabilisation work; or
11. Any work involving any of the following activities-
· Stockpiling of dusty materials;
· Loading, unloading or transfer of dusty materials;
· Transfer of dusty materials using a belt conveyor system;
· Use of vehicles;
· Pneumatic or power-driven drilling, cutting and polishing;
· Debris handling;
· Excavation or earth moving;
· Concrete production;
· Site clearance; or
· Blasting.
3.2.4 Notifiable works require that advance notice of activities be given to EPD. The Regulation also requires the works contractor to ensure that both notifiable works and regulatory works will be conducted in accordance with the Schedule of the Regulation, which provides dust control and suppression measures.
3.3 Study Area and Air Sensitive Uses
Study Area
3.3.1 Clause 3.4.1.2 of the EIA Study Brief prescribed a study area to be generally defined by a distance of 500m from boundary of the Project, or other project alignments as identified in the EIA. Figure 3-1 and Figure 3-2 show the study area (500m envelope) of the two portals and identified representative ASRs falling within this area.
Air Sensitive Uses
3.3.2
Although the study area can be as wide as 500m from the
work sites, the first tier of ASRs will usually be considered in planning the
works in order to minimise the dust nuisances.
Other ASRs further away from these first tier ones will be expected to
be less affected. As the assessment area
fall within the
Table 3‑2 Representative ASRs within the Assessment Area
ASRs |
Location |
Nature of Use |
Distance between ASRs and the work site boundary (m) |
Outfall end (Portal D) |
|||
A1 |
|
Residential |
200 |
A2 |
Golden Time Villas |
Residential |
295 |
A3 |
|
Residential |
290 |
Intake end (Portal A) |
|||
A4 |
|
Residential |
170 |
A5 |
Caldecott Hill |
Residential |
500 |
A6 |
Po |
Educational |
500 |
A7 |
Playground |
Recreational |
320 |
A8 |
Picnic area |
Recreational |
250 |
A9 |
Picnic area |
Recreational |
180 |
3.4.1 There are currently 11 general and 3 roadside air quality monitoring stations operated by EPD and one of the purposes is to provide background air quality information. The proposed IRTS water tunnel starts from the Kowloon Byewash Reservoir and ends at the Lower Shing Mun Reservoir. The two air quality monitoring stations, viz., Sha Tin and Sham Shui Po, are the nearest to the outfall and intake worksites respectively. The annual average air quality measured for the past 5 years (2002 to 2006) at the two stations are presented in Table 3-3. In consideration of the two worksites being at certain distance away from the urban areas, the lower background data at Sha Tin are considered more representative than that of Sham Shui Po, whilst the data at Sha Tin could represent an upper limit of the background air quality at the two worksites lying within country parks.
Table 3‑3 5-year-averaged Background Air Quality of Shatin
and Shum Shui Po Air Quality Monitoring Stations
Pollutants |
Shatin, Annual average (µg/m³) |
Sham Shui Po, Annual average (µg/m³) |
HKAQO (µg/m³) |
NO2 |
45 |
67 |
80 |
RSP |
52 |
55 |
55 |
TSP |
69 |
79 |
80 |
SO2 |
18 |
24 |
80 |
3.5 Construction Phase Impacts
Analysis of Construction Activities
3.5.1 The envisaged construction programme and activities have been presented in Appendix B.
3.5.2 The construction will begin with site clearance/ formation works at both portals. Following the site clearance/ formation works, there would likely to be a combination of mechanical, pneumatic or hydraulic splitting or expanding grout techniques employed for creation of both portals, while the tunnelling works will employ the use of Tunnel Boring Machine (TBM) starting from the outfall portal. Finally, the intake and outfall structures would be constructed together with the tunnel testing and commissioning.
Assessment Methodology
3.5.3 As the construction activities would be phased and are conducted mainly inside the tunnel, it is expected that, with implementation of dust suppression measures given in the Air Pollution Control (Construction Dust) Regulation and proposed mitigation measures mentioned in Section 3.5.9 below, no significant dust impact would be envisaged. A qualitative approach to evaluate the air quality impact induced by the construction of the Project is therefore adopted.
Identification of Potential Construction Dust Impact
3.5.4 It is expected that works at the portals could generate a small amount of dust during the construction activities mentioned above. Potential sources of dust emissions include those listed below and elaborate in the following paragraphs:
· site clearance/ formation works;
· loading, unloading and transfer of dusty materials;
· gaseous emissions from the construction vehicles and the operation of Powered Mechanical Equipment (PME);
· wind erosions from stockpiles of dusty materials; and
· transfer of dusty materials using a conveyor belt system.
3.5.5 The construction will begin with site clearance. This will be a regulatory works procedure that requires appropriate dust suppression measures under the Regulation to adequately control dust to within an acceptable level.
3.5.6 Site preparation may involve minor excavation, which is also regulatory work. Dusty material stockpiling and handling may also be possible, for which dust control measures will have to be implemented.
3.5.7 The works may also involve the use of trucks for material transport. Use of vehicles is a regulatory work procedure and the required dust control measures shall ensure dust levels are controlled to an acceptable level.
3.5.8 The conveyor belt system would be enclosed throughout the tunnel and end at the outfall portal for spoil disposal. Fugitive dust would be the potential air quality impact. However, the nearest ASR identified at Portal D is Lakeview Garden (A1) which is located at 200m away and with ~60m of vertical separation. No picnic areas are found in the vicinity of the site near the outfall portal. Hence, with the implementation of dust suppression measures in Section 3.5.9, the dust impact would be limited and no exceedance of dust level would be envisaged. The same situation also applies to the intake end, where the fugitive dust impact should be controllable.
Mitigation Measures for Fugitive Dust
3.6 Potential Cumulative Impacts due to Concurrent Works
3.6.1 The sections that could lead to potential cumulative air quality impact include: -
·
PWP Item No. 155CD -
· Agreement No. CE 77/2001 (GE) and 2/2006 (GE) – Slope Upgrading Works with no definite program; and
· The Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) – Hong Kong Section likely to commence in 2009.
3.6.2 However, as mentioned in Section 2.7, it is envisaged that given the physical distance separation, the LCK drainage tunnel will unlikely to affect common sensitive receivers of the IRTS. The XRL is all underground with substantial vertical separation with the proposed IRTS tunnel and the slope upgrading works would be relatively minor in nature, hence, the potential cumulative projects would unlikely to contribute significant impact to ASRs.
3.7 Environmental Monitoring and Audit Requirements
3.7.1 It is necessary to ensure proper implementation of the dust control measures as required under the Air Pollution Control (Construction Dust) Regulation. No specific construction dust monitoring is recommended, although environmental audits during the construction stage will be desirable to ensure proper implementation of air quality control measures.
3.8.1 Through proper implementation of dust control measures required under the Air Pollution Control (Construction Dust) Regulation by the works contractor, construction dust can be controlled at source to acceptable levels and hence no unacceptable impacts will be anticipated.
3.8.2 As the project does not require large-scale site formation or other major activities that could generate significant amount of fugitive dust, no specific construction dust monitoring is considered necessary, though on-site environmental audit is recommended to ensure proper implementation of dust control measures during the construction phase.
4.1.1 This section has evaluated and assessed the noise impact quantitatively using standard acoustic principles and has focussed on the construction phase only. The assessment has been based on the criteria and guidelines for evaluation and assessing noise impact as stated in Annexes 5 and 13 of the EIAO-TM and covered the scope outlined in Clause 3.4.2 of the EIA Study Brief.
4.2 Relevant Legislations, Standards & Guidelines
General Construction Activities during Non-Restricted Hours
4.2.1 Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) shall be assessed against the noise standards tabulated in Table 4-1 below.
Table 4‑1 Noise Standards for Daytime
Construction Activities
Noise Sensitive Uses |
0700 to 1900 hours on any day not being a
Sunday or general holiday, Leq (30 min), dB(A) |
All domestic premises including temporary
housing accommodation |
75 |
Hotels and hostel |
|
Educational institutions including
kindergarten, nurseries and all others where unaided voice communication is
required |
70 65 during
examination |
Source:
EIAO-TM, Annex 5, Table 1B - Noise Standards for Daytime construction
Activities
Note:
·
The
above noise standards apply to uses, which rely on opened windows for
ventilation
·
The
above standards shall be viewed as the maximum permissible noise levels
assessed at 1m from the external facade
·
The
above standards shall be met as far as possible. All practicable mitigation measures shall be
exhausted and the residual impacts are minimised
General Construction Activities during Restricted Hours and Percussive Piling during Anytime
4.2.2 Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the Noise Control Ordinance (“NCO”).
4.2.3 For carrying out of any general construction activities involving the use of any Powered Mechanical Equipment (“PME”) within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in Technical Memorandum on Noise from Construction Work Other Than Percussive Piling (GW-TM) under the NCO.
4.2.4 The use of Specified PME (“SPME”) and/or the carrying out of Prescribed Construction Work (“PCW”) within a Designated Area (“DA”) under the NCO during the restricted hours are also prohibited without a CNP. The relevant technical details can be referred to Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO.
4.2.5 Designated areas, in which the control of SPME and PCW shall apply, are established through the Noise Control (Construction Work Designated Areas) Notice made under Section 8A(1) of the NCO. According to the Designated Area defined under the NCO (with effective from 1 January 2009), none of the works area of this project will fall within these areas.
4.2.6 As such, the application for CNP for any general construction activities involving the use of any PME shall refer to the GW-TM only. However, the Contractor has the responsibility to check the latest status and coverage of the Designated Areas at time of construction of the project.
4.2.7 Also, percussive piling is only permitted when the Authority has granted a CNP. Technical Memorandum on Noise from Percussive Piling (PP-TM) under the NCO sets out the permitted hours of operation of percussive piling and Acceptable Noise Level (“ANL”) requirements, which are dependent on the level of exceedance of the Acceptable Noise Level (“ANL”). For this Project in particular, percussive piling is not considered necessary.
4.2.8 Regardless of any description or assessment made in this chapter, in assessing a filed application for a CNP the Authority will be guided by the relevant Technical Memoranda. The Authority will consider all the factors affecting their decision taking contemporary situations/ conditions into account. Nothing in this Report shall pre-empt the Authority in making their decisions, and there is no guarantee that a CNP will be issued. If a CNP is to be issued, the Authority may include any conditions they consider appropriate and such conditions are to be followed while the works covered by the CNP are being carried out. Failing to do so may lead to cancellation of the permit and prosecution action under the NCO.
Ground-borne Noise
4.2.9 Noise arising from general construction works during normal working hours is governed by the EIAO-TM under the EIAO as shown in Table 4-1. The Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM) under the NCO stipulates that noise transmitted primarily through the structural elements of building, or buildings, shall be 10 dB(A) less than the relevant ANLs.
4.2.10 Based on the same principle for the ground-borne noise criteria (i.e. ANL-10 dB(A) under the IND-TM), the ground-borne construction noise levels inside domestic premises and schools relying on open window for ventilation shall be limited to 65 dB(A) and 60 dB(A) respectively when compared to the EIAO-TM.
4.2.11 For daytime during general holidays and Sundays and all days during evening 1900-2300 hrs and nighttime during 2300-0700 the other day, the ground-borne construction noise level shall be limited to 10 dB(A) below the respective ANLs for the Area Sensitivity Rating appropriate to those NSRs affected by the Project. For NSRs close to both portals (i.e. intake and outfall ends), an Area Sensitivity Ratings of “A” is adopted as NSRs in both areas are low density residential area consist of low-rise buildings and are not influenced by major road traffic or industries. A summary of these criteria is given in Table 4-2 below:
Table 4‑2 Ground-borne Noise Criteria (Leq 30min, dB(A))
Ground-borne
Noise Criteria (1), dB(A) |
|||
Daytime
(0700-1900) except general holidays and Sunday |
Daytime
(0700-1900) during general holidays and Sundays and all days during Evening
(1900-2300 hrs) |
Night-time
(2300 – 0700 hrs) |
|
All domestic
premises including temporary housing accommodation |
65 |
50 |
35 |
Hotels and
hostel |
65 |
50 |
35 |
Educational
institutions including kindergarten, nurseries and all others where unaided
voice communication is required |
60 55 (during examination) |
50 45 (during examination) |
35 |
Notes:
(1) Noise descriptor for daytime noise is Leq (30min), others are Leq (5min)
4.3.1 Clause 3.4.2.2 (i) of the EIA Study Brief prescribed the Study Area to be those within 300m from the Project or other project alignments as identified in the EIA. Figure 4-1 and Figure 4-2 shows this study area (the 300m envelope) in details and the noise sensitive receivers (“NSRs”) within the area.
4.3.2 The representative NSRs are the first tier of most affected noise sensitive uses selected for the noise assessment to facilitate works planning and the implementation of necessary mitigation measures. Other NSRs further away from these first tier NSRs are expected to be less affected by comparison.
4.4 Noise Sensitive Uses (Air-borne and Ground-borne)
4.4.1 Noise sensitive receivers (NSRs) have been identified in accordance with Annex 13 of the EIAO-TM. The NSRs have included existing, planned/ committed noise sensitive developments and relevant uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department.
4.4.2 For purpose of this construction noise assessment, representative NSRs close to the site have been selected within the Study Area for prediction of the levels of noise impact. Selected representative existing NSRs are tabulated in Table 4-3 below and shown in Figure 4-1 and Figure 4-2.
Table 4‑3 Locations
of the Existing Representative NSRs for CNIA
NSR
ID. |
Description |
No.
of Floors |
Horizontal
Distance from tunnel alignment (m) |
Horizontal
Distance from portals (m) |
Nature
of Use |
Outfall End
(Portal D) |
|||||
LG |
Tower 1, |
1/F – 6/F |
200 |
200 |
Residential |
AV |
House A, |
G/F – 2/F |
290 |
290 |
Residential |
GTV |
House 17, Golden Time Villas |
G/F – 2/F |
295 |
295 |
Residential |
Intake End
(Portal A) |
|||||
VH |
Village House |
G/F – 1/F |
200 |
170 |
Residential |
4.4.3
As confirmed by WSD, the Tai Po Road Water Treatment
Works Staff Quarters will be vacated before the construction work
commences. Moreover, as confirmed by
CLP, the
4.4.4 No planned/ committed noise sensitive developments and relevant uses were found within the assessment area at the time of this Study.
4.5 Analysis of Construction Activities and Sources of Noise Impact
4.5.1 It is expected that works near the two portals and inside the tunnel can roughly be divided into several work stages and are given in Table 4-4. Figure 2-6 and Figure 2-7 show the locations of these two portals. The detailed construction programme has been given in Appendix B.
4.5.2 Except for tunnelling works, which the TBM will operate round the clock, all other construction activities will only be conducted during daytime, i.e. 0700-1900 on any day not being Sundays or general holidays unless there is a need to extend the working sessions to the restricted hours defined under the NCO. In such case, the Contractor will apply for CNP for the carrying out of the works.
Table 4‑4 Tentative Construction Schedule
Occurrence |
||||
Intake |
Outfall |
Tunnel |
||
1 |
Mobilization |
√ |
√ |
|
2 |
Site
Formation Works |
√ |
√ |
|
3 |
Portal/
Shaft Construction |
|
√ |
|
4 |
Setting up
of Tunnelling Equipment |
√ |
√ |
√ |
5 |
Tunnelling
Works |
√ |
√ |
√ |
6 |
Tunnel
Testing and Commissioning |
√ |
√ |
√ |
7 |
Construction
of intake and outfall structures |
√ |
√ |
|
4.5.3 To facilitate an estimate of the likely level of construction noise, an inventory of project-specific PME needed has been assumed and provided by the project engineer for each portals and tunnel inside were shown in Appendix B.
4.6 Assessment Approach & Methodology
Airborne Noise
4.6.1 Reference has been made to the approach given in the Guidance Note titled “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2004).
4.6.2
Also, as per EIAO-TM Annex 13, the assessment of
construction noise impact arising from works other than percussive piling has
been based on standard acoustic principles, and the guidelines given in GW-TM
issued under the NCO where appropriate.
Where no sound power level (“SWL”) can be found in the relevant TM,
reference has been made to BS 5228 Part I or noise emission levels measured for
QPME used in previous projects in
1. Assume a typical construction schedule as in Appendix B;
2. Assume a typical project-specific equipment inventory in Appendix B for each work stage together with the number and type of PME that are considered necessary for completing the works during the non-restricted hours;
3. Obtain from GW-TM, the Sound Power Level (SWL) for each PME assumed in the equipment inventory;
4. Adopt the worst-case plant inventory in each construction activities (i.e. a higher SWL) in case there are alternative plant inventory;
5. Select representative NSRs for the construction noise impact assessment in Table 4-3;
6. Calculate the unmitigated Predicted Noise Level (“PNL”) and correct it for facade reflection to obtain the Corrected Noise Level (“CNL”) at any NSRs as in Table 4-3;
7. Include screening effect for the NSRs near Outfall end (Portal D) where there are no direct line of sight to the construction activities;
8. If necessary, re-select typical project-specific silenced equipment and/ or erection of noise barrier and calculate the mitigated noise impact; and
9. Compare the mitigated CNL with the noise standards given in Table 4-1 to determine acceptability and the need for further mitigation/ EM&A.
Ground-borne Noise
4.6.3 Both TBM and a combination of mechanical, pneumatic or hydraulic splitting or expanding grout techniques will be used to excavate rock along the alignment. The interaction between the operation of equipments (hydraulic breaker and rock driller), the TBM and the rock will induce ground-borne noise. Potential ground-borne noise impacts on NSRs include the use of rock drill during the excavation at two portals, and the TBM along the tunnel alignment. The methodology for assessing the ground-borne noise impact has been used as follow.
4.6.4 The method used to predict construction ground-borne noise has been based on the U.S. Department of Transportation “High-Speed Ground Transportation Noise and Vibration Impact Assessment”, 1998. The vibration level Lv,rms at a distance R from the source is related to the vibration source level at a reference distance Ro. The conversion from vibration levels to ground-borne noise levels is determined by the following factors:
C dist Distance attenuation
C damping Soil damping loss across the geological media
C building Coupling loss into building foundation
C floor Coupling loss per floor
C noise Conversion factor from floor vibration levels to noise levels
4.6.5 The predicted ground-borne noise level Lp inside the noise sensitive room is given by the following equation.
Lp = Lv,rms + C dist + C damping + C building + C floor + C noise
Table 4‑5 Reference
Vibration Level based on Measurements
Construction Equipments |
Construction Site |
Vibration (RMS) at Reference Distance of 5.5m from source |
Drilling Rig |
|
0.536 mm/s |
Hydraulic Breaker |
TST site |
0.298 mm/s |
Source: Appendix 7-1 of KSL EIA
4.6.7 The vibration measurements for the TBM were extracted from the in-situ measurements during the bored tunnelling of Kwai Tsing Tunnel of the West Rail project. The geology consists of mainly granite, which is similar to the geology along the tunnel alignment (Ref: Section 3.2, Working Paper No. 3 – Evaluation of Construction Methods for the Water Transfer Tunnel). The measurements records above are considered the most appropriate available information for the purpose of assessing TBM ground-borne noise.
4.6.8 The geological profiles along the tunnel alignment are mainly hard rock. No soil damping loss has been assumed.
Coupling Loss into Building Structures
4.6.9 This represents the change in the incident ground-surface vibration due to the presence of the piled building foundation. The empirical values based on the guidance set out in the Transportation Noise Reference Book are given in following table.
Table 4‑6 Loss Factor for Coupling into Building
Foundation
Loss factor for coupling into building
foundation, dB |
Octave Band Frequencies, Hz |
|||||
16 |
31.5 |
63 |
125 |
250 |
500 |
|
Large building on Piles |
-6 |
-7 |
-11 |
-13 |
-14 |
-12 |
Single residences |
-6 |
-8 |
-8 |
-7 |
-5 |
-4 |
4.6.10 This represents the floor-to-floor vibration transmission attenuation. In multi-storey buildings, a common value for the attenuation of vibration from floor-to-floor is approximately 1dB attenuation in the upper floor regions at low frequencies and greater than 3dB attenuation at lower floors at high frequencies. Coupling loss of –1 dB reduction per floor has been assumed for a conservative assessment.
Conversion from Floor Vibration to Noise Levels
4.6.11 Conversion from floor vibration levels to indoor reverberant noise levels has been based on standard acoustic principles. The conversion factor is dependent on the surface area S of the room in m2, the radiation efficiency, s, the volume of the room V in m3 and the room reverberation time RT in seconds. Analyses were carried out for residential units and school in Appendix E with results summarised in the following table.
Table 4‑7 Conversion Factors from Floor
Vibration Levels to Indoor Reverberant Noise Levels
NSR type |
Conversion Cnoise (dB
re 1x10-6 mm/s) |
Residential Unit |
–27 |
School |
–24 |
4.7 Unmitigated Construction Noise Impacts (Airborne)
4.7.1 Based on the construction schedule in Table 4-4 and the assumed equipment inventory in Appendix B, the predicted highest construction noise impact for the unmitigated scenario amongst each construction stage has been summarised in Table 4-8 below with detailed calculations given in Appendix C.
Table 4‑8 Unmitigated Construction Noise Impact
NSR
ID. |
Nature
of Use |
Unmitigated
Noise Impact, dB(A) |
Noise
Criteria, dB(A) |
Compliance
of Noise Criteria? |
Outfall (Portal D) |
||||
LG |
Residential |
71 |
75 |
Y |
AV |
Residential |
67 |
75 |
Y |
GTV |
Residential |
67 |
75 |
Y |
Intake
(Portal A) |
||||
VH |
Residential |
75 |
75 |
Y |
4.7.2 The predicted unmitigated construction noise impacts at NSRs near both the intake and outfall end comply with the noise criteria, no specific mitigation measures at the intake and outfall end is required.
4.8.1 The results show that compliance of noise criteria was predicted no specific mitigation measure was recommended. Hence, no residual impact is predicted.
5. Noisy equipment and noisy activities should be located as far away from the NSRs as is practical;
7. Regular maintenance of all plant and equipment; and
4.8.3 By combining with properly designed EM&A requirements, construction noise impact could be controlled to within acceptable levels.
4.9 Potential Cumulative Impacts due to Concurrent Works
4.9.1 The sections that could lead to potential cumulative construction noise impact include: -
·
PWP Item No. 155CD -
· Agreement No. CE 77/2001 (GE) and 2/2006 (GE) – Slope Upgrading Works with no definite program; and
· The Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) – Hong Kong Section likely to commence in 2009.
4.9.2 However, as mentioned in Section 2.7, It is envisaged that given the physical distance separation, the LCK drainage tunnel will unlikely to affect common sensitive receivers of the IRTS. The XRL is all underground with substantial vertical separation with the proposed IRTS tunnel and the slope upgrading works would be relatively minor in nature, hence, the potential cumulative projects would unlikely to contribute significant impact to NSRs.
4.10 Ground-borne Noise Impact
4.10.1 Both TBM and a combination of mechanical, pneumatic or hydraulic splitting or expanding grout techniques will be used to excavate rock along the tunnel alignment. Rock excavation would take place at both portals during non-restricted hours, while the TBM would be 24-hour working for excavation of the underground tunnel. Different noise criteria for the activities have been selected as shown in Table 4-2 for comparison and check for compliance.
4.10.2 Detailed assessments have been conducted for both construction equipments (hydraulic breaker and rock driller) and TBM, the results are summarised in Table 4-9 to Table 4-11 below. Potential cumulative ground-borne noise impacts due to the overlapping of construction activities have also been assessed, the results are summarised in Table 4-10 below. The detailed assessment results were shown in Appendix E.
Table 4‑9 Highest Ground-borne Noise Impact by Various Construction Equipments (Daytime except Sundays and General holidays)
NSR
ID. |
Nature
of Use |
Ground-borne
Noise Impact, dB(A) |
Noise
Criteria during non- restricted hours, dB(A) |
Compliant
with Noise Criteria? |
||
Hydraulic Breaker |
Rock Driller |
TBM |
||||
Outfall (Portal D) |
||||||
LG |
Residential |
24 |
29 |
23 |
65 |
Y |
AV |
Residential |
22 |
27 |
21 |
65 |
Y |
GTV |
Residential |
22 |
27 |
21 |
65 |
Y |
Intake
(Portal A) |
||||||
VH |
Residential |
36 |
41 |
28 |
65 |
Y |
Table 4‑10 Cumulative Ground-borne Noise Impact (Daytime except Sundays and General holidays)
NSR
ID. |
Nature
of Use |
Ground-borne
Noise Impact, dB(A) |
Noise
Criteria during non-restricted hours, dB(A) |
Compliant
with Noise Criteria? |
Outfall
(Portal D) |
||||
LG |
Residential |
32 |
65 |
Y |
AV |
Residential |
30 |
65 |
Y |
GTV |
Residential |
30 |
65 |
Y |
Note: Possible cumulative ground-borne noise impact is due to
concurrent activities T2 (Rock Drill) and D2 (Rock Drill) which is in Outfall Portal
only (Appendix B refers)
Table 4‑11 Ground-borne Noise Impact by TBM (Nighttime 2300 – 0700 the next day)
NSR
ID. |
Nature
of Use |
Ground-borne
Noise Impact, dB(A) |
Noise
Criteria during nighttime, dB(A) |
Compliant
with Noise Criteria? |
Outfall (Portal D) |
||||
LG |
Residential |
23 |
35 |
Y |
AV |
Residential |
21 |
35 |
Y |
GTV |
Residential |
21 |
35 |
Y |
Intake
(Portal A) |
||||
VH |
Residential |
28 |
35 |
Y |
4.10.3 The assessment results shown in the above tables have demonstrated full compliance with the ground-borne noise criteria. Rock excavation activities at the two portals combined with tunnelling by TBM can comply with the noise criterion during the daytime period (0700 – 1900) except general holiday and Sundays. The ground-borne noise impact due to the use of TBM can also meet the most stringent criterion during the nighttime period (2300-0700) hours.
4.11 Environmental Monitoring and Audit (EM&A) Requirements
4.11.1 In order to ensure that the nearby NSRs will not be subjected to unacceptable construction noise impact, an Environmental Monitoring and Audit (EM&A) programme is recommended. Details on the noise monitoring requirements, methodology and action plans have been described in the accompanying EM&A Manual.
4.12 Evaluation of Constraints on Planned Noise Sensitive Development/ Land Uses
4.12.1 There are no planned noise sensitive developments or land uses found within the assessment area at the time of study, and hence no specific constraints have been established.
4.13.1 This construction noise impact assessment has been based on the best estimate of the construction sequence and machines inventory. The TBM is expected to operate 24 hours a day to maximise the resources and to complete the works under a tight time schedule. Other construction activities will cease during the restricted hours.
4.13.2 The potential noise impact that could arise from daytime construction activities of the Project has been evaluated. The assessment results show no exceedances of construction noise criteria at both the intake and outfall end were predicted in the unmitigated scenario. Hence, no residual noise impact has been predicted.
4.13.3 Potential ground-borne noise impacts during the construction phase have also been assessed. Results indicated that the noise levels predicted can satisfactorily meet the derived noise criteria for the daytime period and the statutory noise criteria during the nighttime period. No mitigation measures are considered necessary.
4.13.4 The Contractor shall, from time to time, be aware of the noise impacts on the surrounding NSRs through adequate noise monitoring during the works so that adjustments could be made to control the construction noise levels. These requirements should be triggered by an Event and Action Plan as part of the EM&A which should be incorporated into the works contract in order to make it enforceable.
5.1.1 This section presents an assessment of the potential water quality impacts associated with the construction of the proposed Inter-Reservoir Transfer Scheme (IRTS).
5.1.2
The assessment has been based on the criteria and
guidelines for evaluation and assessment of water quality impact stated in
Annexes 6 and 14 of the EIAO-TM and covered the scope outlined in
5.1.3 This Project involves the construction of a water tunnel linking the Kowloon Byewash Reservoir with the Lower Shing Mun Reservoir. Although the tunnel will be entirely underground, the portals construction on either ends will fall within the water gathering grounds of both reservoirs and hence water quality impact is a key issue.
5.1.4 The following sections will analyse the baseline situation, assess the potential impacts as well as recommend ways to avoid and control water pollution in the project areas.
5.2 Relevant Legislations, Standards & Guidelines
5.2.1
In carrying out the assessment, references have been
made to the following relevant
· Water Pollution Control Ordinance (“WPCO”) Chapter 358 (as amended by the Water Pollution Control (Amendment) Ordinance 1990 and 1993);
· Water Pollution Control (General) Regulations (as amended by the Water Pollution Control (General) (Amendment) Regulations 1990 and 1994);
· Water Pollution Control (Sewerage) Regulation;
· Water Quality Objectives (“WQOs”) for relevant Water Control Zones (“WCZs”);
· EIA Ordinance and EIAO-TM (Annexes 6 and 14);
· Waterworks Ordinance;
· WSD Conditions for Working within Water Gathering Grounds;
· Practice Note for Professional Persons ProPECC PN1/94, Construction Site Drainage
5.2.2
The Water
Pollution Control Ordinance (WPCO) (Cap. 358) enacted in 1980 is the
principal legislation for protection and control of water quality in
Table 5‑1 Water Quality
Objectives for
Parameters |
Objectives |
Sub-Zone |
Aesthetic Appearance |
Objectionable odours or discolouration of the
water not to be
present. |
Whole zone |
Tarry residues, floating wood, articles made of
glass, plastic, rubber or of any other substances not to be present. |
Whole zone |
|
Mineral oil or surfactants giving rise to a lasting foam not to be present. |
Whole zone |
|
Recognisable
sewage-derived debris not to be
present. |
Whole zone |
|
Floating, submerged and semi-submerged objects
of a size likely to interfere with the free movement of vessels, or cause
damage to vessels not to be
present. |
Whole zone |
|
Substances
which settle to form objectionable deposits not to be present. |
Whole zone |
|
Bacteria |
The level of E.coli not to exceed 1 per 100 mL, calculated as the geometric mean
of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days. |
Whole zone |
Colour |
Not to cause the
colour of water to exceed 30 Hazen units. |
Whole zone |
Dissolved Oxygen (DO) |
Not less than 4 mg/L. |
Whole zone |
pH |
Not to cause the pH of the water to exceed the range of 6.5-8.5. |
Whole zone |
Temperature |
Not to cause the
natural daily temperature range to change by more than 2 oC. |
Whole zone |
Salinity |
Not to cause the natural ambient salinity level to change by more than 10%. |
Whole zone |
Suspended Solids |
Not to cause the
annual median of suspended solids to exceed 20 mg/L. |
Whole zone |
Ammonia |
Un-ionized
ammoniacal nitrogen level not to exceed 0.021 mg/L, calculated as the annual
average (arithmetic mean). |
Whole zone |
5-day Biochemical
Oxygen Demand |
Not to exceed 3
mg/L. |
Whole zone |
Chemical Oxygen
Demand |
Not to exceed 15
mg/L. |
Whole zone |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in
humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains
and to interactions of toxic substances with each other. |
Whole zone |
Should not cause a
risk to any beneficial use of the aquatic environment. |
Source:
Cap. 358AJ, Statement of Water Quality Objectives (
5.2.3
The Technical Memorandum on Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM-DSS) issued under the WPCO
defines the acceptable discharge limits to the different types of receiving
waters (foul sewers, storm water drains, inland and coastal waters) in
5.2.4 The Technical Memorandum on Effluent Standards is a guide to the Authority under the Ordinance. It sets the limits that make effluents acceptable into foul sewers, storm water drains, inland and coastal waters. The limits control the physical, chemical and microbial quality of effluents. The standards apply to effluents through licences, which the Authority issues under sections 15, 16 and 20 of the Ordinance. The Authority is the Director of Environmental Protection.
5.2.5
Chapter 358AK, Part II – Section 8.2 of the WPCO
specifies that Group A inland waters include all waters in water gathering
grounds and within the boundaries of country parks. As the majority of the inland water bodies within the Study Area are waters in
water gathering grounds and within the boundaries of
5.2.6
The Waterworks Ordinance (WWO) is the
principal legislation for protection and control of waterworks in
5.2.7 Under Chapter 102, section 30 - (1) Any person who deposits, or causes or permits to be deposited, any solid or liquid matter in such a manner or place that it may fall or be washed or carried into water forming part of the waterworks shall be guilty of an offence. (3) No act shall be an offence under this section if it is done with the permission in writing of the Water Authority.
5.3.1 Paragraph 3.4.3.2 of the Study Brief specifies an assessment area for water quality impact to include all areas shown in “Appendix A” of the Study Brief.
5.3.2 As this EIA concerns the chosen tunnel alignment, the immediate affected areas within 500m of the Project are shown in Figure 5-1 and Figure 5-2 together with water sensitive receivers highlighted in blue. The assessment area has included other areas/ features such as stream courses and the associated water systems in the vicinity that could be impacted by the project.
5.4 Water Systems, Catchments and Water Sensitive Receivers
5.4.1
The Project works area comprises two sites, viz. the intake
and the outfall. The intake will be
located near the dam at the south western part of the Kowloon Byewash Reservoir
while the outfall will be located along the
5.4.2 Downstream of the intake end worksite drains into the Kowloon Byewash Reservoir, the lowest amongst all other members of the Kowloon Group of Reservoirs. When it is full, the Kowloon Byewash Reservoir will overflow to Tsuen Wan East and Kwai Chung, which falls within the catchment of Victoria Harbour Phase 1 Water Control Zone (“WCZ”)
5.4.3 For the outfall, overflow from the Lower Shing Mun Reservoir will go into the catchments of the Tolo Harbour Supplementary Water Control Zone.
5.4.4 Although the tunnel will be entirely underground, the portals and construction sites on either end will fall within the water gathering grounds of both reservoirs. During the construction phase, surface runoff and groundwater draining from the tunnel at the intake at the Kowloon Byewash Reservoir and the outfall at the Lower Shing Mun Reservoir will be diverted towards discharge points downstream of the Kowloon Byewash Reservoir Dam and Lower Shing Mun Reservoir Dam respectively. The runoff will be desilted before discharge.
5.4.5 The location of the water table within the project boundary and its distance to the proposed tunnel alignment are shown in Figures 5-3a-e.
5.4.6 The main water sensitive receivers (“WSRs”) in the vicinity of the work sites and those downstream are shown in Figure 5-1 and Figure 5-2 and listed below: -
Intake End - Kowloon Byewash Reservoir and streams
Outfall End - Lower Shing Mun Reservoir and streams
5.5 Baseline Water Quality and Water Quality Standards
5.5.1 The year-round raw water quality recorded regularly through routine water quality surveys at the Kowloon Byewash and Lower Shing Mun Reservoirs was obtained from WSD. The raw water quality of the Kowloon Byewash and Lower Shing Mun Reservoirs recorded in 2005 and 2006 are presented in Appendix F. The results indicated that the reservoir water quality was generally satisfactory.
5.5.2 As the project will not involve dredging of the reservoir and/ or disruption to the river/ stream bed, sediment quality is not of a concern in connection with construction of the Project.
5.5.3
The majority
of the inland water bodies within the Study Area are waters in water gathering
grounds and within the boundaries of
Table 5‑2 Standards for Effluents Discharged
into Group A Inland Waters
Flow rate (m3/day) Determinand |
≦10 |
>10 |
>100 |
>500 |
>1000 |
pH (pH units) |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
6.5-8.5 |
Temperature (℃) |
35 |
35 |
30 |
30 |
30 |
Colour (lovibond units) (25mm cell
length) |
1 |
1 |
1 |
1 |
1 |
Conductivity
(ms/cm at 20oC) |
1000 |
1000 |
1000 |
1000 |
1000 |
Suspended solids |
10 |
10 |
5 |
5 |
5 |
Dissolved oxygen |
≧4 |
≧4 |
≧4 |
≧4 |
≧4 |
BOD |
10 |
10 |
5 |
5 |
5 |
COD |
50 |
50 |
20 |
20 |
10 |
Oil & Grease |
1 |
1 |
1 |
1 |
1 |
Boron |
2 |
2 |
1 |
0.5 |
0.5 |
Barium |
2 |
2 |
1 |
0.5 |
0.5 |
Iron |
2 |
2 |
1 |
0.5 |
0.5 |
Arsenic |
0.05 |
0.05 |
0.05 |
0.05 |
0.05 |
Total chromium |
0.05 |
0.05 |
0.05 |
0.05 |
0.05 |
Mercury |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Cadmium |
0.001 |
0.001 |
0.001 |
0.001 |
0.001 |
Selenium |
0.01 |
0.01 |
0.01 |
0.01 |
0.01 |
Copper |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
Lead |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Manganese |
0.5 |
0.5 |
0.5 |
0.5 |
0.5 |
Zinc |
1 |
1 |
1 |
1 |
1 |
Other toxic metals individually |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Total toxic metals |
0.3 |
0.3 |
0.2 |
0.2 |
0.15 |
Cyanide |
0.05 |
0.05 |
0.05 |
0.05 |
0.02 |
Phenols |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Hydrogen sulphide |
0.05 |
0.05 |
0.05 |
0.05 |
0.05 |
Sulphide |
0.2 |
0.2 |
0.1 |
0.1 |
0.1 |
Fluoride |
1 |
1 |
1 |
1 |
0.5 |
Sulphate |
800 |
600 |
500 |
400 |
200 |
Chloride |
800 |
500 |
500 |
200 |
200 |
Total reactive phosphorus |
1 |
0.7 |
0.7 |
0.5 |
0.5 |
Ammonia nitrogen |
1 |
1 |
1 |
1 |
0.5 |
Nitrate + nitrite nitrogen |
15 |
15 |
15 |
10 |
10 |
E. coli (count/100 ml) |
<1 |
<1 |
<1 |
<1 |
<1 |
Note: (All
units in mg/L unless otherwise stated; all figures are upper limits unless
otherwise indicated)
5.6 Water Quality Assessment Methodology
5.6.1 To assess the potential impacts on water quality, a comprehensive desktop study covering the following aspects was carried out to:
· Identify WSRs which may be impacted by the proposed works and the assessment criteria to be complied with;
· Identify potential sources of water quality impacts that may be generated during the construction phase;
· Assess potential impacts upon the identified WSRs during the construction phase;
· Provide actions/remedial measures that need to be implemented to reduce impacts to acceptable levels and best site management practices; and
· Evaluate residual impacts and identify the requirements for preparation of an Environmental Monitoring and Audit Manual.
5.7 Identification and Evaluation of Water Quality Impact during the Construction Phase
Construction Activities and Sequences
5.7.1
The construction will begin with site clearance/
formation works at both portals.
Following the site clearance/ formation works, a combination of
mechanical, pneumatic or hydraulic splitting or expanding grout techniques
would be employed for the creation of both portals, while the tunnelling works
will employ the use of TBM starting from the outfall portal. Finally, the intake and outfall structures
would be constructed.
Construction Site Runoff and Drainage
5.7.2
Siltation
generated by different construction works can have a major impact on water
quality. Runoff from the construction
work areas may contain increased loads of sediments, suspended solids and
contaminants. Potential sources of
pollution from site drainage include:
· Runoff and erosion of exposed surfaces, accidental spillage from plant maintenance and material handling;
· Release of grouting and cement with rain wash;
· Wash water from dust suppression sprays; and
· Fuel and lubricants from maintenance of construction vehicles and mechanical equipment.
5.7.3 Non-point sediment laden runoff during the construction works for the IRTS, if uncontrolled, may carry pollutants (adsorbed onto the particle surfaces) into the Kowloon Byewash and Lower Shing Mun reservoirs. Associated effects which may arise include increased suspended solids concentrations in the receiving water bodies. Mitigation measures should be implemented to control construction site runoff and drainage from the works areas, and prevent runoff and drainage water with high levels of suspended solids from entering the Kowloon Byewash and Lower Shing Mun reservoirs.
5.7.4 With the implementation of adequate construction site drainage and provision of silt removal facilities as described in Section 5.10, adverse water quality impacts to the receiving water bodies is not anticipated.
General Construction Activities
5.7.5 On-site construction activities may cause water pollution from the following:
· Uncontrolled discharge of debris and rubbish such as packaging, construction materials and refuse; and
· Accidental spillage of liquids stored on site, such as oil, diesel and solvents etc. are likely to result in water quality impacts if they enter the adjacent watercourses or stormwater drains.
5.7.6 Good construction and site management practices should be observed, as detailed in Section 5.10, to ensure that litter, fuels and solvents doe not enter the Kowloon Byewash and Lower Shing Mun reservoirs and the local storm water drainage system.
Construction Workforce Sewage
5.7.7 Domestic sewage would be generated from the workforce during the construction phase. However, this temporary sewage can be adequately treated by interim sewage treatment facilities, such as portable chemical toilets, which could be installed within the construction site. It is unlikely that sewage generated from the site would have a significant water quality impact, provided that sewage is not discharged directly to the Kowloon Byewash and Lower Shing Mun reservoirs, local stream courses nor local storm water drainage system and chemical toilets are properly used and maintained.
Construction of Tunnel, Intake and Outfall
5.7.8 The main construction activities which have the potential to impact the water bodies at the intake and outfall of the IRTS tunnel are those which may result in the generation of silt. This is likely at the intake and outfall owing to the construction of the intake and outfall within rock.
5.7.9 Excavated spoil would be disposed of at the outfall portal. It will then be removed through road access at the outfall portal. Excavated spoil would be disposed of as construction and demolition (C&D) material to public fill reception facilities as discussed in Section 6.5. Excavated spoil would be transported within the tunnel by using a conveyor belt system that terminates at the outfall portal where the spoil would be immediately transported away by trucks or unloaded to a temporary stockpile area during the nighttime period. The conveyor belt system should be properly enclosed to prevent dispersion and dropping of material during the transportation process.
5.7.10 If not controlled properly, suspended solid run-offs and nutrient loadings may increase and enter the reservoirs due to the increase of site exposure, reducing light penetration and adversely affecting water quality in the reservoirs. However, with proper handling and disposal procedures, negative impacts from this source will be minimized.
5.7.11 For the major construction works to be carried out at the intake and outfall portals, their potential impacts on the water quality would depend on the nature of the materials excavated and the runoff that can enter the receiving water bodies. Surface run-off and effluent from the construction sites at the intake at Kowloon Byewash Reservoir and outfall at the Lower Shing Mun Reservoir would be directed towards adequately designed sand/silt removal facilities such as sand/silt traps and sediment basins to remove sand/silt particles from runoff to meet the requirements of the TM standards under the WPCO before discharging to discharge points downstream of the Kowloon Byewash Reservoir Dam and Lower Shing Mun Reservoir Dam respectively as shown in Figure 5-4 and Figure 5-5. Other pollutants, such as oil and grease, may also be present in the runoff where they may flow over the storage or maintenance areas. With the proper implementation of mitigation measures and good site practices, no significant impact to the water quality would be expected.
5.7.12 Rock will be encountered in most sections of the proposed tunnel which might require more frequent maintenance of the TBM cutter head. Recycle water will also be required for the cooling of the cutter head during boring. All discharge will be conveyed to desilting facilities for treatment prior to proper discharge.
5.7.13 Based on the available geological information, the proposed raw water tunnel will be mainly bored through hard rock (Grade II/III). With such geological conditions, a hard rock TBM will most likely be adopted for the tunnelling works. Such a TBM will have minimal water quality impacts as no chemicals or other agents will be used for cooling or lubricating the cutter head of the TBM.
5.7.14 Ground water ingress into the tunnel may be encountered during the construction which is undesirable and may cause downtimes to the project. During the progress of tunnel boring, the groundwater inflows will be carefully controlled by pre-injection grouting where necessary. The pre-injection grouting involves the grout injection works in front of the tunnel face during boring of the tunnel, for sealing a limited area around the tunnel with a grout of a suitable strength for controlling the potential groundwater inflows. The pre-injection grouting method will be supplemented by post-injection grouting where necessary to further enhance the groundwater inflow control. With the use of pre-injection with post-injection grouting, the groundwater inflows will be limited and under control. Any intrusion of groundwater during and after execution of advance probing of the TBM is therefore insignificant to affect the water table and the effect of the tunnel project on the ground water system will therefore be minimal.
5.7.15 During tunnelling works, ground water ingress pumped out from the tunnel would have a high content of SS. The water pumped out from the tunnel may be contaminated by grouting materials that would be required for the construction of the bored tunnel (for tunnel boring and groundwater treatment). On-site treatment would be required prior to off-site discharge.
5.7.16
With implementation of mitigation measures, no
significant impact to nearby WSRs is expected.
Sections of tunnel alignment would be underneath
5.8 Project-Related Pollution Sources and Cumulative Impact Implications
5.8.1 Planned projects that could lead to potential cumulative construction water quality impact include: -
·
PWP Item No. 155CD -
· Agreement No. CE 77/2001 (GE) and 2/2006 (GE) – Slope Upgrading Works with no definite program; and
· The Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) – Hong Kong Section likely to commence in 2009.
5.8.2 Given that the LCK drainage tunnel is on the downstream side of the Project, it should unlikely affect the WSRs of the IRTS. The XRL is all underground with substantial vertical separation with the proposed IRTS tunnel and the scale of the slope upgrading works would be relatively minor in nature, hence, cumulative water quality impact is not anticipated.
5.9 Water Quality Impact during the Operational Phase
5.9.1 No water quality impact is envisaged for transfer of raw water between reservoirs in the operational phase.
5.10 Water Pollution Mitigation and Management
Construction of Desilting Facilities
5.10.1
Construction
for the desilting facilities at intake
and outfall portals should be carried out behind a temporary cofferdam which is watertight enclosure built in the
reservoirs and pumped dry to expose the bottom so that construction of intake
and outfall portals could be undertaken.
5.10.2
The
cofferdam is composed of steel pilings driven into the slope surface of the
reservoir to form a watertight structure around the intake and outfall work
sites to prevent excavated materials from getting into the reservoirs. The cofferdams should remain on site until
completion of intake and outfall portals and tunnel construction.
5.10.3
The cofferdams should be regularly inspected and
maintained to ensure no spillage of waste or wastewater into the
reservoirs. Indicative locations of the
cofferdams are shown in Figure
2-6 and Figure 2-7
respectively.
Stormwater Point and
5.10.5 Construction runoff will be managed as per the Practice Note for Professional Persons ProPECC PN1/94 - Construction Site Drainage and the conditions of working within Water Gathering Grounds stipulated by WSD.
5.10.6 A Drainage Management Plan should be prepared by the Contractor for approval by the Engineer for each of the works areas, detailing the facilities and measures to manage pollution arising from surface runoff from those works areas.
5.10.7 An Emergency Contingency Plan should also be prepared by the Contractor, detailing the response and procedures to contain and remove any accidental spillage along the temporary and permanent roads and at the site at short notice to prevent or minimize the quantities of contaminants from reaching the reservoirs and local streams leading to the reservoirs. The Emergency Contingency Plan should be submitted to the Engineer for approval.
Construction Site Runoff and Discharge
1. Surface run-off and effluent from the construction sites at the intake at Kowloon Byewash Reservoir and outfall at the Lower Shing Mun Reservoir will be directed towards adequately designed sand/silt removal facilities such as sand/silt traps and sediment basins to remove sand/silt particles from runoff to meet the requirements of the TM standards under the WPCO before discharging to discharge points downstream of the Kowloon Byewash Reservoir Dam and Lower Shing Mun Reservoir Dam respectively as shown in Figure 5-4 and Figure 5-5. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the retention time for silt/sand traps should be 5 minutes under maximum flow conditions. Sizes may vary depending upon the flow rate, but for a flow rate of 0.1m3/s a sedimentation basin of 30m3 would be required and for a flow rate of 0.5m3/s the basin would be 150m3. The detailed design of the sand/silt traps should be undertaken by the contractor prior to the commencement of construction;
6. Where possible, works entailing soil excavation will be minimized during the rainy season (i.e. April to September). If excavation in soil could not be avoided in these months or at any time of year when rainstorms are likely, for the purpose of preventing soil erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided (e.g. along the crest/edge of excavation) to prevent storm runoff from washing across exposed soil surfaces. Arrangements should always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm;
8. Where surface runoff or construction effluent is likely to be contaminated with oil, properly designed and maintained petrol interceptor will be provided to meet the WPCO/TM-DSS requirements. Oil leakage or spillage shall be contained and cleaned up immediately. Detailed design of the petrol interceptor shall be provided by the Contractor before commencement of construction;
9. Sewage arising from the construction workers on site should be collected by temporary sanitary facilities e.g. portable chemical toilets. Portable toilets should be used coupled with tankering away services provided by a licensed collector;
Construction of Tunnel, Intake and Outfall
Maintenance of Tunnel and Oufall
17. Existing on-site silt removal facilities, channels and manholes, if any, would be maintained such that the deposited silt and grit will be removed regularly, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times;
18. Desilting facilities should be checked and the deposited silt and grit should be removed regularly to ensure they are working properly at all times;
Protection against Accidental Spillage
19. The project may occasionally involve the handling of fuel and generates chemical wastes. It must be ensured that all fuel tanks and chemical storage are sited on sealed and bunded areas, provided with locks and located outside water gathering grounds as far as practicable;
20. The storage areas will be surrounded by bunds with a capacity equal to 110% of the storage capacity of the largest tank to prevent accidentally spilled oil, fuel or chemicals from reaching the receiving waters;
22. Chemical waste arising from the site should be properly stored, handled, treated and disposed of in compliance with the requirements stipulated under the Waste Disposal (Chemical Waste) (General) Regulation.
5.11 Evaluation and Quantification of Residual Impacts
5.11.1 With the implementation of recommended mitigation measures for the construction phase of the proposed Project, no unacceptable water quality impacts are anticipated.
5.11.2 The water discharge from the site is subject to control by the WPCO. The Contractor should obtain a water discharge license before commencement of construction who is obliged to comply with the standards set out in the license which specifies the maximum allowable limits for the parameters of concern in the discharge. The Contractor is also responsible to design, operate and monitor the performance of any on-site treatment system.
5.12 Environmental Monitoring and Audit Requirements
5.12.1 Monitoring of water quality should be carried out during the construction phase at the intake and outfall portals at the discharge points after the desilting facilities. It is also recommended that regular site audits be undertaken to inspect the construction activities at all works areas to ensure the recommended mitigation measures are properly implemented.
5.13 Conclusion and Recommendations
5.13.1 This assessment has identified how tunnel excavations and the construction of the intake and outfall structures may affect the water quality. While minor and short term impacts to water quality could arise directly from these construction activities and from the surface runoff, these impacts could be adequately controlled by complying with the WPCO standards through implementation of recommended mitigation measures, in particular, desilting facilities and good site management practices.
5.13.2 With the implementation of the recommended mitigation measures and management practices, it is anticipated that the impacts upon the WSRs during the construction phase of the Project would be temporary and minimal. An environmental monitoring and audit programme in respect of water quality issues during the construction phase of the Project I is also recommended to monitor the compliance with acceptable levels of water quality indicators and to ensure the proposed mitigation measures are effectively implemented.
6.1.1
This assessment was based on the criteria and
guidelines stated in Annexes 7 and 15 of the EIAO-TM for evaluating and
assessing waste management implications and has covered the scope outlined in
6.1.2 A review of the Project has suggested that the prime source of wastes generated will be largely connected with the construction phase. During the operational phase, no significant waste generation is expected.
6.2 Relevant Legislations, Standards & Guidelines
6.2.1
In carrying out the assessment, reference has been made
to the following relevant
· The Waste Disposal Ordinance (Cap. 354) and subsidiary legislation such as the Waste Disposal (Chemical Waste) (General) Regulation that set out requirements for the storage, handling and transportation of all types of wastes.
· Dumping at Sea Ordinance (Cap. 466);
· Land (Miscellaneous Provisions) Ordinance (Cap 28).
· Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Annexes 7 and 15;
· Public Health and Municipal Services Ordinance (Cap 132) – Public Cleansing and Prevention of Nuisance Regulation – control of disposal of general refuse.
6.2.2
Other relevant documents and guidelines that are also
applicable to waste management and disposal in
· ETWB Technical Circular (Works) No. 19/2005, Environmental Management on Construction Sites;
· ETWB Technical Circular (Works) No. 31/2004 Trip-ticket System for Disposal of Construction and Demolition Materials;
· ETWB Technical Circular (Works) No. 22/2003A, Additional Measures to Improve Site Cleanliness and Control Mosquito Breeding on Construction Sites;
· ETWB Technical Circular (Works) No. 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness;
· ETWB Technical Circular (Works) No. 33/2002, Management of Construction and Demolition Material Including Rock;
· Practice Note for Authorised Persons and Registered Structural Engineers 243: Construction and Demolition Waste
6.3 Analysis of Activities & Waste Generation
6.3.1 In order to assess the impacts associated with waste generation, it is necessary to determine the different categories of wastes that will be generated by the Project at various stages.
6.3.2 During the construction phase, the main types of wastes that will be generated include:
· Vegetation and C&D materials from clearance;
· C&D materials from levelling, excavation, slope works and retaining structure, portals creation;
· C&D materials from tunnelling;
· C&D materials, chemical wastes from machineries and general refuse from work force
6.4 Waste Management Hierarchy
6.4.1 The waste management strategy is based on the following key elements in descending order of priority in carrying out the assessment and in developing relevant mitigation measures: -
· Avoidance;
· Reduce;
· Reuse/ Recycle;
· Bulk Waste Reduction; and
· Disposal.
6.4.2 Opportunities for reducing waste generation have been evaluated in the course of the assessment to:
· Avoid or minimise the generation of waste where possible during the planning/ design stage;
· Adopt better site management practices in materials control and promote on-site sorting of Construction and Demolition (“C&D”) materials, where practicable, during the construction stage, and;
· Explore the potential for reuse/ recycling of materials (e.g. “C&D” materials), e.g. consideration may be given to the possible use of excavated Grade II granite spoil for aggregate/ concrete production.
6.4.3 The types and quantities of residual wastes requiring disposal have been estimated together with the disposal options identified in this assessment in Table 6-1. The disposal options have considered the existing and future spare capacities of the waste disposal facilities and the environmental implications of handling, collection and disposal of waste materials.
6.5 Impact Assessment and Evaluation
Construction Wastes Types
Construction Wastes
6.5.1 Based on the design of the Project, the following types of construction wastes will be expected: -
· Site clearance waste (vegetation)
· Inert C&D wastes from tunnelling works
· Waste metal (off cuts) from in-situ concrete casting work
· Spent concrete
· Materials and equipment wrappings
· General refuse from site staff
6.5.2 It is envisaged that site clearance and tunnelling works will generate the greatest amount of wastes as presented in Table 6-1. All C&D materials generated on site will be sorted into inert (public fill) and non-inert (C&D wastes) wastes. Where possible, reuse of these materials on-site will be identified and implemented as far as practicable to minimise material volumes requiring disposal at landfill and public fill reception facilities.
6.5.3 It is envisaged that the creation of portals and re-profiling/ construction of the intake and outfall ends can absorb some inert C&D materials. However, tunnelling works will generate the largest amount of surplus materials requiring disposal at a rate of 7.5m3 per hour based on an assumption of 0.6m per hour (100m/week) advancing rate and 12.57m3 created per m of tunnel.
6.5.4 It is estimated that approximately 150m3 C&D materials will be generated by TBM excavation during the hours of 19:00 to 07:00 the next day, when disposal by dump trucks is banned for noise considerations. This will happened during Month 9-17 and will last for about 9 months. Soil/rock spoil generated by TBM excavation should be removed out of water gathering grounds as soon as possible.
6.5.5 In any case, construction waste of these types should not cause any significant nuisances/ impact on the environment in their handling, storage and disposal provided that proper mitigation measures are implemented. Appropriate measures such as covering the truckload by tarpaulin sheet should be in place to minimise wind blown litter and dust during transportation.
6.5.6
The disposal trip rate is expected to be less than 2
trucks per hour on average. For disposal
of inert C&D materials, the nearest outlet is at Tuen Mun Area 38. The trucks should follow local main roads to
the
Chemical Waste
6.5.7 Plant and vehicle maintenance will generate a small amount of chemical wastes during the construction period. Typically they include: -
· Solid wastes (empty fuel/ lubricant drums, used oil/air filters, scrap batteries, brake clutch linings which may contain asbestos); and
· Liquid wastes (waste oils/ grease, spent solvents/ detergents, which may be halogenated, and possibly spent acid/ alkali from battery maintenance).
6.5.8 The volume of chemical waste will depend upon the total number of plant / vehicles and how much maintenance is actually required to be carried out on site.
6.5.9 However based on the proposed plant list given Appendix B, it is unlikely that the volume of chemical waste will exceed 100 litres/ month all chemical wastes are to be disposed of outside water gathering grounds as soon as possible. Given the small quantities anticipated, provided the waste is properly handled, stored and disposed of outside water gathering grounds as soon as possible, no unacceptable impact will be expected.
General Refuse
6.5.10 The construction workforce will generate a small amount of refuse such as waste papers, plastic packaging and possibly food wastes. Such refuse will generally be collected on-site and brought to the nearby refuse collection point (RCP).
6.5.11 Prior to disposal off-site, such wastes will have to be temporarily put in suitably covered storage area where it will have to be regularly cleaned and maintained to avoid attracting vermin and pests. Any refuse storage area in water gathering grounds should be located away from any watercourses as far as possible and be covered in such a way as to prevent litter from being blown out of it by wind. With proper on-site handling and storage as well as regular disposal of these wastes to the nearby refuse collection points, no adverse impacts will be envisaged.
Sewage
6.5.12 The construction work force will generate sewage on a daily basis and requires proper disposal. It is anticipated that chemical toilets shall be provided on-site for the workforce and should be located away from any watercourses as far as possible, in which case night soil will need to be collected by an approved contractor for disposal on a regular basis to avoid odour issues.
6.6 Summary of Estimated Quantities of Wastes that could be Generated
6.6.1 Based on the assessment above, the amount of wastes generated for each waste type has been estimated and presented in Table 6-1 below.
6.6.2 In general, the inert portion of C&D materials should be disposed of to public fill reception facilities while the non-inert portion should be sent to landfill for disposal. Any potential for reuse of materials on site should be explored prior to disposal. The estimated quantities of each type of inert C&D materials to be generated, reused and disposed off site are summarized in Table 6-2.
Table 6‑1 Summary of Wastes Generation during the
Construction Phase
Activity |
Material Type |
Likely time of arising |
Estimated Total Amount |
Disposal / Treatment Site |
Site D –
Portal/ Starter Tunnel Construction (Construction Period = 9 months) |
||||
Site clearance & formation |
Non-inert
C&D materials |
Month 1-7 |
100 ton |
Nearest landfill, e.g. the NENT Landfill |
Inert C&D materials |
Month 1-7 |
1,800 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
|
Portal/ starter tunnel works |
Soil/ rock and C&D materials |
Month 8-9 |
1,900 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
Site D –
Outfall Structure Construction
(Construction Period = 5 months) |
||||
Scaffoldings & Superstructure works |
Non-inert
C&D materials |
Month 19-23 |
50 ton |
Nearest landfill, e.g. the NENT Landfill |
Inert C&D materials |
Month 19-23 |
1,680 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
|
Site A –
Portal/ Intake Connection and Tunnel Construction (Construction Period = 5 months) |
||||
Site clearance, access road & site formation |
Non-inert
C&D materials |
Month 1-2,
8-10 |
100 ton |
Nearest landfill, e.g. the NENT Landfill |
Inert C&D materials |
Month 1-2,
8-10 |
200 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
|
Mined Tunnel |
Soil/ rock and C&D materials |
Month 10-12 |
800 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
Site A –
Intake Structure Construction
(Construction Period = 2 months) |
||||
Scaffoldings & Superstructure works |
Non-inert
C&D materials |
Month 17-18 |
50 ton |
Nearest landfill, e.g. the NENT Landfill |
Inert C&D materials |
Month 17-18 |
420 m3 |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
|
Main Tunnel
Excavation & Lining Construction (by TBM method) (a 3.0m ID tunnel)
(Construction Period = 9 months) |
||||
|
Soil/ rock |
Month 9-17 |
37,000m3 or 12.57m3 per m |
Nearest public fill reception facilities e.g.
at Tuen Mun Area 38 |
General
Works |
||||
General works |
General refuse arising from works |
Throughout construction |
300 kg/week |
Nearest RCP |
Chemical waste arising from machineries |
Throughout construction |
100 litre/month |
Chemical Waste Treatment Centre |
|
General refuse (generated by site staff) |
Throughout construction |
100 kg/week |
Nearest RCP |
Table 6‑2 Estimated quantities of each type of inert C&D materials generated
Inert C&D material |
Volume (m3) |
|||||
|
|
Generated |
Reused on site |
Disposed off site |
||
Rock |
|
38,400 |
0 |
|
38,400 |
|
Soil |
|
5,380 |
150 |
|
5,230 |
|
Broken concrete |
20 |
0 |
|
20 |
|
|
Total |
|
43,800 |
150 |
|
43,650 |
|
6.7 Waste Management Practice during the Construction Phase
6.8 Waste Management Practice during the Operational Phase
6.8.1 Insignificant amount of silt in the stilling basins at the outfall end of the IRTS tunnel would need to be removed regularly. This should not present any difficulties or insurmountable problems during the operation phase.
6.9 Environmental Monitoring and Audit Requirements
6.9.1 The assessment has concluded that proper handling, storage, collection, transportation and disposal of waste materials generated during construction of the project will not give rise to any significant impacts to nearby sensitive receivers.
6.9.2 Whilst no specific environmental monitoring requirements are considered necessary, it is recommended that during the construction phase, site inspections and supervisions of waste management procedures and auditing of the effectiveness of implemented mitigation measures should be undertaken on a regular basis (e.g. weekly as a minimum). These tasks shall be scheduled in the Waste Management Plan (WMP) to be prepared by the Contractor, and a summary of the site audits shall be presented in the monthly EM&A reports required under the EM&A Manual.
6.9.3 Given the nature of the project, there are no specific EM&A requirements for waste management considered necessary during the operational phase.
6.10 Conclusion and Recommendations
6.10.1 The potential impacts of wastes arising from the construction and operational phases of the project have been assessed. The construction activities associated with the proposed works will generate a variety of wastes including vegetation from site clearance, excavated materials, and construction wastes, chemical and municipal wastes.
6.10.2 The largest amount of waste expected would be inert C&D materials, which will be generated by tunnelling works during Month 12-17 for around 6 months. The total inert C&D materials expected for the entire project are about 43,800 m3 and that due to tunnelling is estimated as 37,000 m3. 43,650 m3 of the total inert C&D materials will be disposed of at the nearest public fill reception facilities.
6.10.3 In view of the Government policy towards promotion recycling and due to the clear environmental benefits this will provide, recycling and waste reduction by site staff/ contractors (construction phase) should be encouraged whenever it is possible.
6.10.4 While an estimate has been made on the likely volumes and types of waste to be generated from the construction of the project, the Contractor should regularly update and submit the monthly Waste Flow Table (“WFT”) which would provide a more accurate estimate on volumes of waste generation on-site. This WFT shall form part of the Waste Management Plan (“WMP”) to be submitted as part of the EM&A requirements and in accordance with ETWB Technical Circular (Works) No. 19/2005, Waste Management on Construction Sites.
6.10.5 Provided that the waste management practices outlined are put in place, potential impacts on the environment associated with waste generated during the construction phases of the Project should be well under controlled.
7.1.1
The Hazard to Life assessment has to be based on the
criteria and guidelines stated in Annexes 4 of the EIAO-TM for evaluating and
assessing hazard and to follow the scope outlined in
7.1.2 As indicated in the Study Brief, hazard to life can attribute to the following two sources, viz.
· Possible use of explosives for tunnelling works
· Transport, storage and use of chlorine for disinfection of water at the Shek Lei Pui Water Treatment Works (“SLPWTW”)
7.1.3 The intake work site as shown in Figure 7-1 will be within the 1km consultation zone of the SLPWTW, which is a potentially hazardous installation (“PHI”) defined by Co-coordinating Committee on Land Use Planning & Control relating to potentially hazardous installations (“CCPHI”).
7.1.4 As outlined in Section 2.6.3, the use of explosives has been ruled out due to proximity of the tunnelling works to the Lower Shing Mun Reservoir dam. As such, explosive hazard assessment is not to be carried out.
7.1.5 Due to construction requirements, the Shek Lei Pui WTW will be temporarily taken out of service as the construction of the intake portal and TBM retrieving would require the water at the Kowloon Reception Reservoir and the Kowloon Byewash Reservoir to be temporarily drawn down, If Kowloon Reception Reservoir and Kowloon Byewash Reservoir are required to be drawn down to facilitate the construction works, both Shek Lei Pui WTW and Tai Po Road WTW are required to be shut down. The yield of Kowloon Group Reservoirs could not be fully utilized. Therefore, it is advisable for Contractor to plan the construction works taking into account of seasonal effects as far as practicable to minimize loss of yield.
7.1.6 The relatively lower capacity of water treatment at SLPWTW can easily be compensated by other water treatment works and hence would not cause unacceptable disruption to treated water supply to the area.
7.1.7 Suspension of water treatment at the SLPWTW will be accompanied by relocation of all chlorine drums before the construction works and hence remove hazard due to transport, storage and use of chlorine at SLPWTW. However, it is recommended that the inventory of chlorine should be phased out by natural consumption at SLPWTW before the construction works commence, which could eliminate the risk of chlorine drum relocation.
7.1.8 On account of the foregoing, no hazard to life assessment is considered necessary as the two hazard sources will be removed.
8.1.1 This section presents an assessment of the ecological impacts arising from construction and operation of the Project. Field surveys covering a period of more than 4 months (October 2007 to February 2008) have been undertaken to establish the baseline ecological conditions of the Study Area. The assessment has been based upon the criteria and guidelines for evaluating and assessing ecological impact stated in Annexes 8 and 16 of the EIAO-TM and covered the scope outlined in Section 3.4.6 of the EIA Study Brief.
8.2 Relevant Legislations, Standards & Guidelines
8.2.1 A number of international conventions and local legislation and guidelines provide the framework for the protection of species and habitats of ecological importance. Those relating to the Project are:
· Forests and Countryside Ordinance (Cap 96);
· Wild Animals Protection Ordinance (Cap 170);
· Country Parks Ordinance (Cap 208);
· Protection of Endangered Species of Animals and Plants Ordinance (Cap 586);
· Town Planning Ordinance (Cap 131);
· The Technical Memorandum on Environmental Impact Assessment Process under the Environmental Impact Assessment Ordinance (EIAO-TM); and
·
8.2.2 The Forests and Countryside Ordinance (Cap. 96) prohibits felling, cutting, burning or destroying of trees and growing plants in forests and plantations on Government land. The subsidiary Forestry Regulations prohibit the picking, felling or possession of listed rare and protected plant species. The list of protected species in Hong Kong which comes under the Forestry Regulations was last amended on 11 June 1993 under the Forestry (Amendment) Regulation 1993 made under Section 3 of the Forests and Countryside Ordinance.
8.2.3 Under the Wild Animals Protection Ordinance (Cap.170), designated wild animals are protected from being hunted, whilst their nests and eggs are protected from disturbance, destruction and removal. All birds and most mammals including all cetaceans are protected under this Ordinance, as well as certain reptiles, amphibians and invertebrates. The Second Schedule of the Ordinance that lists all the animals protected was last revised in June 1992.
8.2.4
The Country Parks
Ordinance (Cap. 208) prohibiting or restricting the killing, hunting,
trapping, molesting or disturbance of any form of wild life within a country
park or special area, the taking of, destruction of or interference with
vegetation within a country park or special area or the doing of anything
therein which will interfere with the soil.
It also prohibits or restricts any lighting of fires within a country
park or special area and the prevention of fire hazards. The study area fall within the
8.2.5 The Protection of Endangered Species of Animals and Plants Ordinance (Cap.586) was gazetted on 10 March 2006 and effective in December 2006 to replace the Animals and Plants (Protection of Endangered Species) Ordinance (Cap. 187) which gives effect to CITES. The Ordinance aims to regulate the import, introduction from the sea, export, re-export and possession or control of certain endangered species of animals and plants and parts and derivatives of those species and to provide for incidental and connected matters.
8.2.6 The Town Planning Ordinance (Cap. 131) provides designation of land use zoning such as “Coastal Protection Areas”, “Sites of Special Scientific Interest (SSSIs)”, “Green Belt” and "Conservation Areas” to promote conservation and protect significant habitats.
8.2.7 Annex 8 and 16 of the EIAO-TM: Annex 8 recommends the criteria that can be used for evaluating ecological impacts. Annex 16 sets out the general approach and methodology for assessment of ecological impacts arising from a project or proposal, to allow a complete and objective identification, prediction and evaluation of the potential ecological impacts.
8.2.8
8.3.1 Assessment methodologies were prepared in accordance with the technical requirements set out in Annexes 8 and 16 of the EIAO-TM and Study Brief ESB-154/2006, relevant EIAO Guidance Notes (GNs) regarding Ecological Impact Assessment (EcoIA) which include GN 6/2002, GN 7/2002 and GN 10/2004. The study area of the EcoIA covered all the habitats within a 500m boundary of the works, with focus to area around the proposed intake and outfall portals (Figure 8-1). Terrestrial ecological surveys mainly included plantation woodland/secondary woodland and flora/ fauna species depending on these habitats, while aquatic ecological surveys covered the reservoirs, the feeding streams and aquatic wildlife.
8.3.2 Ecological surveys were conducted from September to December 2007 and January to February 2008 covering both the wet and dry seasons for more than four months.
Habitat Survey
8.3.3 Aerial photos covering the Study Area have been studied to identify the general land use/ habitat type of the study area. A preliminary habitat map was generated through translating the visualized condition in the aerial photos for the subsequent ground truthing exercise.
8.3.4 The preliminary habitat map was finalised by ground truthing which verified and confirmed the habitat types and their boundaries (Figure 8-2 and Figure 8-3).
8.3.5 The finalised habitat map with suitable scale (1:1000 to 1:5000) showing the types and locations of habitats was overlaid with project alignment for further assessment.
Vegetation Survey
8.3.6 Vegetation surveys were carried out on 21, 24, 25 September 2007; 25, 29 ,31 October 2007; 2, 15, 16 November 2007; 5, 14, 17 December 2007; 3, 4, 7 January 2008 and 5, 6, 12 February 2008 by walking through habitats in the study area and recording plant species encountered by visual observation. Attention was paid to habitats of higher ecological value and to rare, protected and threatened plant species. Plant species list with plant status, form, relative abundance and location recorded was produced.
Mammal Survey
8.3.7 Mammal surveys were conducted in conjunction with herpetofauna surveys during daytime and at night time just after dusk. All sighting and sign of traits (footprints, faeces or burrows) were recorded. The secondary woodland / plantation woodland, grassland, muddy area adjacent to the streams were actively searched for mammal tracks where animals come to feed or drink. Feeding signs such as partially eaten vegetation or carcasses may provide evidence of traits of mammals. Habitat types, measurement and photographs were taken for signs of tracks to aid the identification works. Ad hoc sighting during other faunal group surveys was marked to produce a full species list. Nomenclature for mammals follows Shek (2006).
8.3.8
Mammal surveys were conducted on 25 and 31 October, 3
and 14 December 2007 and 15 January 2008 at
8.3.9 Night survey was conducted to search for nocturnal species of mammals on 31 October 2007. Hand or head torches were used to assist active searching in exposed areas of their potential habitats.
Bird Survey
8.3.10 Bird surveys were conducted by point count method at secondary woodland/ plantation woodland, grassland, stream courses and reservoirs (Figure 8-1 refers). Ten minutes were spent counting birds at each sampling point. Bird species within 30m of the sampling point were identified visually by using a pair of binoculars or by hearing their calls. Birds using the site and the adjacent area other than the sampling points for feeding, nesting and roosting was also recorded to form a complete species list. Ornithological nomenclature follows Carey et al. (2001).
8.3.11
Bird surveys were conducted on 25 and 31 October, 3 and
14 December 2007 and 15 January 2008 at
Herpetofauna (Amphibians and Reptiles) Survey
8.3.12 Herpetofauna surveys were conducted by active searching in conjunction with mammal survey during daytime and at night time just after dusk. Streams, reservoirs, secondary woodland / plantation woodland and grassland were actively searched for potential breeding areas of amphibians and reptiles. Microhabitats like stones, crevices, leaf litter/debris, rotten log and abandoned cardboard was also examined or uncovered to search for the eggs and tadpoles of amphibians in aquatic habitats or to reveal the presence of the amphibians and reptiles hiding under these covers. Ad hoc records during other faunal group surveys were included in the report. Nomenclature for herpetofauna follows Karsen et al. (1998).
8.3.13
Herpetofauna surveys were conducted on 25 and 31
October, 3 and 14 December 2007 and 15 January 2008 at
8.3.14 Night survey was conducted on 31 October 2007 to search for nocturnal species of amphibians and reptiles in their active stage. Hand or head torches were used to assist active searching in exposed areas of their potential habitats. Auditory detection of mating calls at their breeding sites was also recorded during night survey. Species identified, number and habitat used was included in the report.
Butterflies and Dragonflies Survey
8.3.15 The surveys for butterflies and dragonflies were conducted by visual observation and photography. Survey was conducted by point counting within 15m from the sampling points for 10 minutes at secondary woodland / plantation woodland, grassland, streams and reservoirs. Butterflies and dragonflies encounter outside counting points but within the study area were also recorded to produce a complete species list. Nomenclature for butterflies follows Lo (2004), while for dragonflies follows Wilson et al. (2003).
8.3.16
Butterfly and dragonfly surveys were conducted on 25
and 31 October, 3 and 14 December 2007 and 15 January 2008 at
Aquatic Fauna Survey
8.3.17 Aquatic fauna survey including freshwater fishes and macro-invertebrates was carried out at stream courses and reservoirs that would potentially be impacted by the proposed development. Bank side counting of freshwater fish species with the aids of short focal length binoculars along stream bank and embankment of the reservoirs was conducted. Pot trapping and hand netting was applied at the shallow water region of the reservoirs to investigate freshwater fishes inhabit in the surface water layer. For deeper water region, angling and interviewed with the anglers were conducted to supplement the information gap from literature review. Freshwater fish survey at drainage channels within the Study Area were also conducted by bank side counting. Species observed and the estimated abundance was recorded. The riparian vegetation and the streambed environment were also recorded for species identification works. Nomenclature for freshwater fish follows Lee et al. (2004), other macroinvertebrates follows Dudgeon (2003).
8.3.18 Aquatic fauna surveys in small stream tributaries were conducted on 25 and 31 October, 3 and 14 December 2007. Fish surveys were carried out in Kowloon Byewash Reservoir and Kowloon Reception Reservoir on 13 November and 17 December 2007. No fish survey was conducted in the Lower Shing Mun Reservoir due to construction works were being carried out and drained down the reservoir during the survey period.
8.4 Description of Existing Ecological Baseline Conditions
8.4.1
The works area including the proposed intake location
and tunnel alignment are within the
8.4.2
A very small portion of the study area at southeast is
within the
Habitats and Vegetation
8.4.3 Six types of habitat were identified within the study area, including secondary woodland/ plantation woodland, grassland, stream, drainage channel, reservoir and developed area/ bare ground. (Figure 8-2 and Figure 8-3 refer). Photographic illustrations of each type of habitat are presented in Plates 8.1 to 8.5 in Appendix H.
8.4.4 The size and % coverage of each habitat type within the study area are tabulated below.
Table 8‑1 Habitat types recorded within the Study Area
Habitat |
Size |
||
Worksite Area
at |
Worksite Area
at |
Study Area |
|
Secondary |
0.03ha (11%) |
- |
304.61ha (81.29%) |
Grassland |
- |
0.08ha (17%) |
0.14ha (0.04%) |
Stream |
- |
- |
0.35ha / 5.3km (0.09%) |
Drainage Channel |
0.01ha (4%) |
- |
0.26ha / 0.7km (0.07%) |
Reservoir |
0.15ha (53%) |
0.31ha (68%) |
35.38ha (9.44%) |
Developed Area / Bare Ground |
0.09ha (32%) |
0.07ha (15%) |
34.00ha (9.07%) |
Total Area |
0.28ha (100%) |
0.46ha (100%) |
374.74ha
(100%) |
Note: Worksite Area refers to the area occupied for the
proposed waterworks during construction period (Figure 2-6 and Figure 2-7).
8.4.5 A total of 74 and 104 plant species were recorded at Kowloon Byewash Reservoir Worksite Area and Lower Shing Mun Reservoir Worksite Area respectively. Plant lists of these two areas are presented in Table G1a and Table G1b respectively in Appendix G.
8.4.6 A total of 376 plant species were recorded within the study area, in which ten of them were species of conservation concern. The plant list is presented in Table G1c in Appendix G.
Worksite
Area of
8.4.7 The proposed worksite area comprises four types of habitats including secondary woodland/ plantation, drainage channel, reservoir and developed area / bare ground (Figure 8-4). This area will mostly cover part of the existing barbecue site while its south eastern end will encroach into the secondary woodland / plantation. The reservoir portion within the worksite area is bare rocky slope while the section of drainage channel within the worksite area is a complete concrete structure. The barbecue site within the worksite area is an open area with some tree planting for amenity function.
8.4.8 The woodland part comprises common native species such as Acronychia pedunculata, Schefflera heptaphylla and Sterculia lanceolata. One individual of Artocarpus hypargyreus was located at the north eastern corner of the worksite area. According to the proposed layout plan, this portion of woodland will be of 0.03ha in size.
Worksite
Area of
8.4.9
A vehicle access roughly divides the worksite area into
two halves (Figure 8-5).
The bigger half is the exposed soil overgrown with grasses and herbs on
the drained reservoir. All the plant
species are common and widespread, which include Ageratum conyzoides, Bidens alba, Leucaena leucocephala, Stachytarpheta
jamaicensis and Rhynchelytrum repens. On the slope along the vehicle access, one Pavetta hongkongensis (it was a young
individual of less than 1m in height) was found which is protected under the
Forestry Regulations (Cap. 96 sub. Leg.).
This species is very common in
8.4.10 Another half is the grassland east of the access. Common grasses such as Microstegium ciliatum and Miscanthus sinensis dominate the vegetation cover. The grassland is being disturbed which was evidenced by the presence of invasive and exotic species such as Mikania micrantha, Bidens alba and Lantana camara.
Secondary
8.4.11 This is the dominant habitat inside the study area, which is established by the mixture of plantation and secondary woodlands. Many tree species commonly used for afforestation such as Acacia confusa, Lophostemon confertus, Eucalyptus spp., Melaleuca quinquenervia and Schima superba can be found in the mixed woodlands. As the areas between the Lower Shing Mun and Kowloon Byewash reservoirs are quite far away from sources of urban disturbance, secondary woodlands have been established within these plantations. These secondary woodlands are evidenced by the presence of native tree and shrub species including Acronychia pedunculata, Alangium chinense, Aporusa dioica, Cinnamomum camphora, Cleistocalyx operculatus, Cratoxylum cochinchinense, Diospyros morrisiana, Litsea cubeba, Phyllanthus emblica, Sapium discolour.
8.4.13
Aquilaria
sinensis, Cibotium barometz, Enkianthus
quinqueflorus, Liparis nervosa, Pavetta hongkongensis, Peristylus tentaculatus and
Tainia hongkongensis are plant
species under protection by either the Forestry Regulations (Cap. 96 sub. Leg.)
or Protection of Endangered Species of Animals and Plants Ordinance (Cap 586). Artocarpus hypargyreus and Ixonanthes reticulata are not protected
by local law but listed as Near Threatened (NT) or Vulnerable (V) respectively
in Mainland
8.4.14
Except Castanopsis
carlesii, all these above species are common in Hong Kong despite having
protection status in Hong Kong or Mainland
8.4.15 Most of these species are situated far away from the two proposed worksite areas. Only one individual of each Artocarpus hypargyreus and Pavetta hongkongensis were found within the worksite area at Kowloon Byewash Reservoir and Lower Shing Mun Reservoir respectively (Figure 8-4 and Figure 8-5).
Grassland
8.4.16 One small area of grassland was identified near the proposed portal site at Lower Shing Mun reservoir. This small grassland is dominated by common grass species including Microstegium ciliatum and Miscanthus sinensis. Shrub species Ficus hispida, Lantana camara are common pioneer plants grown on similar habitats. The common invasive climber Mikania was found along the edge adjoining the road access.
Stream
8.4.17 As the study area covers the water gathering ground of the nearby reservoirs, a number of rocky streams feeding the reservoirs were identified. Vegetation found on this habitat are those common riparian species including Adina pilulifera, Elaeocarpus chinensis, Ficus fistulosa, Glochidion zeylanicum, Ficus superba, etc.
Drainage Channel
8.4.18 Few drainage channels were located around Shek Lei Pui Reservoir, Kowloon Byewash Reservoir and Kowloon Reception Reservoir. One of these drainage channels was found in between Kowloon Byewash reservoir and Kowloon Reception reservoir. It links up the two reservoirs and is a complete concrete structure which is free of vegetation.
Reservoir
8.4.19 The study area covers five reservoirs viz. Lower Shing Mun Reservoir, Kowloon Reservoir, Kowloon Byewash Reservoir, Kowloon Reception Reservoir and Shek Lei Pui Reservoir. The Lower Shing Mun Reservoir has been fully drained down for WSD’s maintenance works while the other four reservoirs are in use during this study.
8.4.20 As these reservoirs share the same boundary with the plantation woodland / secondary woodlands, the vegetation are those along the edge of these woodlands such as Acacia confusa, Lophostemon confertus, and Melaleuca quinquenervia. Since the Lower Shing Mun Reservoir has been drained for a time period of over 2 years and the area around the proposed portal (Lower Shing Mun Reservoir portal) is of higher topographical level, the exposed bare soil are covered with grasses and herbs during the survey period in 2007 and 2008. Many of these plants are pioneer and exotic species such as Ageratum conyzoides, Leucaena leucocephala and Stachytarpheta jamaicensis.
Developed Area / Bare Ground
8.4.21 This category of habitat includes all types of urban land uses such as pavement, buildings and bare engineering slopes. Usually these habitats are free of vegetation despite some landscape planting or weed species can be found. This habitat type in general is of negligible ecological importance.
Fauna
Mammal
Literature Review
8.4.18
Macaques are recorded as the largest group of
mammals in the
8.4.19 Rhesus Macaque is highly social species
which live in troops of about 20-100, sometimes over 200 (Shek, 2006). Although
8.4.20 Longtailed Macaque has a restricted distribution in Hong Kong and was also found in Lion Rock Country Park, where a monkey domain is found in the woodland near Tai Po Road (AFCD, 2008). The macaques roaming wild in the region now are actually the descendants of introduced individuals in early 1950s and some individuals mixed with Rhesus Macaque to form small troops or mated with Rhesus Macaque to produce hybrid macaques (Shek, 2006). The estimated population in 2003 was about 75 individuals (Shek, 2006), however, the result of direct counting survey conducted by the AFCD showed that there were less than five individuals existed in Kam Shan Country Park (Shek, Chan and Wan, 2007).
8.4.21 Tibetan Macaque (Macaca thibetana) and Golden Rhesus Macaque (Complete albino form of the Rhesus Macaque) were reported as very rare in Kam Shan Country Park (Shek, 2006). It is believed that only one Tibetan Macaque left in Kam Shan (Shek, 2006).
8.4.22 There is one flying mammal recorded around
the study area, the Intermediate Horseshoe Bat (Rhinolophus affinis). They have a wide distribution in Hong Kong,
including area near
8.4.23 A direct sighting of Pallas’s squirrel (Callosciurus erythraeus) has been recorded in the study area (Shek, 2006). It was also reported to find shelter at Kam Shan (AFCD, 2008).
8.4.24 East Asian Porcupine (Hystrix brachyura), Small-toothed Ferret Badger (Melogale moschata), Masked Palm Civet (Paguma larvata), Small Indian Civet (Viverricula indica), Leopard Cat (Prionailurus bengalensis), Eurasian Wild Pig (Sus scrofa), Red Muntjac (Muntiacus
muntjac) and Domestic Ox (Bos taurus)
were also recorded in Kam Shan and Lion Rock Country Park during camera
trapping survey conducted by AFCD during 2002 to 2006. All the species have
wide distributions in
8.4.25 The East Asian Porcupine, Small-toothed Ferret Badger, Masked Palm Civet, Small Indian Civet and Leopard Cat are protected under the WAPO (Cap.170). East Asian Porcupine also listed under IUCN Red List as vulnerable species (Baillie, 1996). The Leopard Cat is listed in CITES Appendix II (UNEP-WCMC, 2008) and the China Red Data Book (CRDB) as vulnerable species (Wang and Xie, 2004).
Survey Results
8.4.26
Two species of non-flying mammals were recorded within
the study area during the survey period (Table G2). The monkey Rhesus Macaque, which is the most
abundant species recorded in
Birds
Literature Review
8.4.27
Silver-eared Mesia (Leiothrix
argentauris) and Rufous-capped Babbler (Stachyris
ruficeps) were recorded by local bird watcher in December 2006 in the
8.4.28
Black Kite (Milvus
migrans) was recorded in the
8.4.29
Previous EIA study in Butterfly Valley that partially
within the southern portion of the study boundary of this Project recorded 14
and 20 species of birds during wet season (July to September 1998) and dry
season survey (January to March 1999) respectively (ERM, 1999) (Table G3a).
All the species are common and typical to the rural village habitat of
Survey Results
8.4.30 A total of 16 species of bird were recorded during the point count survey (Table G3b). An additional of 8 species was recorded outside the sampling point but within the Study Area during September 2007 to January 2008. Bird abundance and total species recorded were highest in secondary woodland/ plantation, while lowest records were observed in stream and grassland.
8.4.31 Thirteen species were recorded in the secondary woodland/ plantation during point count, most species recorded are common and widespread, except for Black-throated Laughingthrush, Pale-legged Leaf Warbler and Red-throated Flycatcher that are rare or very local.
8.4.32 Black Kite recorded soaring over secondary woodland/ plantation and standing in barbecue site (probably foraged on rubbish or scavenged on small animal dead body) in the Kam Shan Country Park is considered of regional concern (Fellowes et al., 2002) and is Class 2 Protected Animals of PRC and listed in Appendix II of CITES (Zheng and Wang, 1998).
8.4.33
Other species of conservation interest recorded within
the study area are not recorded during the point count survey. They include 3
individuals of Rufous-capped Babbler (Stachyris
ruficeps) recorded singing in undergrowth of plantation which is considered
of local concern (Fellowes et al.,
2002) and 3 individuals of Common Teal (Anas
crecca) recorded during angling survey at Kowloon Reception Reservoir on 17
December 2007 considered of regional concern (Fellowes et al., 2002). Rufous-capped Babbler is scarce resident of captive
origin. One individual was recorded in Shing Mun in early 90s and singing males
have subsequently become regularly occurred there (Carey et al., 2001). It is expected that this species is gradually
colonising suitable maturing woodland habitats in
8.4.34 Bird species recorded that may utilize the reservoir include Common Kingfisher (Alcedo atthis), Common Teal, Yellow Wagtail (Motacilla flava) and Grey Wagtail (Motacilla cinerea). One Common Kingfisher was recorded by ad hoc standing on tree leaning to the Kowloon Byewash Reservoir. This species is common and widespread passage migrant and winter visitor to wetland, riverine and coastal habitats that often perches just above water level and plunges into water to catch fish (Viney et al., 2005). Yellow Wagtail and Grey Wagtail were recorded in Lower Shing Mun Reservoir (with shallow water flow) and Kowloon Byewash Reservoir respectively. They are also common winter visitor and passage migrant that found mostly recorded in damp areas or near water and also in open cultivated land (ibid).
Herpetofauna (Amphibians and Reptiles)
Literature Review
8.4.35 Water Monitor (Varanus salvator) was traced in Kowloon Reservoir according to the Hong Kong Biodiversity Database and the specimen is believed to be released or escaped individuals. It is a very rare species and may be locally extinct (Karsen et al., 1998). This species is considered of regional concern (Fellowes et al., 2002) and is protected under the Wild Animals Protection Ordinance (WAPO) (Cap. 170), Protection of Endangered Species of Animals and Plants Ordinance (PESAPO) (Cap. 586) and listed in the China Red Data Book (CRDB) as Critically Endangered/Extinct in Wild.
8.4.36 Beale’s Turtle (Sacalia bealei) was reported as a rare species and specimen was recorded in fast-flowing streams near the Kowloon Reservoirs (Karsen et al., 1998). This species is considered of global concern (Fellowes et a., 2002) and protected by the WAPO (Cap. 170), listed in the IUCN and CRDB as Endangered species.
8.4.37
Three reptiles and 2 amphibians were recorded in
Survey Results
8.4.38
Three reptiles and 2 amphibians were recorded during
herpetofauna survey between September 2007 and January 2008. They include
Chinese Gecko (Gekko chinensis),
Grass Lizard (Takydromus sexlineatus
ocellatus), Red-eared Slider (Trachemys
scripta elegans), Asian Common Toad (Bufo
melanostictus) and Lesser Spiny Frog (Rana
exillispinosa). All the species were recorded in the
8.4.39
Three Red-eared Sliders were recorded in the Kowloon
Byewash Reservoir. Two of them were being stained with red paint (Plate 8.10).
This species has been introduced in
8.4.40 The Grass Lizard was recorded in shrubs at daytime. It is an uncommon species with low populations in hill and mountain grassland or in mixed habitats of shrubland and grassland (ibid).
8.4.41
The Lesser Spiny Frog is the most common hill stream
frogs in
Butterflies and Dragonflies
Literature Review
8.4.42
Eight butterfly species were recorded in shrubland near
the stream at
Survey Results
8.4.43
A total of 27 species of butterflies were recorded
during point count survey (Table G5a). Four additional species were recorded
within the study area outside the sampling point (Table G5b). Only the Tree Flitter (Hyarotis adrastus) is uncommon but is
widely distributed in woodland throughout
8.4.44 Abundance of butterfly was highest in secondary woodland/ plantation and species richness is highest in grassland. The most abundant species is the Red-base Jezebel (Delias pasithoe) (Table G5b), pupa and the emergence of adult from pupa were observed from the food plant Microsolen cochinchinensis (Plate 8.12) in Lower Shing Mun and Kam Shan Country Park during the survey period September 2007 to January 2008. This species is a forest butterfly that large numbers can be found near flowering plants in fall and winter (Lo, 2004). The other common species recorded in most of the habitats are Common Grass Yellow (Eurema hecabe), Common Mormon (Papilio polytes), Dark-brand Bush Brown (Mycalesis mineus), Common Sailer (Neptis hylas), Ceylon Blue Glassy Tiger (Ideopsis similis) and Blue Spotted Crow (Euploea midamus). No rare or endangered species of butterfly was recorded.
8.4.45 Seven species of dragonfly were recorded during point count survey (Table G6a). All species are common and abundant. The most abundant species is the Wanderling Glider (Pantala flavescens). It recorded in all habitats with a large number recorded in secondary woodland/ plantation near the Kowloon Byewash Reservoir (Table G6b). This species can be found all year round flying over woodland in January (Wilson et al., 2003). The shallow flow streams in Lower Shing Mun Reservoir recorded 5 species of dragonflies (Figure 8-3). They include the Common Blue Skimmer (Orthetrum glaucum), Wandering Glider, Black Threadtail (Prodasineura autumnalis), Saddlebag Glider (Tramea virginia) and the Indigo Dropwing (Trithemis festiva). All these species are common in streams and drainage channels in the urban (Wilson et al., 2003). No rare or endangered species of dragonfly was recorded.
Aquatic Fauna
Literature Review
8.4.46 Species recorded in the reservoirs within the study area include some edible fish Goldfish (Carassius auratus), Mud Carp (Cirrhinus molitorella), Common Carp (Cyprinus carpio), and Wild Carp (Hemiculter leucisculus); fish recorded in the wild Chinese Barb (Puntius semifasciolatus); aquarium fish Jewelfish (Hemichromis stellifer); and introduced species Nile Tilapia (Oreochromis niloticus) and Redbelly Tilapia (Tilapia zillii) (Lee et al., 2004).
8.4.47 According to the territory-wide long-term monitoring survey records on major taxon groups undertaken by the Agriculture, Fisheries and Conservation Department (AFCD) of the Hong Kong SAR from 2002 to 2006, 10 fish species were recorded in the Lower Shing Mun Reservoir. These include Goldfish (Carassius auratus), Mud Carp (Cirrhinus molitorella), Hainan Culter (Culter recurviceps), Common Carp (Cyprinus carpio), Mosquito Fish (Gambusia affinis), Fork Tongue Goby (Glossogobius giuris), Wild Carp (Hemiculter leucisculus), Large Mouth Bass (Micropterus salmoides), Barcheek Goby (Rhinogobius giurinus) and Redbelly Tilapia (Tilapia zillii) (AFCD, unpublish data).
8.4.48 Species recorded in streams around Kam Shan include Predaceous Chub (Parazacco spilurus), Chinese Barb (Puntius semifasciolatus), Nile Tilapia (Oreochromis niloticus), Redbelly Tilapia (Tilapia zillii) and Barcheek Goby (Rhinogobius giurinus) (Lee et al., 2004).
Survey Results
8.4.49
Nine species of freshwater fish and 3
macroinvertebrates were recorded during the aquatic fauna surveys. The most
abundant fish species recorded in the Kowloon Byewash Reservoir is the Redbelly
Tilapia (Tilapia zillii) followed by
the Jewel Fish (Hemichromis stellifer).
These two species were captured by pot traps and angling. The former one is an
aquarium fish that occurs in large number in a few local reservoirs (Lee et al., 2004). The later one is an
introduced species common in streams and rivers. The other common species
recorded in reservoir is the Predaceous Chub (Parazacco spilurus). This species was recorded in abundant in the
Kowloon Reception Reservoir and in the connected stream tributaries. This
species is listed in the China Red Data Book as vulnerable species (AFCD Hong
Kong Biodiversity Database website). One freshwater fish species Flat-headed
Loach (Oreochromis platycephalus) was
recorded in the water pool of Kowloon Byewash Reservoir upstream tributary at
AF-7 (Figure 8-1). This species can commonly found in upper
streams throughout
8.4.50 One rare species of local concern, Rose Bitterling (Rhodeus ocellatus), was recorded in the Kowloon Reception Reservoir (Figure 8-2) upstream of the Kowloon Byewash Reservoir. This species depends on the freshwater mussels by laying the eggs inside the mantle cavity of the mussels (ibid). The dead mussel Anodonta woodiana was observed at the bed of the Kowloon Reception Reservoir (Plate 8.13, Appendix H).
8.4.51 No freshwater fish was recorded in all drainage channels within the Study Area. These drainage channels are having shallow or no flow during dry season and very rapid flow during wet season or when the upstream reservoirs discharge the overflow downstream.
8.4.52 No freshwater fish was recorded in the stream flowing to the Lower Shing Mun Reservoir during the survey period. Only the freshwater shrimp (Caridina cantonensis) and Water Skater (Ptilomera tigrina) were recorded in the upstream of the outfall (AF-2 and AF-3 in Figure 8-1).
8.5 Evaluation of Sites and Species
8.5.1 The two sites proposed for worksite areas were evaluated in accordance with the criteria set forth in Annex 8, Table (2) of the TM-EIAO.
Table 8‑2 Ecological Evaluation of Worksite Area
at
Criteria |
Worksite Area at |
Habitat Quality |
The barbecue
site and the deep concrete channel are of negligible ecological value while
the secondary woodland / plantation and the reservoir are considered of high
and medium-low in terms of habitat quality respectively. |
Naturalness |
Most of the
site is man made; only the very small woodland area is semi-natural. |
Size |
Very small,
the total site area is approx. 0.28ha; the woodland inside the worksite
boundary is only 0.03ha. |
Diversity |
Flora and
fauna diversity is low. |
Rarity |
All of the
identified habitats and species are not rare in |
Re-creatability |
The existing
barbecue site is easy to be re-created. The secondary woodland /plantation
can be re-created in longer duration. |
Fragmentation |
The site is
not fragmented. |
Ecological linkage |
The small
piece of woodland is ecologically linked with the adjacent woodland but the
linkage is weak as disturbance from the human activities is anticipated. |
Potential value |
Low |
Nursery/breeding ground |
No record of
nursery or breeding ground of any species. |
Age |
The Kowloon
Byewash Reservoir (including the associated structures dams and roads) is of
over 70 years of age. The part of woodland within the worksite area is of
about 40 years. |
Abundance/ Richness of wildlife |
Low wildlife
richness and abundance |
Overall Ecological value |
Low |
Table 8‑3 Ecological Evaluation of Worksite Area
at
Criteria |
Worksite Area at |
Habitat Quality |
Quality of the
grassland and exposed areas of the reservoir are medium-low, while the
remaining artificial habitats are ranked as low. |
Naturalness |
Most of the
site (reservoir, road access, engineering slopes) is artificial; only the grassland
and the edge of the woodland are semi-natural. |
Size |
Very small.
The total site area is approx. 0.46ha in size. |
Diversity |
Flora
diversity is low, fanua diversity is moderate-low for butterfly and low
diversity for other fauna. No fish is recorded at the Lower Shing Mun
Reservoir as the the whole reservoir was drained for construction during the
study period. |
Rarity |
All of the
identified habitats and species are not rare in |
Re-creatability |
The reservoir,
roadside vegetation and grassland are easy to be re-created. As only the edge
of the woodland would be affected, it can be re-created by replantation. |
Fragmentation |
No
fragmentation within the site. |
Ecological linkage |
The small
grassland and woodland directly linked with the adjacent woodland. |
Potential value |
Potential
value is low due to the small size of the site. |
Nursery/breeding ground |
Neither
nursery nor breeding ground is recorded. |
Age |
The Lower
Shing Mun Reservoir (including the associated structures dams and roads) is
of about 40 years old. Age of the grassland is not available. |
Abundance/ Richness of wildlife |
Low wildlife
richness and abundance |
Overall Ecological value |
Low |
8.5.2 Ecological evaluation of each habitat within the study area was presented in Table 8-4 to Table 8-9 below.
Table 8‑4 Ecological
Evaluation of Secondary
Criteria |
Description |
Habitat Quality |
Habitat
quality is considered as high in overall. |
Naturalness |
Semi-natural. |
Size |
Large. Totally
over 300ha in size. |
Diversity |
Floral and
faunal diversity is high. |
Rarity |
One rare tree
species of Castanopsis carlesii and
nine other floral species of conservation concern; a rare species of mammal
Longtailed Macaque. |
Re-creatability |
Reforestation
requires several ten years. |
Fragmentation |
Most of the
habitat is continuous. Only at the southern end of the study area the
secondary woodland / plantation in |
Ecological linkage |
This habitat
is directly linked with the remaining part pf the |
Potential value |
Potential
value is high |
Nursery/breeding ground |
Breeding and
nursery ground for Rhesus Macaque and butterfly Red-base Jezebel. |
Age |
At least 50
years |
Abundance/Richness of wildlife |
High abundance
of plants and animals |
Overall Ecological value |
High |
Table 8‑5 Ecological Evaluation of Grassland
Criteria |
Description |
Habitat Quality |
Habitat
quality is medium-low. |
Naturalness |
Semi-natural
in natural. Exotic plants exist inside the habitat. |
Size |
Small. Approx
0.14ha. |
Diversity |
Flora
diversity is low, moderate-low diversity for butterfly and low diversity for
other fauna. |
Rarity |
No rare
species were identified. |
Re-creatability |
Semi-natural
grassland is easy to be re-created. |
Fragmentation |
No
fragmentation within the grassland. |
Ecological linkage |
The grassland
is directly linked with the adjacent secondary woodland /plantation. |
Potential value |
Potential
value is medium. |
Nursery/breeding ground |
Potential
nursery ground for butterfly. |
Age |
Not known |
Abundance/Richness of wildlife |
Low abundance
of wildlife. |
Overall Ecological value |
Medium-low |
Table 8‑6 Ecological Evaluation of Stream
Criteria |
Description |
Habitat Quality |
High |
Naturalness |
Natural |
Size |
Approx 5.3km
in length. |
Diversity |
Floral
diversity is medium while faunal diversity is low. |
Rarity |
One rare
species of reptile Beale’s Terrapin was recorded in fast-flowing streams near
the Kowloon Reservoirs. |
Re-creatability |
Natural stream
is difficult to be re-created. |
Fragmentation |
No
fragmentation was observed. |
Ecological linkage |
These habitats
ecologically linked with the surrounding woodlands, plantations and
reservoirs |
Potential value |
Potential value
is high. |
Nursery/breeding ground |
Streams are
nursery and breeding grounds of some freshwater fish and amphibians. |
Age |
Not known |
Abundance/ Richness of wildlife |
Medium-low |
Overall Ecological value |
Medium-high |
Table 8‑7 Ecological Evaluation of Drainage Channel
Criteria |
Description |
Habitat Quality |
Low |
Naturalness |
Drainage channel are man-made habitat. |
Size |
Approx 0.7km in length. |
Diversity |
Low for both flora and fauna diversity. |
Rarity |
Neither the habitat nor the species are rare. |
Re-creatability |
Drainage channel is already man-made structure. |
Fragmentation |
No fragmentation was observed. |
Ecological linkage |
These habitats ecologically linked with the
surrounding woodlands, plantations and reservoirs. |
Potential value |
Low |
Nursery/breeding ground |
Not nursery / breeding grounds of any fauna. |
Age |
Not known |
Abundance/ Richness of wildlife |
Low |
Overall Ecological value |
Low |
Table 8‑8 Ecological Evaluation of Reservoir
Criteria |
Description |
Habitat Quality |
Habitat
quality is medium. |
Naturalness |
Reservoir is
man-made habitat. |
Size |
Large. Totally
over 35ha in size. |
Diversity |
Both fauna and
flora diversity are low. |
Rarity |
A very rare
Water Monitor and a rare freshwater fish Rose Bitterling were recorded in
Kowloon Reservoir and Kowloon Reception Reservoir respectively. An uncommon
Wild Carp (Hemiculter leucisculus) was recorded in the Lower Shing Mun
Reservoir by AFCD previous study. The current status of the reservoir is
being drained and no fish was recorded. |
Re-creatability |
Reservoir is
re-creatable. |
Fragmentation |
No
fragmentation was observed. |
Ecological linkage |
Reservoirs are
ecologically linked with the feeding streams and the adjacent woodlands /
plantations. |
Potential value |
Potential
value is medium-low |
Nursery/breeding ground |
Breeding and
nursery ground for Rose Bitterling and other freshwater fish species. |
Age |
Over 70 years. |
Abundance/Richness of wildlife |
High abundance
of exotic fishes and medium to low abundance for native fish species and
edible fishes. Species richness is moderate-low. |
Overall Ecological value |
Medium-low |
Table 8‑9 Ecological Evaluation of Developed Area / Bare Ground
Criteria |
Description |
Habitat Quality |
Low |
Naturalness |
Artificial |
Size |
Approx. 34ha in size. |
Diversity |
Low |
Rarity |
No rare species were identified. |
Re-creatability |
Easy to be re-created. |
Fragmentation |
- |
Ecological linkage |
No ecological linkage was identified. |
Potential value |
Low |
Nursery/breeding ground |
Not nursery / breeding grounds of any fauna. |
Age |
- |
Abundance/ Richness of wildlife |
Low abundance and richness of wildlife |
Overall Ecological value |
Low |
Evaluation of Species
8.5.3 All the species of conservation concern were evaluated in accordance with the criteria set forth in Annex 8, Table (3) of the TM-EIAO. Table 8-10 evaluate the floral species found within the proposed worksite areas (on-site) while Table 8-11 evaluate the floral species recorded within the study area but ouside the proposed worksite areas (offsite). Table 8-12 evaluates the faunal species of conservation concern recorded within the study area.
Table 8‑10 Ecological Evaluation of Floral Species within Proposed Worksite Area (On-site)
Species |
Location |
Protection Status / Conservation
Status |
Distribution |
Rarity |
Artocarpus hypargyreus |
Distributed widely within the study
area; one individual situated within the worksite at Kowloon Byewash
Reservoir |
Not protected in Listed as Near Threatened in Listed as Vulnerable in IUCN 2008 |
Distributed widely in |
Common (4) |
Pavetta hongkongensis |
Distributed widely within the study
area; one individual is found within the worksite area at Lower Shing Mun
Reservoir. |
Protected in |
Distributed widely in |
Common (4) |
Reference source:
(1) Rare and Precious Plants of
(2)
(3) Hong Kong Plant Check List 2001;
(4) Corlett’s study “Hong Kong
Vascular Plants: Distribution and Status”.
Table 8‑11 Ecological Evaluation of Floral Species outside the Proposed Worksite Areas (Offsite Habitats within the Study Area)
Species |
Location |
Protection Status / Conservation Status |
Distribution |
Rarity |
Aquilaria sinensis |
Distributed widely within the study
area; not within the worksite areas |
Listed in Protection of Endangered
Species of Animals and Plants Ordinance (Cap 586); Listed as Near Threatened in Listed as Vulnerable in IUCN 2008 |
Distributed widely in |
Common (4) |
Artocarpus hypargyreus |
Distributed widely within the study
area. |
Not protected in Listed as Near Threatened in Listed as Vulnerable in IUCN 2008 |
Distributed widely in |
Common (4) |
Castanopsis carlesii |
About 400m away from the worksite
area at Lower Shing Mun Reservoir |
Not protected in Hong Kong and |
Recoded distributions include: Mt
Nicholson, Wu Kau Tang, Cheung Sheung, Nei Lak Shan, Tai Mo Shan and |
Rare (4) |
Cibotium barometz |
Distributed widely within the study
area; not within the worksite areas |
Listed in Protection of Endangered
Species of Animals and Plants Ordinance (Cap 586); Listed as Vulnerable in |
Distributed widely in |
Common (4) |
Enkianthus quinqueflorus |
Distributed widely within the study
area; not within the worksite areas |
Protected in |
Distributed widely in |
Common (4) |
Ixonanthes reticulata |
Distributed widely within the study
area; not within the worksite areas |
Not protected in Listed as Vulnerable in |
Distributed widely in |
Common (4) |
Liparis nervosa |
Found on some hill slopes within the study area; not within the
worksite areas |
Protected in |
Distributed widely in |
Common (4) |
Pavetta hongkongensis |
Distributed widely within the study
area. |
Protected in |
Distributed widely in |
Common (4) |
Peristylus tentaculatus |
Found on some hill slopes within the study area; not within the
worksite areas |
Protected in |
Distributed widely in |
Common (4) |
Tainia hongkongensis |
Found on some hill slopes within the study area; not within the worksite
areas |
Protected in |
Other recorded distribution: Wong
Lung Hang, |
Common (4) |
Reference source:
(1) Rare and Precious Plants of
(2)
(3) Hong Kong Plant Check List 2001;
(4) Corlett’s study “Hong Kong Vascular Plants: Distribution and
Status”.
Table 8‑12 Ecological Evaluation of Faunal Species with Conservation Concern within the Study Area
Common Name |
Scientific Name |
Location |
Protection Status |
Distribution |
Rarity |
Intermediate Horseshoe Bat |
Rhinolophus affinis |
Previous records in |
WAPO Cap. 170 |
Widely distributed |
Common; considered of local concern |
Palla’s Squirrel |
Callosciurus erythraeus |
Previous records in Kam Shan CP and
Lion Rock CP |
WAPO Cap. 170 |
Widely distributed |
Common |
Small-toothed Ferret Badger |
Melogale moschata |
Previous records in Kam Shan CP and
Lion Rock CP |
WAPO Cap. 170 |
Widely distributed in forested
areas throughout |
Common |
Masked Palm Civet |
Paguma larvata |
Previous records in Kam Shan CP and
Lion Rock CP |
WAPO Cap. 170 |
Widely distributed in forested
areas throughout |
Uncommon; considered of potential
regional concern |
Small Indian Civet |
Viverricula indica |
Previous records in Kam Shan CP and
Lion Rock CP |
WAPO Cap. 170 |
Widely distributed in forested
areas throughout |
Common |
Leopard Cat |
Prionailurus bengalensis |
Previous records in Kam Shan CP and
Lion Rock CP |
WAPO Cap.170; PEAPO Cap.586; CITES Appendix II;
CRDB – Vulnerable |
Widely distributed in forested
areas throughout |
Uncommon |
Rhesus
Macaque |
Macaca
mulatta |
Kam Shan CP including Kowloon
Reservoirs Group, secondary woodland/ plantation, barbecue site and slopes of
retaining wall |
WAPO
Cap.170; PEAPO Cap.586; IUCN - Lower Risk/Near Threatened; |
Widely
distributed |
Common |
Longtailed Macaque |
Macaca fascicularis |
Previous records in |
WAPO
Cap.170; PEAPO Cap.586; IUCN - Lower Risk/Near Threatened; |
Mainly
occurred in |
Rare |
East Asian
Porcupine |
Hystrix
brachyura |
Scat recorded at nature trail of
Kam Shan CP along woodland |
WAPO
Cap.170; IUCN - Vulnerable |
Widely
distributed |
Very common |
Common Teal |
Anas
crecca |
|
WAPO Cap.170 |
Common
winter visitor found in any wetland habitat |
Locally
common; considered of regional concern |
Black Kite |
Milvus migrans |
Soaring over secondary woodland /
plantation in Kam Shan CP and Lower Shing Mun Reservoir and at barbecue site
in Kam Shan CP |
WAPO Cap.170 |
Widely
distributed |
Common; considered of regional
concern |
Rufous-capped Babbler |
Stachyris ruficeps |
Undergrowth of plantation in Kam
Shan CP |
WAPO Cap.170 |
Scarce resident |
Scarce resident of captive origin;
considered of local concern |
Water Monitor |
Varanus salvator |
Previous records in Kowloon
Reservoir |
WAPO Cap.170; PEAPO Cap.586; |
Records in several localities and
Kowloon Reservoir but probably released or escaped individuals. |
Very rare locally, may be extinct
in the wild in |
Beale’s Terrapin |
Sacalia bealei |
Previous records in fast-flowing
streams near the Kowloon Reservoirs |
WAPO Cap.170; IUCN – Endangered; CRDB - Endangered |
A few specimens found in Tai Mo
Shan, Fanling, Kowloon Reservoirs and Tai Po Kau |
Rare; considered of global concern |
Lesser Spiny Frog |
Rana exilispinosa |
Water pools of stream tributaries
in |
Not protected |
Widely distributed in mountain
streams throughout |
Common; considered of potential
global concern |
Rose Bitterling |
Rhodeus ocellatus |
|
Not protected |
Recorded in one stream and
reservoir |
Rare; considered of local concern |
Predaceous Chub |
Parazacco spilurus |
Kowloon Reception Reservoir and its
stream tributaries |
CRDB – Vulnerable |
widespread species occurring in
most unpolluted hill streams in both upper and lower courses |
Common |
Wild Carp |
Hemiculter leucisculus |
Previous AFCD records in Lower
Shing Mun Reservoir |
Not protected |
Recorded in several local
reservoirs |
Uncommon |
8.6 Identification of Potential Impacts
Identification of Impacts during Construction Phase
8.6.1 Construction activities for the proposed waterworks project will comprise site clearance, construction of cofferdam, draining part of the reservoir and operation of a tunnel boring machine (TBM). Potential ecological impacts arising from these activities would include: habitat loss, impact on floral species of conservation concern, direct injury to wildlife, dust deposition on vegetation, site runoff and construction disturbance to wildlife.
Habitat Loss
8.6.2 Habitat loss will be a direct impact resulting from site clearance for works operation and temporary storage. Loss of different types of habitats at the two proposed worksite areas was presented in the following table.
Table 8‑13 Habitat Loss at Worksite Areas
Habitat |
Worksite Area at |
Worksite Area at |
Total |
Secondary |
0.03ha |
- |
0.03ha |
Grassland |
- |
0.08ha |
0.08ha |
Stream |
- |
- |
- |
Drainage Channel |
0.01ha / 26m |
- |
0.01ha / 26m |
Reservoir |
0.15ha |
0.31ha |
0.46ha |
Developed Area/ Bare Ground |
0.09ha |
0.07ha |
0.16ha |
8.6.3 In the above table, all habitats within the boundary of Worksite Area were assumed to be affected during the construction, and therefore the sizes of the potentially affected areas are considered as the worst case scenario.
8.6.5 Low species diversity and abundance were recorded at the Lower Shing Mun Reservoir during the study period. No fish species was recorded recently as the whole reservoir was drained for maintenance. Although an uncommon fish species Wild Carp Hemiculter leucisculus was previously recorded in this reservoir, it is not likely that the fish will recruit to the reservoir prior to the proposed construction.
8.6.7 Temporary loss of reservoir habitats would occur during construction phase since draining down of part of the reservoirs would be required for the construction of cofferdams (indicative locations of cofferdam refer to Figure 5-4 and 5-5). As both worksite areas are situated on a higher ground level at the edge of the reservoirs, both reservoirs only need to be drained down partially to expose these areas. Therefore the remaining major portion of the reservoirs will not be affected. The actual habitat loss will only be confined to the portion within the cofferdams. Aquatic fauna especially fishes inhabit in the drained portion will temporary loss their habitat. Fishes utilizing the habitat in this portion will be confined in the remaining water at the reservoir portion with normal function outside the works area. The cofferdams will be removed after completion of the works.
8.6.8 Developed area/bare ground within the worksite areas would be lost due to site clearance for works operation, temporary storage and site haul roads. These habitats will be reinstated after the completion of the works.
Impact on Floral Species of Conservation Concern
8.6.9
As described in Section 8.4.15 and Table 8-10, two floral species of conservation
interest were identified at proposed worksite areas despite both species are
common and widespread in
8.6.10 The affected A. hypargyreus at Kowloon Byewash Reservoir worksite area was found on the slope within the proposed worksite area at Kowloon Byewash Reservoir. The tree is small in size of about 190mm in trunk diameter and 6m in height. Preservation of the tree onsite is the prioritised option required by the Environment, Transport and Works Bureau Technical Circular (Works) No. 3/2006 (ETWB TCW No. 3/2006). However as the tree will be in direct conflict with the slope re-grading works for the construction of the intake structure and it has an anticipated low survival rate after transplanting, removing the tree will be the unavoidable option. Taking into account the high commonness of the tree species, only one individual involved, no significant ecological impact on this species community is anticipated.
8.6.11
The P.
hongkongensis listed in the Forestry Regulations (Cap. 96 sub. leg.) was
found on the slope along the existing vehicle access. Like A.
hypargyreus, it is also common in
Direct Injury to Wildlife
8.6.12 Wildlife like Rhesus Macaque near the reservoir may be hurt during the operation of the construction plants, machinery and during draining of the reservoir. No direct injury of fishes will occur during the draining process of the reservoir prior to construction, as both worksite areas are situated on a higher ground level at the edge of the reservoirs, both reservoirs only need to be drained down partially to expose these areas. No pumping pipes are required in the draining process. Instead, the reservoirs will be drained down through rountine process currently operated during reservoir overflow events. Fishes will colonize to other portion of the reservoir following the water retreat outside the proposed works area.
Dust Deposition on Vegetation
8.6.13 Construction activities such as site clearance and transportation of materials may generate dust if no proper dust control measures were implemented. Dust may deposit on leaves of plants in the nearby habitats and inhibit photosynthesis, which could deteriorate the plant health.
Impacts to Water Quality
8.6.14 As the proposed worksite areas will encroach into the reservoirs, water quality may be affected by the site runoff, sediment release to the water column and chemical spillage associated with the construction works. Potential impacts to water quality include increase concentration of suspended solids and increase nutrient levels in the water column. This may eventually cause adverse impacts on aquatic ecology and water supplies of the reservoirs.
8.6.15 The water quality impact assessment of the EIA also showed that the water tunnel will not affect the water table of the existing condition. The potential effect of the proposed freshwater transfer tunnel on the water table is of negligible impact.
Disturbance to Wildlife
8.6.16
Presence of workers, moving machines and other
construction activities including drilling may disturb the wildlife utilizing
the reservoirs, plantation woodland and grassland within the works area in the
8.6.17
Disturbance impacts to wildlife utilizing the adjacent
habitats within the study area may include noise disturbance and silt runoff to
the reservoirs. Species of conservation
concern that may affect include the Rufous-capped Babbler, Black Kite, Palla’s
Squirrel, Rhesus macaque and Longtailed Macaque. They are all mobile species that will avoid
utilizing the adjacent habitats during the construction period. The nocturnal species recorded in the
Identification of Impacts during Operational Phase
8.6.18 Only the two portal structures were proposed on surface while the whole water tunnel will be constructed underground. As these two permanent portal structures were planned on existing bare rock (i.e. at Kowloon Byewash Reservoir) or bare soil (i.e. Lower Shing Mun Reservoir), no adverse impact on ecology was anticipated during the operational phase.
Identification of Cumulative Impacts
8.6.19 As stated in Section 2.7 of this report, three planned projects may be implemented concurrently, including:
·
PWP Item No. 155CD -
· The Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) – Hong Kong Section likely to commence in 2009; and
· Agreement No. CE 77/2001 (GE) and 2/2006 (GE) – Slope Upgrading Works with no definite program.
8.6.20 The Lai Chi Kok Drainage Tunnel project will be located outside the EIA study area of our project, while XRL is all underground with substantial vertical separation with the IRTS tunnel. The slope upgrading works will only involve minor maintenance works on existing artificial slopes. Therefore no cumulative impacts were identified.
Impacts during Construction Phase
8.7.1 Potential construction impacts identified in the study included: habitat loss, direct injury to wildlife, dust deposition on vegetation, impacts to water quality and disturbance to wildlife.
Habitat Loss
8.7.2 Although the habitat loss would be likely the potential direct impact, this impact will be temporary in nature as all the lost habitats will be reinstated after the completion of the project.
8.7.3 At worksite area at Kowloon Byewash Reservoir, although four types of habitat were included, only the secondary woodland / plantation had got a higher ecological value for its denser vegetation, semi-naturalness and support of diverse wildlife. However the affected portion of the woodland is very small in size (approx. 0.03ha) and it is directly adjoining the barbecue site where high level of human disturbance is expected. Unlike the core part of the secondary woodland / plantation, the portion within the worksite area is only the edge of the habitat which contains common species despite one individual of Artocarpus hypargyreus was recorded. Therefore even though the habitat type of secondary woodland / plantation within the whole study area was evaluated as high in overall, impact on the onsite habitat is anticipated to be not significant.
8.7.4 The construction of intake structure at the Kowloon Byewash Reservoir and outfall structure at Lower Shing Mun Reservoir will cause temporary loss of part of the reservoir areas within the proposed worksite areas (approx. 0.15ha and 0.31ha respectively) during the construction period. Cofferdams would be constructed along the interface between the reservoirs and the worksite areas to separate the reservoir from construction activities. In order to build the cofferdams, the reservoirs would be required to be drained down temporarily.
8.7.5 As the cofferdam will be used to separate the reservoirs from the worksite areas, no further draining down would be required for the remaining part of the reservoirs. Therefore the minor habitat loss will not cause significant impact on the main bodies of the reservoirs which will carry out their normal function during the construction period. These cofferdams will be removed after the completion of the works. Fishes inhabit in the drained portion will follow the water flow to the remaining reservoir portion. Taking into account the small size involved, temporary nature of the impact, and the colonization of fish species to the remaining reservoir portion with normal function, the temporary impact of draining down of a small portion of the reservoir is considered negligible.
8.7.6 Taking into account the very small size of the habitats to be affected, and the temporary nature of the impact, the impact level to the habitat loss and loss of foraging ground for Rhesus macaque is considered to be moderate-low.
8.7.7 As all the habitats within the worksite area at Lower Shing Mun Reservoir were of low to medium-low ecological value, the temporary loss of the habitats was considered Low.
8.7.8 The temporary loss of feeding ground for butterfly species in the Lower Shing Mun Reservoir will have low impact on the butterflies, as the butterfly species recorded are common and very common that dominated by Riodinidae and Nymphalidae that also prefers plantation woodland habitat, the butterflies will re-colonize to the habitat once reinstate in the operation phase.
8.7.9 The temporary loss of developed area/bare ground at the two proposed worksite areas for works operation, temporary storage and site haul roads will have negligible impact for their low ecological value.
8.7.10 Summary of the impact evaluation is presented in below.
Table 8‑14 Evaluation of Ecological Impact of Habitat Loss
Criteria |
Worksite Area at |
Worksite Area at |
Habitat Quality |
Most of the
habitats are of medium-low to low;
only the small part of the habitat
edge of the secondary woodland /plantation has higher habitat quality |
Overall
medium-low to Low |
Species |
All species
are common and widespread except the potential of having Rose Bitterling flow
from the upstream Kowloon Reception Reservoir. One individual of Artocarpus hypargyreus was found
within the site. It is a common tree species in |
All species
are common and widespread except the Wild Carp (Hemiculter
leucisculus) of uncommon status. |
Size / Abundance |
The affected
area is small in size; both flora and fauna abundance is low. |
The affected
area is small in size and both flora and fauna abundance is low especially for the aquatic fauna due to the drain down of reservoir
for maintenance works. |
Duration |
During construction
period |
During
construction period |
Reversibility |
Reversible but
restoration of secondary woodland / plantation requires longer time. |
Reversible. |
Magnitude |
Medium |
Medium |
Overall Impact Severity |
Moderate-low |
Low |
Impact on Floral Species of Conservation Concern
8.7.11
As described in Section 8.4.15 and Table 8-10, two floral species of conservation concern
were identified at proposed worksite areas.
The Artocarpus hypargyreus
found at Kowloon Byewash Reservoir worksite area is a species ranked as Near
Threatened under the List of Wild
PlantsUnder State Protection of Mainland
8.7.12
The removal of the tree will be regulated by the
requirements stipulated in the relevant technical circular ETWB TCW No. 3/2006.
Although the individual is not suitable for transplanting for its low survival
rate after transplanting, compensatory planting is required for its removal
during the tree removal application stage in accordance with the technical
circular ETWB TCW No. 3/2006. Taking into the account only one individual is
affected and the species is very common in
8.7.13
The Pavetta hongkongensis could be either preserved
onsite or transplanted. Taking into the account only one individual is
affected, the affected species is common in
8.7.14 Summary of the impact evaluation is presented below.
Table 8‑15 Evaluation of Ecological Impact on Floral Species of Conservation Concern
Criteria |
Artocarpus hypargyreus |
Pavetta hongkongensis |
Species |
- Not
protected in - listed as
Near Threatened in Mainland - species is
common and widespread in |
- Protected
locally under the Forestry Regulations. - species is
common and widespread in |
Size / Abundance |
Young tree;
one individual |
Young shrub;
one individual |
Duration |
During
construction period |
During
construction period |
Reversibility |
Not reversible |
Not reversible |
Magnitude |
Low |
Low |
Overall Impact Severity |
Low |
Low |
Direct Injury to Wildlife
8.7.15 Wildlife like Rhesus Macaque may be hurt during the operation of the construction plants and machinery. Precautionary measures like avoidance of eating in the works area and feeding of wildlife could minimize the chance of attracting the wildlife to the works area. The impact on direct injury to wildlife will be of insignificant with the implementation of good site practices.
8.7.16 No direct injury of fishes may occur during the draining process of the reservoir prior to construction, as the draining process is routinely operated during reservoir overflow event and the fishes will colonize to other portion of the reservoir with water outside the works area.
Table 8‑16 Evaluation of Ecological Impact on Direct Injury to Wildlife
Criteria |
Rhesus Macaque |
Fishes in the Reservoir |
Species |
- Protected
under WAPO and PEAPO in - listed in
IUCN as Lower Risk/Near Threatened; - listed in
CRDB as Vulnerable; - species is
common and widely distributed in |
- One
potential rare species the Rose Bitterling of potential global concern; - Other fish
species in the Kowloon Byewash Reservoir is common and widespread or exotic
to - One uncommon species the Wild Carp (Hemiculter
leucisculus) recorded in the Lower Shing Mun Reservoir by previous AFCD study |
Abundance |
High abundance
in |
- No
observation of Rose Bitterling was recorded in the Kowloon Byewash Reservoir
but may flow from the upstream Kowloon Reception Reservoir during water
discharge; - Abundance
for other fish species are moderate-low to low for Kowloon Byewash Reservoir - No fish was recorded in the Lower Shing Mun Reservoir during the
study period due to the drain down of reservoir for maintenance |
Duration |
During
construction period |
During
construction period |
Reversibility |
Not reversible |
Not reversible |
Magnitude |
The chance of
direct injury to wildlife is low |
The chance of
direct injury to wildlife is low |
Overall Impact Severity |
Low |
Negligible |
Dust Deposition on Vegetation
8.7.1 As standard good site practices must contain dust suppression measures to control the air quality (details refer to Section 3 Air Quality), dust impact on offsite vegetation is considered not significant. Summary of the impact evaluation is presented below.
Table 8‑17 Evaluation of Ecological Impact of Dust Deposition
Criteria |
Worksite Area at |
Worksite Area at |
Habitat Quality |
The habitat
quality along the edge of the woodland is medium. |
The habitat
quality along the edge of the woodland is medium. |
Species |
No rare
species was identified. |
No rare
species was identified. |
Size / Abundance |
The interface between
the worksite area and the surrounding habitats is small. |
The interface
between the worksite area and the surrounding habitats is small. |
Duration |
During
construction period |
During
construction period |
Reversibility |
Reversible |
Reversible |
Magnitude |
Low |
Low |
Overall Impact Severity |
Low |
Low |
Impact to Water Quality
8.7.2 As standard good site practices must contain site runoff control measures to maintain the water quality (details refer to Chapter 5 Water Quality) within acceptable level, no significant level of impact is thus predicted. Summary of the impact evaluation is presented in below.
Table 8‑18 Evaluation of Ecological Impact of Deterioration of Water Quality
Criteria |
Worksite Area at |
Worksite Area at |
Habitat Quality |
Medium-low to
low |
Medium-low to
low |
Species |
- One
potential rare species the Rose Bitterling of potential global concern; other
fish species are common and widespread or exotic to |
- One uncommon Wild Carp (Hemiculter
leucisculus) was recorded in previous AFCD study - No aquatic
fauna was recorded during the study period as it is being
drained for construction. |
Size / Abundance |
- Size of the
site is small and no observation of Rose Bitterling was recorded in the
Kowloon Byewash Reservoir but may flow from the upstream Kowloon Reception
Reservoir during water discharge; - Abundance
for other fish species are moderate-low to low |
Size of the
site is small |
Duration |
During
construction period |
During
construction period |
Reversibility |
Reversible |
Reversible |
Magnitude |
Low |
Low |
Overall Impact Severity |
Low |
Low |
Disturbance to Wildlife
8.7.3 The disturbance impacts due to this proposed project are expected to be low owing to the temporary nature and the existing area in Kam Shan Country Park is frequently visit by visitors and morning hikers, while construction works is being in progress in the Lower Shing Mun Reservoir, the impacts on wildlife are anticipated of low significant with good construction site practices.
8.7.4
The disturbance impacts to wildlife utilizing the
adjacent habitats will be temporary and of moderate-low significance due to a
large area of suitable habitats presence in connection to the affected
area. There will be no impact on the
8.7.5 Summary of the impact evaluation is presented in the table below.
Table 8‑19 Evaluation of Ecological Impact of Disturbance to Wildlife
Criteria |
|
|
Habitat Quality |
High for
secondary woodland / plantation and medium-low for Kowloon Reservoirs Group |
High for
secondary woodland / plantation and medium-low to low for other habitats |
Species |
Species of
conservation concern that may affect by noise and other construction
disturbances: Rhesus Macaque, Longtailed Macaque, Palla’s Squirrel, Small-toothed Ferret
Badger, Masked Palm Civet, Small Indian Civet, Leopard Cat and East Asian
Porcupine Black Kite and Rufous-capped Babbler |
No rare
species is identified, common bird species will be disturbed by the
construction activities |
Size / Abundance |
Small area
adjacent to the works site will be affected and the species abundance is low |
Small area adjacent
to the works site will be affected and the species abundance is low |
Duration |
During
construction period |
During
construction period |
Reversibility |
Reversible |
Reversible |
Magnitude |
Low |
Low |
Overall Impact Severity |
Moderate-low |
Low |
8.8 Recommendations on Ecological Impact Mitigation Measures
Mitigation Measures for Habitat Loss
8.8.1 Although the impact of habitat loss is considered not significant for both sites around the two portals, mitigation measures were recommended to further minimise adverse effect.
8.8.2 During detailed design, vegetation clearance should be minimised as far as possible. Clearance of certain areas of habitat may be required for the implementation of the project. Restoration of same type of habitat (i.e. woodland and grassland) in ratio not less than 1:1 in terms of area should be conducted to avoid residual impact and allow re-colonization of bird and butterfly species utilizing the habitats.
8.8.3 The actual size of habitat loss will be subject to the detailed design. If the worst case scenario is adopted, all the habitats within the works boundary are assumed to be affected. Table 8-20 shows the quantities of affected and compensated areas and Figure 8-6 and 8-7 indicate proposed area for habitat reinstatement.
Table 8‑20 Habitat Loss and Proposed Mitigation at Worksite Areas
Habitat |
Habitat Loss at Worksite Area at |
Habitat Loss at Worksite Area at |
Ecological Mitigation Measure |
Compensated Area |
Secondary |
0.03ha |
- |
Habitat Restoration in ratio at least 1:1 |
0.03ha |
Grassland |
- |
0.08ha |
Habitat Restoration in ratio at least 1:1 * |
0.08ha |
Drainage Channel |
0.01ha / 26m |
- |
None ** |
N/A |
Reservoir |
0.15ha |
0.31ha |
None ** |
N/A |
Developed Area/ Bare Ground |
0.09ha |
0.07ha |
None ** |
N/A |
* No active
planting work is proposed as the grassland habitat will be reinstated through
natural colonisation after the completion of the project.
** No active
restoration is proposed as these habitats will be reinstated readily after the
completion of the project.
8.8.4 In addition, clear definition of works boundary should be provided to prevent disturbance and damage to the adjacent habitats and wildlife.
8.8.5 The reservoirs will be restored once the removal of cofferdam and associated structure on-site, and water will be refilled to the two reservoirs to restore the ecological function by natural rainfall in the wet season.
8.8.6 With the recommended mitigation measures, the impact severity is anticipated to be insignificant.
Mitigation Measures for Impact on Floral Species of Conservation Concern
8.8.7 Avoidance should be the first prioritised option for the impact on the subject plants. Though the two species are common in nature, preservation of them should be considered and this avoidance measure is likely practical for Pavetta hongkongensis as it is not situated on area proposed for permanent structures. Nevertheless if this option becomes impossible due to engineering, safety or other site constraints, transplanting the affected plants instead of felling should be implemented to minimise the impact.
8.8.8
The removal of the tree will be regulated by the
requirements stipulated in the relevant technical circular ETWB TCW No. 3/2006.
Although the individual is not suitable for transplanting for its low survival
rate after transplanting, compensatory planting is required for its removal
during the tree removal application stage in accordance with the technical
circular ETWB TCW No. 3/2006. Taking into the account only one individual is
affected and the species is very common in
8.8.9 As described in Section 8.6.10, preservation of the Artocarpus hypargyreus may not be feasible as it will be in direct conflict with the constructions. Although the individual is not suitable for transplanting for its low survival rate after transplanting, compensatory planting is required for its removal during the tree removal application stage in accordance with the technical circular ETWB TCW No. 3/2006. The compensatory planting plan regulated by the ETWB TCW No. 3/2006 will be reviewed and approved by the control authority AFCD before implementation
8.8.10 The impact severity of either unmitigated or mitigated condition is anticipated to be insignificant as only one individual of each species was involved.
Mitigation Measures for Direct Injury to Wildlife
8.8.11 Although the potential of direct injury to wildlife is predicted to be low, precautionary measures are recommended as below:
· Workers should avoid eating or leave food in the works area and feeding of wildlife, this could minimize the chance of attracting the wildlife especially the Rhesus Macaque to the works area to cause direct injury.
· If any fauna species are injured by accident, the species should be reported and handed to the Agricultural, Fisheries and Conservation Department.
· Fishes observed remaining at the proposed works area during the drain down process should be translocated to the portion of the reservoir outside the cofferdam.
8.8.12 The impact on direct injury to wildlife will be of insignificant with the implementation of good site practices.
Mitigation Measures for Dust Deposition on Vegetation
8.8.13 Standard good site practices for dust suppression as suggested in Chapter 3 were considered adequate to control the dust level. No additional measure is required.
Mitigation Measures for Impacts to Water Quality
8.8.14 Standard good site practices for site runoff control as suggested in Section 5.10 were considered adequate to maintain the water quality in acceptable level. No additional measure is required.
Mitigation Measures for Disturbance to Wildlife
8.8.15 Precautionary measures to minimize disturbances arising from the construction activities to wildlife are recommended as follows:
· Workers shall not disturb birds and other wildlife
· Litter shall not be burned on-site but shall be removed off-site
· Machinery not in use should be switched off to minimize the noise nuisance
· No fishing is allowed in the reservoir without permission
· Feeding prohibition
8.8.16 The implementation of precautionary measures and the provision of cofferdam to separate the works area from the remaining portion of the reservoir, the disturbance impacts to wildlife and fishes can be maintained in an acceptable level.
8.8.17 A summary of the recommended mitigation measures is presented below.
Table 8‑21 Summary of Recommended Mitigation Measures
Impacts |
Recommended Mitigation Measures |
Habitat Loss of: -
Secondary
-
Grassland -
Reservoir |
- Restoration of secondary woodland / plantation at Worksite Area at
Kowloon Byewash Reservoir by planting (species should be made reference to
the Tree Survey for this project) to compensate the temporary loss of the
same kind. The compensation ratio in terms of area should not be less than
1:1. - Restoration of grassland at Worksite Area at Lower Shing Mun
Reservoir by natural colonisation to compensate the same kind. The
compensation ratio in terms of area should not be less than 1:1. Although
active planting is not necessary for this type of habitat, suitable planting
soil should be provided for natural colonisation. - Apart from the Intake and outfall structures, the ecological
function of the reservoir will be restored after the removal of cofferdam and
associated structures and refill of the reservoir in the wet season by
natural rainfall. |
Impact on Floral Species of
conservation Concern |
- Preservation by onsite protection should be considered as
prioritised option. - Mitigation through either transplanting the affected plants or
compensatory planting if onsite preservation is not feasible. |
Direct Injury to Wildlife |
- Workers should avoid eating and leave food in works area and avoid
feeding the wildlife. - Fishes observed remaining at the proposed works area during the drain down process should be translocated to the portion of the reservoir outside the
cofferdam. |
Dust Deposition on Vegetation |
- Standard good site practices for dust suppression should be strictly
implemented. |
Impacts to Water Quality |
- Standard good site practices for dust suppression and avoidance of
chemical spillage should be strictly implemented. |
Disturbance to Wildlife |
- Workers shall not disturb birds
and other wildlife -Litter shall not be burned on-site but shall be removed off-site -Machinery not in use should be switched off to minimize the noise
nuisance -No fishing is allowed in the reservoir without permission |
8.8.18 In addition to the mitigation measures for the identified impacts, a potential enhancement measure of providing roosting surface for bats inside the proposed water tunnel was considered in the tunnel design stage. However, this option was found impractical due to the engineering constraint that the water tunnel will be of full-bore flow at its capacity.
8.9 Environmental Monitoring and Audit Requirements
8.9.1 The implementation of the ecological mitigation measures stated in Section 8.8 should be checked as part of the environmental monitoring and audit procedures during the construction period as presented in the separate Environmental Monitoring and Audit Manual. No other ecology-specific measures are considered necessary.
8.10.2 Six types of habitats were identified within the study area, including reservoir, secondary woodland / plantation, grassland, stream, drainage channel and developed area / bare ground. The habitats inside the boundaries of the proposed worksite areas were not of high ecological value.
8.10.3
The dominant faunal species recorded in
8.10.4 As the entire water tunnel will be constructed underground, the scale of surface construction works is limited in nature. The ecological impact with the implementation of recommended mitigation measures should be within acceptable level.
AFCD, 2001. Hong Kong Plant Check List 2001. HKSAR.
AFCD,
2003. Rare and Precious Plants of
Agriculture, Fisheries and Conservation Department (AFCD), 2008. Website: AFCD Kam Shan, retrieved on 21 February 2008: http://www.afcd.gov.hk/english/country/cou_vis/cou_vis_cou/cou_vis_cou_ks/cou_vis_cou_ks.html
Agriculture, Fisheries and Conservation Department (AFCD), 2008. Website: AFCD Lion Rock, retrieved on 21 February 2008: http://www.afcd.gov.hk/english/country/cou_vis/cou_vis_cou/cou_vis_cou_lr/cou_vis_cou_lr.html
Baillie, J. 1996. Hystrix brachyura. In: IUCN 2007. 2007 IUCN Red List of Threatened Species. <www.iucnredlist.org>. Downloaded on 23 February 2008.
Corlett, R. 2004. Macaques as seed predators
and dispersal agents in
Corlett, R.T., Xing,
F.W., Ng, S.C., Chau, L.K.C. and Wong, L.M.Y, 2000.
Carey, G.J., Chalmers, M.L., Diskin, D.A.,
Kennerley, P.R., Leader, P.J., Leven, M.R., Lewthwaite, R.W., Melville, D.S.,
Turnbull, M., and Yound, L.(2001): The
Avifauna of
Dudgeon, D. (2003). Hong Kong Field Guides 2: Hillstreams. The Department of Ecology
& Biodiversity, The
Environmental Resources Management (1999). Agreement No.
Fellowes, J.R., Lau, M.W.N., Dudgeon, D.,
Reels, G.T., Ades, G.W.J., Carey, G.J., Chan, B.P.L., Kendrick, R.C., Lee,
K.S., Leven, M.R., Wilson, K.D.P. and Yu, Y.T. (2002). Wild Animals to Watch:
Terrestrial and Freshwater Fauna of Conservation Concern in
Karsen S.J., Lau, M.W.N. and Bogadek, A.
(1998).
Lee, V.L.F., Lam, S.K.S., Ng, F.K.Y., Chan,
T.K.T. and Young, M.L.C. (2004). Field
Guide to the Freshwater Fish of
Lo, P.Y.F. (2004).
Shek, C.T. (2006). A Field Guide to the Terrestrial Mammals of
Shek, C.T., Chan, C. S. M. and Wan, Y.F.
(2007). Camera Trap Survey of
UNEP-WCMC. 24 February, 2008. UNEP-WCMC Species Database: CITES-Listed Species On the World Wide Web : http://www.cites.org/eng/resources/species.html
Viney, C., Phillipps, K. and Lam, C.Y.
(2005). The Birds of Hong Kong and
Wang, S. and Xie, Y. (2004).
Zheng, G.M. and Wang, Q.S. (1998).
9.1.1
This section sets out to assess the potential landscape
and visual impact of the proposed water tunnel between Kowloon Byewash
Reservoir and Lower Shing Mun Reservoir under the West Kowloon Drainage
Improvement – Lai Chi Kok Transfer Scheme - Inter-reservoirs Transfer Scheme
(IRTS). The project partly falls within the
9.1.2 The aim of this section of the report is to focus on the major intake and outlet structures at both ends of the proposed water tunnel between Kowloon Byewash Reservoir (Southern Portal) and Lower Shing Mun Reservoir (Northern Portal). This session also identifies the condition of existing landscape resources (LRs) and landscape character areas (LCAs), and the visual amenity and visually sensitive receivers (VSRs). The assessment identifies potential landscape and visual impacts that would occur during the construction and operation phases of the proposed above ground structure, recommends landscape mitigation measures to alleviate the impacts; and identifies residual effects apparent after mitigation. The report concludes by making specific recommendations for reducing the visual impacts caused by the proposed intake and outlet structures of the water tunnel.
9.2 Environmental Legislation, Standards and Legislation
9.2.1 The following legislation, standards and guidelines are applicable to the evaluation of landscape and visual impacts associated with the construction and operation of the project:
· Environmental Impact Assessment Ordinance (Cap.499.S.16) and the Technical Memorandum on EIA process (EIAO-TM), particularly Annexes 3, 10, 11, 18, 20 and 21;
· EIAO Guidance Note 8/2002;
·
· Forests and Countryside Ordinance (Cap 96) and its subsidiary legislations;
· Waterworks Ordinance (Cap 102);
· Country Parks Ordinance (Cap 208);
· Land Drainage Ordinance (Cap 446);
· Animals and Plants (Protection of Endangered Species) Ordinance (Cap 187);
· ETWBTC No. 29/93 – Control of Visual Impact of Slopes;
· ETWBTC No. 12/2000 - Improvement to the Appearance of Slopes in connection with WBTC 23/93;
· ETWBTC No. 7/2002 – Tree Planting in Public Works;
· ETWBTC No. 3/2006 –Tree Preservation;
· Land Administration Office Instruction (LAOI) Section D-12 – Tree Preservation;
· GEO publication (1999) – Use of Vegetation as Surface Protection on Slopes;
· GEO 1/2000 – Technical Guidelines on Landscape Treatment and Bio-engineering of Man-made Slopes and Retaining Walls;
· Outline Zoning Plan - Shatin (Plan No. S/ST/23)
· Outline Zoning Plan - Cheung Sha Wan (Plan No. S/K5/30)
9.3 Landscape and Visual Impact Assessment Methodology
9.3.1 Landscape and visual impacts have been assessed separately for the construction and operational phases. The assessment of landscape impacts has involved the following procedures.
1. Identification of the baseline landscape resources/ character areas found within the study area - This is achieved by site visit and desktop study of topographical maps, information databases and photographs.
2. Assessment of the degree of sensitivity to change of the landscape resources/ character areas - This is influenced by a number of factors including whether the resources/ character areas is common or rare, whether it is considered to be of local, regional, national or global importance, whether there are any statutory or regulatory limitations/ requirements relating to the resources, the quality of the resources, the maturity of the resource, and the ability of the resource to accommodate change.
9.3.2 The sensitivity of each landscape resource/ character area is classified as follows:
High: Important
landscape resource/ character area of particularly distinctive character or
high importance, sensitive to relatively small changes.
Medium: Landscape
resource/ character area of moderately valued landscape characteristics
reasonably tolerant to change.
Low: Landscape
resource/ character area, the nature of which is largely tolerant to change.
3. Identification of potential sources of landscape impacts. These are the various elements of the construction works and operation procedures that would generate landscape impacts.
4. Identification of the magnitude of landscape impacts. The magnitude of the impact (or magnitude of change) depends on a number of factors including:
· the physical extent of the impact,
· compatibility of the project with the surrounding landscape,
· duration of impacts i.e. whether it is temporary (short, medium or long term), under construction and operation phases, and
· reversibility of change
9.3.3 The magnitude of landscape impacts is classified as follows:
Large: The landscape
resource or character area would suffer a major change
Intermediate: The landscape resources or character area would
suffer a moderate change
Small: The landscape
resources or character area would suffer slight or barely perceptible change
Negligible: The landscape
resources or character area would suffer no discernible change
1. Identification of potential landscape mitigation measure - Mitigation measures may take the form of
· Adopting alternative design or revisions to the basic engineering the architectural design to prevent and/or minimize adverse impacts,
· Remedial measures such as colour and textual treatment of physical, engineering and building features,
· Compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc.) to compensate for unavoidable adverse impacts and to attempt potentially beneficial long term impacts.
A programme for
the mitigation measures is provided. The
agencies responsible for the funding implementation, management and maintenance
of the mitigation measures are identified.
2. Predicted significance of landscape impacts before and after the implementation of the mitigation measures - By synthesizing the magnitude of the various impacts and the sensitivity of the various landscape resources it is possible to categorize impacts in a logical, well-reasoned and consistent fashion. Table 9-1 shows the rationale for dividing the degree of significance into four thresholds, namely insubstantial, slight, moderate, and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of impact and a low-medium-high degree of sensitivity of landscape resources.
Table 9‑1 Relationship between Landscape Resources/ Character Area Sensitivity and Impact Magnitude in Defining Impact Significance
Magnitude of |
Large |
Slight /
Moderate |
Moderate/ |
Substantial |
Intermediate |
Slight /
Moderate |
Moderate |
Moderate
/ |
|
Small |
Insubstantial
/ |
Slight /
Moderate |
Slight /
Moderate |
|
Negligible |
Insubstantial
|
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Receptor
Sensitivity (of
Landscape Resources/ Character Area) |
3. Prediction of Acceptability of Impacts - An overall assessment of the acceptability, or otherwise, of the landscape impacts according to the five criteria set out in Annex 10 of the EIAO TM.
9.3.4 The assessment of visual impacts involves the followings:
1. Identification of Zones of Visual Influence (ZVIs) during the construction and operation phase of the Project. This is achieved by site visit and desktop study of topographic maps and photographs, and preparation of cross-section to determine visibility of the project from various locations.
2. Identification of Visual Sensitive Receivers (VSRs) within the Zone of Visual Influence (ZVIs) at construction and operation stages. These are the people who would reside within, work within, play within, or travel through, the ZVIs.
3. Assessment of the degree of sensitivity to change of the VSRs. Factors considered include:
· the type of VSRs, which is classified according to whether the person is at home, at work, at school, at construction and operation stages. These who view the impact from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life. Those who view the impact from their workplace of and at school are considered to be only moderately sensitive as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life. The degree to which this applies depends on whether the workplace is industrial, retail or commercial. Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity. Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel.
· Other factors which are considered (as required in the EIAO GN 8/2002) include the value and quality of existing views, the availability and amenity of alternative views, the duration or frequency of view, and the degree of visibility.
9.3.5 The sensitivity of VSRs is classified as follows:
High: The VSR is highly
sensitive to any change in their viewing experience.
Medium: The VSR is
moderately sensitivity to any change in their viewing experience.
Low: The VSR is only slightly
sensitive to any change in their viewing experience.
4. Identification of relative numbers of VSRs - this is expressed in term of whether there are very few, few, many or very many VSRs in any one category of VSR
5. Identification of potential sources of visual impacts - these are the various elements of the construction works and operation procedures that would generate visual impacts.
6. Assessment of the potential magnitude of visual impacts. Factors considered include
· the compatibility with the surrounding landscape,
· the duration of the impact,
· the reversibility of the impact,
· the scale of the impact and distance of the source of impact from the viewer, and
· the blockage of view
9.3.6 The magnitude of visual impacts is classified as follows:
Large: The VSRs would
suffer a major change in their viewing experience
Intermediate: The VSRs would suffer a moderate change in their
viewing experience
Small: The VSRs would
suffer a small change in their viewing experience
Negligible: The VSRs would
suffer no discernible change in their viewing experience
7. Identification of potential visual mitigation measures - These may take the form of adopting alternative designs or revisions to the basic engineering and architectural design to prevent and/or minimize adverse impacts, remedial measures such as colour and textural treatment of building features, and tree planting to screen the roads and associated structures. A programme for the mitigation measures is provided. The agencies responsible for the implementation, management and maintenance of the mitigation measures are identified and their approval-in-principle has been sought.
8. Prediction of the significance of visual impacts before and after the implementation of the mitigation measures - by synthesizing the magnitude of the various visual impacts and the sensitivity of the VSRs, and the numbers of VSRs that are affected, it is possible to categorize the degree of significance of the impacts in a logical well-reasoned and consistent fashion. The degree of significance are divided into four thresholds, namely, insubstantial, slight, moderate and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of impact and a low-medium-high degree of sensitivity of VSRs.
9.3.7 The significance of visual impacts is categorized as follows:
Substantial: Adverse /
beneficial impact where the proposal would cause significant deterioration or
improvement in existing visual quality
Moderate: Adverse /
beneficial impact where the proposal would cause noticeable deterioration or
improvement in existing visual quality
Slight: Adverse /
beneficial impact where the proposal would cause barely perceptible
deterioration or improvement in existing visual quality
Insubstantial: No discernible change in the existing visual quality
9. Prediction of acceptability of impacts - an overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM.
9.3.8 It is assumed that funding, implementation, management and maintenance of the mitigation proposals can be satisfactorily resolved according to the principles in WBTC 3/2006. All mitigation proposals in this report are practical and achievable within the known parameters of funding, implementation, management and maintenance. The suggested agents for the funding and implementation (and subsequent management and maintenance, if applicable) are indicated in Table 9-6. Approval-in-principle to the implementation, management and maintenance of the proposed mitigation measures is being sought form the appropriate authorities.
9.4.1
As a part of the overall flood control strategy for
Southern Portal
9.4.2 The construction of the intake structure requires excavation of the existing ground profile from approximately +120.0mPD to +108.0mPD where the tunnel opening is located with a portal wall above. A circular weir with the radius of 10m and the weir level at +115.0mPD will be situated surrounding the tunnel opening.
Northern Portal
9.4.3 The construction of the outfall structure requires excavation of existing ground profile to the future ground level of +82.0mPD. An energy dissipater will be constructed in associated with the outfall structure with RC wing wall at both sides. The gabions steps will be situated 8m in front of the tunnel opening with the height of 4m. The size of the outfall structure will be 20m in length and 12m in width.
9.5 Review of Planning and Development Control Framework
9.5.1
The proposed water tunnel has been reviewed against a
number of relevant Outline Zoning Plans of Kowloon and
Southern Portal
9.5.2 The landscape-related land use zonings present in the Study Area surrounding the Southern Portal and relevant to the LVIA are as follows:
· Green Belt (GB) – the planning function of GB is to limit the encroachment of urban development into the countryside.
· Residential Group C (R(C)4) – the planning function of R(C)4 is to allow low-to-medium density residential developments.
· Government, Institution or Community (G/IC) – the planning function of (G/IC) is to provide land for uses directly related to or in support of the work of the Government, organizations providing social services to meet the community needs.
Northern Portal
9.5.3 The landscape-related land use zonings present in the Study Area surrounding the Northern Portal and relevant to the LVIA are as follows:
· Green Belt (GB) – the planning function of GB is to limit the encroachment of urban development into the countryside.
· Residential Group B (R(B)) – the planning function of R(B) is to allow medium density residential developments.
· Government, Institution or Community (G/IC) – the planning function of (G/IC) is to provide land for uses directly related to or in support of the work of the Government, organizations providing social services to meet the community needs.
9.5.4 No part of the proposed water tunnel will be constructed through any of the above landscape zonings, therefore the Project is considered not to be in conflict with the landscape zonings in the area. Therefore the proposals will fit within the future landscape planning framework as represented by the OZPs and so no amendment to the published land use plans is required.
9.6 Landscape and Visual Baseline Study
9.6.1 The baseline landscape resources that would be affected during the construction phase and operation phase, together with their sensitivity to change, are described below. The locations of baseline landscape resources are mapped in Figure 9-1a and 9-1b.
LR1
– Mixed
9.6.2 This LR refers to the continuous secondary forests and fragmented plantation forests covering hillsides and slopes around Kowloon Byewash Reservoir and Lower Shing Mun Reservoir. These provide contribute to the quality of the mountain setting and form a green backdrop to views for trail walkers at both the reservoir areas, and for the residents at Caldecott Road and Sha Tin Heights. Since all works for the connecting tunnel will be undertaken using a tunnel boring machine (TBM) the affected woodland areas are mainly concentrated at the South and North Portals where the construction of the above ground structures is required. Regarding the conditions of existing trees near the affected areas, tree surveys have been conducted for both portals of the Proposed Water Tunnel and the results of the survey are presented below.
Existing Trees - Southern Portal
9.6.3 The main concentration of trees is located on the back slope to the north of the proposed intake structure. The site contains some 262 trees as described in the preliminary tree survey schedule in Appendix I (KBR) prepared by Mott MacDonald Hong Kong Limited. Some of the trees are non-native plantation species which were planted as part of the greening of the slopes in the past. The typical plantation species include Acacia confusa and Eucalyptus robusta; and the main native species include Celtis sinensis, Schefflera heptaphylla, Sterculia lanceolata, Artocarpus hypargyreus, Aporusa dioica, Antirhea chinensis and Acronychia pedunculata etc. Despite their origins, these trees contribute to the landscape and visual amenity of the site and the local area. Generally the trees have an average form, fair condition and good amenity value. None of the surveyed trees were categorized as a ‘Significant Tree’ with a Diameter Breast Height (DBH) of over 1m.
Existing Trees - Northern Portal
9.6.4 The main concentration of trees is located on the slope to the south on the back slope above the proposed outfall structure. The site contains some 203 trees as described in the preliminary tree survey schedule in Appendix I (LSMR). Similarly a number of the tree species are non-native being planted as part of greening of the reservoir access road and slopes. The typical plantation species include Acacia confusa and Schima superba while the main native species include Ixonanthes reticulata, Schefflera heptaphylla, Diospyros morrisiana, Schima superba, Garcinia oblongifolia and Mallotus paniculatus. Again these trees contribute to the landscape and visual amenity of the site and the local area. Generally the trees have an average form, fair condition and good amenity value. None of the surveyed trees were categorized as ‘Significant Tree’ with a DBH of over 1m.
9.6.5 No rare or protected tree species (based on Forests and Countryside Ordinance, Cap. 96) or Champion Trees (identified in the book ‘Champion Trees in Urban Hong Kong’) were found in both portal areas.
9.6.6 As this LR is one of the key resources of the area with a high landscape value, and trees are relatively mature and of a generally fair condition; and despite there being a combination of native and exotic plantation species, the sensitivity to change for LR1 is High.
LR2
– Modified Water Course
9.6.7
The Study Area covers two main reservoir systems in
LR3
– Developed Areas
9.6.8
These landscape resources include the existing
residential groups comprising of medium-rise residential buildings. These are mainly located at the northern and
southern edge of the Study Area. Apart
from residential groups, there are a number of government institutional
buildings including the staff quarters
and WSD maintenance areas situated the southern edge of the Study Area.
In addition to the institutional buildings, an Over Head Line Training School
with access road located at the northern part. These
landscape resources also include part of
Landscape Character Area (LCA)
9.6.9 The following landscape character areas are identified and described below, and their locations are mapped in Figure 9-2.
LCA1
– Kowloon Reservoir Group LCA
9.6.10
This LCA refers to the entire system of Kowloon
Reservoir Group including the Shek Lei Pui Reservoir, Kowloon Reservoir,
Kowloon Reception Reservoir, Kowloon Byewash Reservoir, the upstream catchwater
course linked to the reservoir group and the hillside enclosing the reservoir
group. This LCA is formed by the steep
wooded hill sides which enclose the valleys containing the reservoir
system. The water body with is bare rock
strewn shores and man-made features such as the dam structures and access roads
form an important part of the landscape character. The enclosing hillside and upstream courses
connected to catchwater form a remnant of the natural valley landscape
character. The existing vegetation which
encloses this area is formed from secondary forests and plantation trees on the
hillsides. Based on the overall quality
of this LCA and considering its importance to the landscape and visual amenity
of the
LCA2
–
9.6.11
This is characterized by the Lower Shing Mun Reservoir,
the catchwater linked to the reservoir and the enclosing wooded hillsides. This LCA shares the same landscape attributes
as those described for LCA1 above. The
LCA is bisected by the boundary of the
LCA3
– Sha Tin Height Urban Fringe LCA
9.6.12 This LCA is characterized by low to medium-rise residential development. These are a residual landscape type characteristic of the transition from urban to rural, the urban fringe type development. Two minor peaks located to the north and south with the levels of about +160mPD are identified with low to medium-rise residential blocks. A valley is located between two minor peaks with a level of +120mPD. The hillside is generally clothed with dense secondary forest with more composition of shrubs when it comes to higher altitude.
9.6.13 The dense vegetation which extends from the Green Belt areas provide the setting for the residential development and contribute to its integration within the existing landscape context. As a consequence the residential development is relatively inconspicuous within the overall landscape of the Study Area. The sensitivity to change of LCA3 is regarded as Medium.
LCA4
– Cheung Sha Wan Urban Fringe LCA
9.6.14
This LCA forms part of the urban fringe or transition
from the urban Cheung Sha Wan area to the
Landscape Sensitivity to Change
9.6.15 The landscape resources (LR) and landscape character areas (LCA) that would be potentially affected during the construction phase and operation phase, together with their sensitivity to change, are summarised in Table 9-2.
Table 9‑2 List of Landscape Resources / Landscape
Character Areas and their Sensitivity to Change
IID. No.
|
Landscape Resource / |
Sensitivity to Change |
|
Landscape Resource |
|
LR1 |
Mixed |
High |
LR2 |
Modified
Water Course |
Low |
LR3 |
Developed
Areas |
Low |
|
Landscape Character Area |
|
LCA1 |
Kowloon
Reservoir Group LCA |
High |
LCA2 |
|
Medium |
LCA3 |
Sha Tin
Height Urban Fringe LCA |
Medium |
LCA4 |
Cheung
Sha Wan Urban Fringe LCA |
Low |
Figure 9-3a-d illustrate the photographic record of the site
context and identified LRs / LCAs.
Existing Visual Context
Visual
Envelope
9.6.16 As the Project includes two portals of the proposed water tunnel, where underground tunnel alignment is not observable, visual envelope, the area from which the proposed intake structures will be seen, is divided into two parts, i.e. the area around the Southern Portal and that of the Northern Portal. Figure 9-3a-b illustrate the photographic record of site context at both Southern and Northern Portal.
Southern Portal
9.6.17
The visual envelope for the Southern Portal is shaped
by the upland landscape which surrounds it including the ridge line of the
Eagle’s Nest and associated foothills to the east. Views from the north are
contained by the existing undulating topography and it’s covering of dense
vegetation along both sides of the Kowloon Byewash Reservoir. The top of the main dam structure is evident
in these views. The visual envelope to
the west is also contained by the densely vegetated hillside behind the
proposed intake structure. To the south,
the visual envelope is shaped by the existing landform extending across the
valley to the residential development adjacent to
9.6.18 When viewed from close proximity the site context is dominated by existing dam structure and the water body of Kowloon Byewash Reservoir, situated next to the proposed intake structure (refer to Figure 9-3a – Photographic Record of the Site Context). The following views provide an indication of the character of the site and its surroundings:
9.6.19 Views to the northwest (viewpoint 1) from the existing Kowloon Byewash Reservoir dam show the roadway on top of the dam structure connecting to Cheung Yuen Road. The proposed location of the intake is located on the rocky shore to the north (right) of the dam structure. The view shows a panorama extending north east to the end of the reservoir. The image shows the screening effect of the landform and mature vegetation at the edge of the reservoir. Although the summit of Golden Hill is visible in this view it does demonstrate the screening effect of the intervening landscape features for views beyond the edge of the reservoir.
9.6.20 The view to the northeast (viewpoint 2) from the existing Kowloon Byewash Reservoir dam show a more detailed view of the proposed location for the Intake structure. The site is one formed from a combination of rock outcrops and a sandy rock strewn beach area which is exposed when the reservoir is low. Again the screening effect of the vegetation at the edge of the reservoir is apparent in this view.
9.6.21 Views to the southwest (viewpoint 3) from the existing Kowloon Byewash Reservoir dam shown the area to the south of the dam structure. Visible at the end of the dam on the hillside is the 2-storey high former WSD staff quarters. The view from this location is characterized by the landscape of the natural valley although the valley floor is dominated by the structures associated with the reservoir. The view shows the steep sides of the valley clothed by mature woodland. As with the other view points views towards the dam and the proposed site are largely enclosed by the landform and vegetation which form the valley sides.
9.6.22
The view to the west and southeast (viewpoint 4) from
the dam form a continuation of viewpoint 2 and shows the south eastern shore of
the reservoir with its steep terrain and dense vegetative covering. The eastern shore of the reservoir with its
steep wooded sides and the summit of the Eagle’s Nest appearing above are
clearly visible. The 2-storey high
former WSD staff quarter is visible together with the elevated dam structure as
a part of
Northern Portal
9.6.23
The visual envelope for the proposed outfall structure
is shaped by the natural elevated topography including the summit and ridges of
Needle Hill,
9.6.24
The visual envelope to the north (viewpoint 1) is
contained by a combination of the landform and vegetation of the valley sides
and the wooded hillside of Sha Tin Height in the background. It should be noted that the reservoir is
currently drained to facilitate the proposed works hence the extensive
visibility of rock and gravel surfaces.
A shotcrete slope is visible mid-way up the wooded slope to the north of
the proposed structure. The
9.6.25 Views to the southwest (viewpoint 2) from the maintenance track on the north eastern side of the valley are enclosed by the vegetated landform on the slopes above the reservoir. The cut slope in the central portion of the picture shows the extensive modification of the existing landform which was undertaken in the past to accommodate the reservoir and its associated structures. Above the cut slope the landscape is one characterized by the secondary woodland.
9.6.26
Views to the east (viewpoint 3) taken from the same
location of viewpoint 1 show the reservoir maintenance access road lined by
extensive tree and shrub planting. This
vegetation coupled with the steep landform serve to contain the visual envelope
extending east from the reservoir. The
extension of the valley leading to
9.6.27
Views to the east (viewpoint 4) taken from the
southeastern shore of the reservoir show the farmed view towards the
residential development of
9.6.28 Views to the northwest (viewpoint 5) taken from the same location as viewpoint 4 are partially blocked by the vegetated slopes to the east and west of the valley however these views and hence the visual envelope extends north to the summit of Needle Hill and the extensive foothills to the south.
Zone
of Visual Influence (ZVI)
9.6.29 The primary ZVI for the Project during the construction phase are illustrated in Figure 9-4a-b with annotated locations of Visual Sensitive Receivers.
Visual
Sensitive Receivers (VSRs)
9.6.30 Table 9-3 lists the key VSRs found within the ZVIs. For ease of reference, each VSR is given an identity number, which is used in all relevant tables and figures in this report.
Table 9‑3 Key VSRs Identified within the ZVIs
ID. No. |
Key
Visual Sensitive Receivers (VSRs) |
Type of
VSRs |
Number
of Individuals |
Quality
of Existing View |
Availability
of Alternative Views |
Degree
of Visibility |
Frequency
of View (Very Frequent/ Frequent/ Occasional/ Rare |
Sensitivity
to Change |
R1 |
Residents of |
Residential |
Large |
Good |
Yes |
Partial |
Occasional |
High |
R2* |
Residents of |
Residential |
Large |
Good |
Yes |
Partial |
Occasional |
High |
T1 |
Visitors in |
Traveller |
Intermediate |
Good |
Yes |
Full |
Occasional |
High |
T2 |
Trail Walkers in |
Traveller |
Few |
Good |
Yes |
Full |
Occasional |
High |
*No access for viewing from R2 was allowed; assessment
is therefore made by assumption
9.7 Landscape Impact Assessment
Sources of Landscape Impacts
Construction Phase
9.7.1 Sources of impacts in the construction phase would include:
· Construction of intake and outfall structure;
· Temporary loss of vegetative cover including trees at both the site of the intake and the outfall;
· Construction of temporary site access to the works areas at southern portal;
· Associated slope works around the intake and outfall structure;
· Construction of temporary cofferdam;
· Temporary site office, parking area, material storage, workshop, de-silting facilities, site cabins and heavy machinery;
· Temporary road diversion at northern portal;
· Temporary diversion of culverts at northern portal; and
· Construction site traffic.
Operational phase
9.7.2 Sources of impacts in the operational phase would include:
· The appearance of the intake and outfall structures, and
· Partial refill of Lower Shing Mun Reservoir with stormwater diverted from Kowloon Byewash Reservoir. (Existing drought reservoir is due to concurrent WSD’s maintenance work)
Nature and Magnitude of Impacts of Unmitigated Landscape Impact during the Construction and Operational Phases
9.7.3 The magnitude of the impacts, before implementation of mitigation measures, on the landscape resources and character areas that would occur in the construction and the operation phase are described and tabulated in Table 9-4. All impacts are adverse unless otherwise stated.
Table 9‑4 Significant
Landscape Impacts of the Proposed Works during Construction and Operation Phase
ID. No. |
Landscape Resources / |
Source of Impact |
Description of Impacts |
Magnitude of Change |
|
Construction |
Operation |
||||
LR1 |
Mixed (Approx. area: 319ha) |
Construction
of intake and outfall structure |
Southern
Portal ․ About
212m2 of woodland
(0.006% of total area of LR1) within ․ About
2366.11m2 of woodland (0.07%
of total area of LR1) within ․ About 19
trees would be affected by permanent works Northern
Portal ․ About
4561.17m2 of government land (0.14%
of total area of LR1) would be temporarily affected at
Northern Portal ․ About 42 trees
would be affected by permanent works. |
Small |
Small |
LR2 |
Modified
Water |
Construction
of intake and outfall structure with associated slope works |
Southern
Portal ․ Reform
of sloping ground inside Reservoirs Northern Portal ․ Reform
of sloping ground inside Reservoirs ․ Culvert
would be temporarily diverted |
Intermediate |
Small |
LR3 |
Developed
Areas |
Nil |
N. A. |
Negligible |
Negligible |
LCA1 |
Kowloon
Reservoir |
Construction
of intake structure |
․
About 2366.11m2 of
government land within ․
About 212m2 of
government land within ․
About 19 nos. of
existing trees would be affected by the permanent works |
Small |
Small |
LCA2 |
|
Construction
of outfall structure |
․ About
4561.17m2 of government land would be temporarily
affected ․ About 42 nos. of
existing trees would be affected by the permanent works ․ Refill
of currently dry reservoir with diverted stormwater from Kowloon Byewash
Reservoir during operation |
Small |
Small |
LCA3 |
Sha Tin
Height |
Nil |
N. A. |
Negligible |
Negligible |
LCA4 |
Cheung
Sha Wan |
Nil |
N. A. |
Negligible |
Negligible |
Visual Impacts during Construction Phase
9.8.1 The visual impacts on existing views during construction will be generated by the removal of existing vegetation, the associated slope works, and the activity generally associated with construction works such as machinery, temporary buildings and hoarding.
Visual Impacts during Operational Phase
9.8.2 The visual impacts on existing views during operation will be generated by the appearance of the intake and outfall structures.
9.8.3 As it is impossible to accurately portray the appearance of the Project during construction, visual changes are illustrated in Figure 9-5a-j by comparing the existing views to those immediately after construction and assuming no mitigation measures in place.
9.8.4 The magnitude of the impacts, assuming no mitigation measures on the VSRs that would occur in the construction and operation phase are described and tabulated in Table 9-5. All impacts are adverse unless otherwise stated.
Table 9‑5 Significant
Visual Impacts of the Proposed Works during Construction and Operation Phase
ID. No. |
Key
Visual Sensitive Receivers (VSRs) |
Blockage
of View |
Viewing
Distance |
Scale of
Development |
Compatibility |
Reversibility
of Change |
Magnitude of Change |
|
Construction |
Operation |
|||||||
R1 |
Residents
of |
Glimpse |
200 |
Medium |
Fair |
No |
Small |
Small |
R2 |
Residents
of |
Glimpse |
600 |
Medium |
Fair |
No |
Small |
Small |
T1 |
Visitors
in |
Glimpse |
20 |
Medium |
Fair |
No |
Large |
Intermediate |
T2 |
Trail
Walkers in |
Glimpse |
20 |
Medium |
Fair |
No |
Large |
Intermediate |
9.9 Landscape and Visual Mitigation Measures
Introduction
9.9.1 The rationale behind landscape mitigation measures is described in Section 9.3.2 to 9.3.3 including the feasibility of mitigation measures in respect to funding, implementation phasing and their management and maintenance.
Landscape Mitigation Measures
9.9.2 The proposed landscape mitigation measures for the construction phase of the Project are listed in Table 9-6, together with an indication of Funding, Implementation and Maintenance and relevant Authorities. Generally, all landscape mitigation measures are to be implemented as early as possible and they are illustrated in Figure 9-6a-b.
9.9.3 The areas to receive LMM3 – Compensatory Tree Planting (Heavy Standard Trees) are as follows:
· Southern Portal: 31 trees (Heavy Standard); and
· Northern Portal: 82 trees (Heavy Standard).
9.9.4 The proposed species to be used for the compensatory tree planting comprise of a woodland mix including both native tree species and some pioneer tree species including the following species: Celtis sinensis, Cinnamomum camphora, Bauhinia blakeana, Cinnamomum burmanni, Ficus microcarpa, Ficus variegata var. chlorocarpa.
Tree Preservation
9.9.5 The tree survey schedules in Appendix I contain detailed information about the trees around both southern and northern portals.
9.9.6 For trees not covered under ETWB No. 29/2004; i.e. all trees in the Study Area, the following order of priority was adopted for tree felling considerations:
1. Retain the trees at their existing locations;
2. If (1) is not possible, transplant the affected trees to other permanent locations near the site, unless the trees affected are of low conservation and amenity value, or have low survival rates or a low chance of recovering normal form after transplanting;
3. If both (1) and (2) are not possible, transplant the trees affected to a permanent, local, offsite location. Only trees with high conservation value or high amenity value, including rare and precious species and ‘transplantable’ trees are considered for this option.
4. Felling of trees to be considered as a last resort under the following circumstances:
· There is no other practical alternatives; or
· The tree(s) has unrecoverable health problems and is in poor condition; or
· Other justifications are provided by the project proponent.
9.9.7 The preliminary treatment of the existing trees on site is listed in Appendix I Tree Survey Schedule with relevant statistics.
Measures for Preservation and Protection of Trees
9.9.8 During construction progress, the Contractor are requested to carefully preserve retained trees and submit a Tree Preservation and Protection Plan to the ET for review and Engineering for approval before commencing of any works on site.
9.9.9 During the construction phase of the project it is important that the existing trees including all of the preserved and transplanted trees, be protected from the construction activity. As part of the tree protection measures a protection zone known as the ‘Cordon Area’ will be established around the existing trees or tree groups taking the canopies of the outermost trees as a guide to its extent. This Cordon Area is designed to prevent unauthorized access to the trees and to protect the soil and roots therein from disturbance. It will be protected by chain link fencing to prevent unauthorized access. The footings for the fencing should not infringe upon the proposed Cordon Area. It will be closed to all construction activity apart from the proposed tree preservation works and prevent potentially detrimental activities such as the storage of materials including fuel, the movement of construction vehicles, and the refuelling and washing of equipment occurring within the area of the tree canopy. The fencing shall be erected prior to the commencement of the construction phase operations and remain in place until their completion.
9.9.10 The retained trees, particularly the root systems, are potentially sensitive to runoff and contamination from adjacent construction activity. Therefore measures will be implemented to protect the trees including:
· Prevention of runoff from adjacent construction activities entering the root zone of the retained trees. Contamination through the soil of the preserved root area shall be strictly prohibited through the use of a protective rim along the base of the fence at the edge of the cordon area. This protective rim will be constructed from a waterproof membrane weighted down with sand bags.
· Prevention of chemical and mechanical damage to the trunk, branches and foliage, and the soil bed of trees immediately adjacent to the construction works through the erection of a bamboo scaffolding and transparent polythene sheeting during the proposed construction activities. This will prevent damage to the trees while maintaining solar radiation access and gaseous exchange needed for continued photosynthesis and respiration.
· Pollution control will also be addressed at the source particularly in respect to the piling machines and their associated equipment.
9.9.11 Other considerations for the protection of the existing trees include the following measures:
· The root collar of each tree shall be marked prior to the commencement of works to ensure that the finished soil level after the completion of the works will be the same as the marked collar level. The finished soil level below the retained trees will be same as the existing level.
· Excessive water shall be drained away from the tree protection zones to prevent damage to tree roots by asphyxiation.
· Where possible measures will be taken to ensure that plumes of exhaust fumes, smoke and heated air generated by construction vehicles, machines and equipment will not drift into the Cordon Area.
· Measures will be undertaken to ensure that lifting equipment with cable, pulley gears and haulage will not sail above the Cordon Area.
· Watering of existing vegetation particularly during periods of excavation.
· The rectification and repair of damaged vegetation following the construction phase to its’ original condition prior to the commencement of the works or replacement using specimens of the similar or comparable species, size and form where appropriate to the design intention of the area affected.
9.9.12 The Contractor should erect, secure and maintain in good condition temporary protective fencing to protect the preserved trees before commencement of any works within the site. The Contractor should submit method statements including proposed design details of the temporary protective fencing to the ET for review and to the Engineer for approval.
9.9.13 The Contractor should follow all requirements listed in the General Specification for Civil Engineering Works: Section 26 – Preservation and Protection of Trees.
9.9.14 Where advanced tree works including surgery or pruning may be necessary for the enhancement of tree health as well as appearance, the Contractor should provide detailed proposals and method statements to the ET for review and to the Engineer for approval before commencement of any tree surgery or tree pruning works. Pruning should be conducted in accordance with good arboriculture and horticultural practices.
9.9.15 A competent member of the site supervisory staff should be assigned by the Contractor to oversee and supervise tree works related to horticultural operations and preservation of trees within the site, including but without limitation to, planting, transplanting, tree surgery work, pruning and disease or pest control affecting trees on site.
9.9.16 A number of trees were found to be in direct conflict with the works due to their position on the proposed works area for slope regarding works at both portals and permanent access road at southern portal. Trees suitable for transplant within the areas were identified based on the following criteria:
1. Health – healthy, free of disease, infestation and undamaged.
2. Species – rare species deserve higher rating of retaining. No rare species was found in the Project Area. Native trees reserve higher ecological value than exotic tree species by supporting local ecosystem, which native trees deserve higher rating in transplanting priority. Therefore, good specimen of native trees are good candidates for transplanting.
3. Size – large trees, 500mm girth or larger (at breast height), which require specialized method to transplant, and have relatively lower survival rate than juvenile trees
4. Form – Trees of poor form (e.g. serious leaning, forked or multi-stem trees) increase difficulty in transplantation.
5. Location – Trees situated in positions that are difficult to transplant from due to their direct conflict with the proposed structures or slope regarding works makes careful excavation or protection of their roots impossible. Trees may also located at slopes which are not suitable for transplanting due to the nature of their distorted root orientation.
Compensatory Tree Planting (LMM3)
9.9.17 Where trees cannot be retained or transplanted and have to be felled, compensatory tree planting (LMM3) is proposed as shown in Figure 9-6a-b. In addition, existing retained and new slopes or open space should be planted with suitable tree planting mix for greening and screening views as mitigation purposes. Based on the current available information, the approximate numbers of trees to be felled and compensated are summarized below.
Portal |
Felled Trees |
Compensatory Planting |
Replanting Ratio |
Southern Portal |
19 |
31 |
1: 1.93 |
Northern Portal |
42 |
82 |
1: 1.95 |
Total |
61 |
113 |
|
Note:
The results will be subject to the finalisation of the Tree Survey Report
Old & Valuable Trees (OVT) / Trees for Religious Rituals
9.9.18 No OVT or trees for religious rituals have been identified.
Landscape Plan
9.9.19 As the landscape design for the scheme is at a preliminary stage the details of the landscape mitigation measures have sought to establish the conceptual approach to the design and establish the number and location of the proposed tree planting. The Landscape Plan includes the location, size, number and species of plantings, the implementation programme, and the maintenance and management schedules. The Landscape Plan should be read in conjunction with the Ecology Impact Assessment chapter (See Section 8). The landscape Plan shall be certified by the ET Leader and verified by the IEC to confirm that it conforms with the recommendations set out in the approved EIA Report before submission to the relevant authorities.
Table 9‑6 Proposed
Construction Phase Landscape and Visual Mitigation Measures
Mitigation Measure |
Landscape and Visual Mitigation Measures |
Funding Agency |
Implementation
|
Maintenance Agency |
LMM1 |
Topsoil, where identified, should be stripped and
stored for re-use in the construction of the soft landscape works, where
practical. |
WSD |
WSD |
N/A |
LMM2 |
Existing Trees to be retained on site should be
carefully protected during the construction phase. |
WSD |
WSD |
WSD / AFCD |
LMM3 |
Compensatory tree planting should be provided to
compensate for felled trees. |
WSD |
WSD |
WSD / AFCD |
LMM4 |
Erection of decorative screen hoarding compatible
with surrounding setting. |
WSD |
WSD |
N/A |
LMM5
|
Locations of the site office, storage or
workshops should be carefully adjusted to areas out of tree protection zones. |
WSD |
WSD |
N/A |
LMM6 |
Selection of portals to areas enclosed by
existing topography or vegetation. |
WSD |
WSD |
N/A |
LMM7 |
Appearance of the water intake and outfall
structures will be of optimal size and colour that
fuses with the surrounding environment |
WSD |
WSD |
WSD |
LMM8 |
Reinstatement of disturbed vegetation
at both portal areas |
WSD |
WSD |
AFCD |
9.10 Residual Environmental Impact
Residual Landscape Impacts
9.10.1 The residual landscape impacts are defined and assessed with reference to Sections 9.3.2 to 9.3.4. Figure 9-6a-b illustrate the proposed landscape mitigation measures that would be incorporated into the Project to mitigate landscape impacts. Residual landscape impacts on landscape resources and landscape character areas are summarized in Table 9-7.
9.10.2 The primary impact would be on the mixed woodland due to the direct conflict between existing trees and the proposed works. Some 19 trees in total would be affected due to the construction of temporary site access at southern portal, associated slope works and construction of intake structure. 31 new trees would be compensated within study area for the loss of greenery from the proposed work. The detail compensatory plan is provided as Figure 9-6a-b. No Champion Trees or Registered Old and Valuable Trees, rare or endangered species were found near both portal areas. The detailed tree preservation, transplanting and felling including the compensatory planting proposals shall be submitted to relevant government departments for approval in accordance with ETWB TCW no. 3/2006. The overall residual impacts on the existing woodland will become insubstantial with the implementation of the recommended mitigation measures.
Residual Visual Impacts
Construction Phase
9.10.3 The residual visual impacts in the Construction Phase are listed in Table 9-8. After implementation of mitigation measures, some adverse residual visual impacts still exist and are shown in Table 9-8.
9.10.4 Moderate adverse impacts would be posed to the VSRs adjacent or close to the works area, i.e. R1 and R2 would receive moderate impacts. VSRs, T1 and T2, are occasionally with close distance to the works area. Therefore, the impacts would be moderate adverse.
Operation Phase
9.10.5 Residual visual impacts in the Operation Phase are listed in Table 9-8. In the Operation Phase, day 1 after implementation of proposed mitigation measures, residual visual impacts of some VSRs are slight, i.e. R1 and R2. When it comes to 10 years after the implementation of proposed mitigation measures, residual visual impacts on R1 and R2 would become insubstantial. For VSRs T1 and T2, due to the permanent existence of the intake and outfall structure in reservoir area, the residual visual impacts would be slight with the reinstatement of woodland.
Table 9‑7 Summary
of Landscape Impact
ID No. |
Landscape Resource / |
Sensitivity to Change (Low, Medium, High) |
Magnitude of Change (Negligible, Small,
Intermediate, Large) |
Impact Significance before Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended Mitigation Measures |
Impact Significance Day 1 after Mitigation |
Impact Significance 10 years after
Mitigation |
||||
(Insubstantial,
Slight, Moderate, Substantial) |
|||||||||||
Con |
Oper |
Con |
Oper |
Con |
Oper |
Con |
Oper |
Oper |
|||
|
|
|
|
|
|
|
|
|
|
|
|
LR1 |
Mixed |
High |
High |
Small |
Small |
Moderate
adverse |
Moderate
adverse |
LMM1 to
LMM8 |
Slight
adverse |
Slight
adverse |
Insubstantial |
LR2 |
Modified
Water Course |
Low |
Low |
Intermediate |
Small |
Moderate
adverse |
Slight
adverse |
LMM4,
LMM7 |
Slight
adverse |
Insubstantial |
Insubstantial |
LR3 |
Developed
Areas |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
Not
required |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
|
|
|
|
|
|
|
|
|
|
LCA1 |
Kowloon
Reservoir |
High |
High |
Small |
Small |
Moderate
adverse |
Moderate
adverse |
LMM1 to
LMM8 |
Slight
adverse |
Slight
adverse |
Insubstantial |
LCA2 |
|
Medium |
Medium |
Small |
Small |
Moderate
adverse |
Moderate
adverse |
Slight
adverse |
Slight
adverse |
Insubstantial |
|
LCA3 |
Sha Tin
Height |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
Not
required |
Insubstantial |
Insubstantial |
Insubstantial |
LCA4 |
Cheung
Sha Wan |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
Not
required |
Insubstantial |
Insubstantial |
Insubstantial |
Key: Con =
construction phase
Oper =
Operational phase
Table 9‑8 Summary
of Visual Impact
Id No. |
Key Visual Sensitive Receiver |
Receptor |
Magnitude of Impact |
Impact Significance without Mitigation
Measures |
Recommended Mitigation Measures |
Residual Impact Significance with
Mitigations |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Day 1
Operation |
10 year
after operation |
||||
R1 |
Residents of |
High |
Small to
negligible |
Small to
negligible |
Moderate
adverse |
Slight
adverse |
LMM1-LMM8 |
Moderate
adverse |
Slight
adverse |
Insubstantial |
R2 |
Residents of |
High |
Small to
negligible |
Small to
negligible |
Moderate
adverse |
Slight
adverse |
Moderate
adverse |
Slight
adverse |
Insubstantial |
|
T1 |
Visitors in |
High |
Intermediate |
Small to
negligible |
Moderate
adverse |
Slight
adverse |
Moderate
adverse |
Slight
adverse |
Insubstantial |
|
T2 |
Trail Walkers in |
High |
Intermediate |
Small to
negligible |
Moderate
adverse |
Slight
adverse |
Moderate
adverse |
Slight
adverse |
Insubstantial |
9.11 Environmental Monitoring and Audit Requirement
9.11.1 This section defines the Environmental Monitoring and Audit (EM&A) requirements that have been recommended to ensure that the proposed landscape and visual mitigation measures are effectively implemented. An implementation schedule for Landscape and Visual Mitigation Measure is provided as Table 9-9.
9.11.2 Regarding the necessary felling of trees within the project area, tree felling application will be submitted for approval by the relevant government departments prior to the commencement of works and tree debris to be removed immediately after felling. Compensatory planting is encouraged to be carried out as soon as possible in order to speed up restoration of greening of environment.
9.11.3 Monitoring and audit should be taken place throughout the construction and operation phases of the Project to ensure and the progress of implementing landscape and visual mitigation measures.
9.11.4 A landscape auditor (as a member of ET) shall be employed to review contractor’s submissions and proposals and to monitor and audit the contractor’s landscape works in particular to ensure the existing trees retained on-site are being well preserved, tree transplanting and felling operations are being undertaken in accordance with the requirements. Procedures and specifications as stipulated in the contract and the approvals granted by concerned authorities, and all the newly planted vegetations are being maintained properly during the establishment period.
9.11.5 Please also refer to the EM & A Manual for the details of monitoring and audit.
Table 9‑9 Landscape
and Visual Mitigation Measures Implementation Schedule
Id No. |
Landscape and Visual |
Location |
Funding |
Implementation/ |
Relevant Standard |
Implementation
Stage * |
Timing of |
Objectives of the Recommended |
||
D |
C |
O |
||||||||
LMM1 |
Topsoil, where identified, should be stripped |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To provide a viable growing medium suited to the
existing conditions and reduce the need for the importation of top soil |
LMM2 |
Existing Trees to be retained on site should |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To ensure the success of the |
LMM3 |
Compensatory tree planting should be provided to
compensate for felled trees |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout design and construction phase |
The planting proposal seeks to compensate for the
predicted tree loss resulting form the construction, visually integrate the
proposals within its existing landscape framework and provide an improved
visual amenity |
LMM4 |
Erection of decorative screen hoarding compatible
with surrounding setting |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To integrate the construction site with the
existing environment |
LMM5 |
Locations of the site office, storage or
workshops should be carefully adjusted to areas out of tree protection zones. |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To avoid unnecessary felling of trees |
LMM6 |
Selection of intake and outfall portals to areas
enclosed by existing topography or vegetation |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To preserve the existing topography and as many
as trees as possible |
LMM7 |
Appearance of the water intake and outfall
structures |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To reduce the apparent visual mass of water
intake and outfall structures |
LMM8 |
Reinstatement of disturbed vegetation
at both portal areas |
Site |
WSD |
Contractor |
TM-EIA |
|
|
√ |
After the completion of construction works |
To mitigate disturbance to vegetation arising
from the proposed construction |
* Implementation Stage: D = Design Stage; C = Construction Stage; O =
Operation Stage
9.12.1 This section summaries the landscape and visual impact assessment result for the Project and highlights the potential residual impacts after fully establishment of recommended landscape mitigation measures. Given the utilization of tunnelling method with no provision of vent and access shaft along the inter-reservoirs transfer alignment, the source of impact is limited to the construction of the water intake and outfall portals which is located at the reservoir embankment of Kowloon Byewash Reservoir (Southern Portal) and Lower Shing Mun Reservoir (Northern Portal).
9.12.2 Landscape mitigation measures are recommended and discussed in section 9.9 of this report to alleviate the potential and visual impacts to ensure the implementation of the Project will fit into the existing landscape and visual context. These measures include the selection of portal location which enclosed by existing topography or vegetation to minimize the visual intrusion of engineering structure, maximizing the retention of existing trees in existing location or through transplantation ,as far as technical feasible, through responsive site planning for construction works, site access, offices, material storage, hoarding and temporary work areas, compensation to the loss of existing trees through new woodland planting to enhance the ecological value of the local context and reinstate the disturbed areas to its original as far as possible to maintain existing reservoir side amenity.
No Impact on Planning and Development Control Framework
9.12.3 No part of the proposed water tunnel will be constructed through any of the landscape zonings discussed in section 9.5 regarding to the use of tunnelling method, therefore the Project will fit within the future landscape planning framework as represented by the OZPs and so no amendment to the published land use plans is required.
Landscape Impacts
Preservation of Existing Trees
9.12.4 Majority of trees would be preserved on the sloping areas surrounding the reservoir, only some 19 out of total 262 surveyed trees at southern portal and would be affected by the construction of Southern Portal and 42 out of total 203 surveyed trees at northern portal would required to be felled. These affected trees are majority non-native plantation species composed of medium to small size of DBH. These trees are directly in conflict with the works and not feasible to be transplanted due to their growing condition on steep slope with dense plantation at where difficult for preparation of a viable root ball for transplantation and lowered survival rate after transplanting
9.12.5 The tree loss will be compensated through planting of new woodland trees with a replanting ratio of minimum 1:1 at reinstated areas adjacent to the portal.
Preservation of Landscape Resources
9.12.6 Given the proposed works are limited to the embankment of the reservoirs, adjacent road and sloping area, the predicted impact on landscape resources, including LR1 Mixed Woodland and LR2 Modified Watercourse will receive moderate and slight adverse impact respectively due to the modification of existing artificial topography and loss of existing trees. These impacts will be further mitigated to insubstantial through responsive site planning, restoration of disturbed area and fully establishment of compensatory planting formed part of landscape mitigation measures to ensure no net loss of landscape resources
Maintain Landscape Character
9.12.7 In summary the predicted impact on landscape character areas, limited to LCA1 Kowloon Reservoir Group and LCA2 Lower Shing Mun Reservoir LCAs, will receive moderate adverse impact due to introduction of portal structures in their landscape context, the alternation of existing topography with man-made structure and loss of existing trees, however the magnitude of change to their landscape context is comparative small due to the scale and nature of the Project. Impact on other landscape character areas within the study area including LCA3 Sha Tin Height Urban Fringe and LCA4 Cheung Sha Wan Urban Fringe will be negligible due to no activities are carried out in these areas. Impact on LCAs will be further mitigated to insubstantial through responsive site planning, restoration of disturbed areas, fully establishment of compensatory planting formed part of landscape mitigation measures to successfully integrate the portal structures into existing reservoir setting and countryside landscape character.
Visual Impacts
9.12.8 Given the scale and nature of the Project which do not form a major component in the existing countryside visual context, VSRs, including residents of Lakeview Garden and No. 8 Caldecott Road Government Apartment located in a distance at least 200m away from the portal sites and trail walkers along reservoir side adjacent to the portals, will experience a moderate adverse impact during construction phase and slight adverse impact during operation phase. This different of impact is largely due to the intrusion of permanent portal structures during operation phase leading to a relatively smaller change of visual amenity when compared with the mobility of tunnel boring machine and increase of construction traffic during construction. This visual impact will be further alleviate through responsive alignment and portal locations, site planning and site management, preservation of trees, to slight adverse residual impact during construction. Upon to fully establishment of compensatory planting and restoration of disturbed areas, these portals will appear as an insubstantial component in views looking from the above VSRs and that the Project can be successfully integrated within the existing landscape and visual context.
Conclusion on Significant of Residual Impact
9.12.9 Although the tunnel alignment will have no impact on both landscape and visual context, there is slight adverse residual effect locally to the areas adjacent to the portals, mainly due to tree loss and the appearance of permanent intake and outfall structures upon to the fully establishment of landscape mitigation measures. In accordance with Annex 10, Paragraph 1.1(c) of the EIAO TM, the landscape and visual impacts of the proposed works would be ‘acceptable with mitigation’ that is to say ‘there would be some adverse effects, but these can be eliminated, reduced or offset to a large extent by specific measures’.
10.1.1 The project will consist of the construction of a 2.8 kilometre long tunnel, including intake and outfall structures at the Kowloon Byewash and Lower Shing Mun Reservoirs, respectively. The Cultural Heritage Impact Assessment (CHIA) was conducted within the 300 metres boundary from the proposed works at the outfall / intake works and tunnel alignment.
10.2 Relevant Legislation and Guidelines
10.2.1 Legislation, standards, guidelines and criteria relevant to the consideration of Cultural Heritage Impacts under this study include the following:
· Antiquities and Monuments Ordinance
· Environmental Impact Assessment Ordinance
·
· Technical Memorandum on Environmental Impact Assessment Process.
· Criteria for Cultural Heritage Impact Assessment
· Development Bureau Technical Circular (Works) No. 11/2007
Antiquities and Monuments Ordinance
10.2.2 The Antiquities and Monuments Ordinance (the Ordinance) provides the statutory framework to provide for the preservation of objects of historical, archaeological and palaeontological interest. The Ordinance contains the statutory procedures for the Declaration of Monuments. The proposed monument can be any place, building, site or structure, which is considered to be of public interest by reason of its historical, archaeological or palaeontological significance.
10.2.3 Under Section 6 and subject to sub-section (4) of the Ordinance, the following acts are prohibited in relation to certain monuments, except under permit:
· To excavate, carry on building works, plant or fell trees or deposit earth or refuse on or in a proposed monument or monument;
· To demolish, remove, obstruct, deface or interfere with a proposed monument or monument.
10.2.4
The discovery of an Antiquity, as defined in the
Ordinance must be reported to the Antiquities Authority (the Authority), or a
designated person. The Ordinance also
provides that, the ownership of every relic discovered in
10.2.5 No archaeological excavation may be carried out by any person, other than the Authority and the designated person, without a licence issued by the Authority. A licence will only be issued if the Authority is satisfied that the applicant has sufficient scientific training or experience to enable him to carry out the excavation and search satisfactorily, is able to conduct, or arrange for, a proper scientific study of any antiquities discovered as a result of the excavation and search and has sufficient staff and financial support.
Environmental Impact Assessment Ordinance
10.2.6 The Environmental Impact Assessment Ordinance (EIAO) was implemented on 1 April 1998. Its purpose is to avoid, minimise and control the adverse impact on the environment of designated projects, through the application of the EIA process and the Environmental Permit (EP) system.
10.2.7
Chapter 10 of the HKPSG details the principles of
conservation of natural landscape and habitats, historical buildings and
archaeological sites. It also addresses
the issue of enforcement. The appendices
list the legislation and administrative controls for conservation, other
conservation related measures in
Technical Memorandum on Environmental Impact Assessment Process
10.2.8 The general criteria and guidelines for evaluating and assessing impacts to Cultural Heritage are listed in Annexes 10 and 19 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). The guidelines state that preservation in totality and measures for the integration of sites of cultural heritage into the proposed project will be a beneficial impact. It also states that destruction of a site of cultural heritage must only be undertaken as a last resort.
Guidelines for Cultural Heritage Impact Assessment
10.2.9 This document, as issued by the Antiquities and Monuments Office, outlines the specific technical requirement for conducting terrestrial archaeological and built heritage impact assessments. It includes the parameters and scope for the Baseline Study, specifically desk-based research, field survey and the reporting requirements. As well, the prerequisite conditions for conducting impact assessment and mitigation measures are presented in detail.
Development Bureau Technical Circular (Works) No. 11/2007: Heritage Impact Assessment Mechanism for Capital Works Projects
10.2.10 The circular deals with certain categories of capital works projects and the requirements for conducting HIA if required by the AMO. The paper states that if “Heritage Sites” are located within or in the vicinity of the project boundary, the works agent must submit this information to AMO and the AMO will decide if an HIA should be conducted for the project. The works agent is also responsible for submitting a proposed Study Brief to the AMO on the scope of the HIA.
10.3.1 The preferred alignment and intake/ outfall locations for the project can be seen in Figure 2-5.
Baseline Study
10.4.1 A desk-based study was undertaken to assess the potential for built heritage resources to be present. The following sources were consulted; the AMO published and unpublished papers and studies; publications on relevant historical, anthropological and other cultural studies; unpublished archival, papers, records; collections and libraries of tertiary institutions; historical documents which can be found in Public Records Office, Lands Registry, District Lands Office, Museum of History; cartographic and pictorial documentation.
10.4.2 In addition to the desk-based review, in cases where the sources of information proved to be inadequate or where the project area had not been adequately studied before, field survey was conducted to assemble the necessary data.
Study Area
10.4.3 The general Study Area for the Cultural Heritage Impact Assessment (CHIA) will be 300 metres from the proposed works at the outfall and intake works areas.
Resources to be Covered by the Cultural Heritage Impact Assessment
10.4.4 As stated in the project brief the CHIA will identify all Sites of Cultural Heritage within the project Study Area. A Site of Cultural Heritage is defined as “an Antiquity or Monument, whether being a place, building, site or structure or a relic, as defined in the Antiquities or Monuments Ordinance (Cap. 53) and any place, building, site or structure or a relic identified by the Antiquities and Monuments Office to be of archaeological, historical or palaeontological significance”
10.4.5 The resources shall include, but will not be limited to the following;
· All pre 1950 structures, which include any built feature (apart from graves and historical land use features, which are dealt with separately), such as domestic structures, ancestral halls, temples, shrines, monasteries and nunneries, village gates, wells, schools, historic walls, bridges and stone tablets;
· Any post 1950 structure deemed to possess features containing architectural or cultural merit;
·
All Proposed and
· All pre-war clan graves;
· Cultural landscape features, such as fung shui woods and ponds, historical tracks and pathways, stone walls and terraces, ponds and other agricultural features;
Impact Assessment and Mitigation Recommendations
10.4.6 Prediction and Identification of both direct and indirect impacts that may affect the built heritage resources within the project Area will be undertaken with special attention paid to the built heritage resources identified in the project Study Brief. Preservation in-situ will always be the first priority for sites of Cultural Heritage. If preservation in totality is not possible, mitigation will be proposed to minimise the degree of adverse impact to the greatest possible extent. As well, any disturbance to sites of Cultural Heritage that may cause physical damage should be avoided wherever possible through alteration of design, construction method or protective measures as appropriate.
10.5 Identified Sites of Cultural Heritage within Study Area
The
10.5.1 There are two Graded Historical Structures in the vicinity of the proposed Intake Structure A, these are the Dam itself and also the valve house (both are Grade II). A map showing the locations of the dam and valve house can be found in Figure 10-1 and a description of both structures in the catalogue in Appendix J. The dam was built between 1929 and 1931. The function of the dam was to receive surplus water from Kowloon Reception Reservoir and Kowloon Reservoir (AMO File).
The
10.5.2 The Shing Mun Reservoir Scheme was constructed as part of the Plover Cove Water Scheme. It was designed to act as a transfer and storage reservoir and works were completed in 1965 (AMO File). One Grade I Structure was identified i.e. the Lower Shing Mun Reservoir Dam (on AMO’s list of graded historic buildings it is named as the Shing Mun Reservior (Jubilee) Lower Reservoir Pineapple Pass Dam). A map showing the locations of the structure can be found in Figure 10-2 and a description of the structure in the catalogue in Appendix J.
The Shek Lei Pui Reservoir
10.5.3
The reservoir was one of the early projects for
expanding water supply in the
The
10.5.4
Construction of this reservoir took place between 1902
and 1910 (as part of the Kowloon Waterworks Gravitation Scheme) and it was the
first reservoir in the
10.5.5 There are no other sites of Cultural Heritage in the project Study Area.
Prediction of Impacts
10.6.1 The method of construction for the portals at the intake and outfall structures will be a combination of mechanical, pneumatic or hydraulic splitting or expanding grout techniques. The tunnel excavation will be conducted by tunnel boring machine (or by conventional excavation methods in areas unsuitable for use of the TBM). There will be no blasting involved in the construction phase of the project and as stated in section 2.6.4 the methods to be used will create much lower levels of vibration than D&B. Impacts on historic structures are particularly sensitive to vibration therefore is considered unlikely during the construction phase.
10.6.2 The identified Sites of Cultural Heritage within the project Study Area are all parts of functioning dams and are not sensitive to changes in the surrounding environment. The project will include a Landscape and Visual Impact Assessment to ensure that the proposed works do not adversely impact on the environmental setting of the area and no additional visual impact assessment will be required from a cultural heritage standpoint.
Evaluation of Impacts
10.6.3 The following table will present the impacts associated with the construction phase of the project. No impacts have been identified during the constructional and operational phase of the project. The assessment presented in this section is based upon the works areas as currently designed. If any additional or alternate works areas are proposed in future, supplemental assessment will be undertaken.
Table 10‑1 Anticipated Impacts associated with Construction of the Project
Resource |
Minimum Distance from Works Area |
Impact Assessment |
Dam (Grade
II) IRTS-01 |
30 m |
The Dam is located
in close proximity to the proposed works at Intake A, but no blasting is
proposed for the proposed construction works. No adverse impacts are
expected. |
|
45 m |
The Valve House is
located in close proximity to the proposed works at Intake A, but no blasting
is proposed for the proposed construction works. No adverse impacts are
expected. |
(Shing Mun
Reservoir (Jubilee) |
200 m |
All of the
identified structures are located at a sufficient distance from the proposed
works area at Outfall D and no adverse impacts are expected. |
Shek Lei Pui
Northeast Dam (Grade II) IRTS-04 |
69 m |
No blasting is
proposed for the proposed construction works. No adverse impacts are
expected. |
Shek Lei Pui
Northeast Dam Valve House (Grade II) IRTS-05 |
78 m |
No blasting is
proposed for the proposed construction works. No adverse impacts are
expected. |
Shek Lei Pui
Southwest Dam (Grade II) IRTS-06 |
159 m |
No blasting is
proposed for the proposed construction works. No adverse impacts are
expected. |
Kowloon Reservoir Dam (Grade I) IRTS-07 |
257 m |
All of the
identified structures are located at a sufficient distance from the proposed
works area along the alignment and no adverse impacts are expected. |
Note: * The dam is referred to as Lower Shing Mun Reservoir Dam within WSD while it is named as Shing Mun Reservoir (Jubilee) Lower
Reservoir Pineapple Pass Dam on AMO’s list of graded historic buildings
10.7 Mitigation Recommendations
10.7.1 The following table presents the required mitigation for the identified sites of Cultural Heritage for which adverse impacts have been identified.
Table 10‑2 Mitigation Recommendations for Sites of Cultural Heritage adversely impacted by the proposed construction works at Intake A
Resource |
Map Reference |
Mitigation Recommendation |
(Grade II) IRTS-01 |
Although no adverse impacts are
expected, conducting a condition survey prior to the construction phase of
the project as a precautionary mitigation measure is recommended. The survey shall check the state of
the dam / valve house and provide the most up-to-date information of the
condition of these structures; and advise any other additional protective
measures are required during the construction period. The report should be
submitted to AMO for review prior to the construction phase. |
|
IRTS-02 |
||
(Shing Mun
Reservoir (Jubilee) (Grade I) I RTS-03 |
No mitigation will be required for
the identified structures. |
|
Shek Lei Pui Northeast Dam (Grade II) IRTS-04 |
Although no adverse impacts are
expected, conducting a condition survey prior to the construction phase of
the project as a precautionary mitigation measure is recommended. The survey shall check the state of
the dam and provide the most up-to-date information of the condition of the
structure; and advise any other additional protective measures are required
during the construction period. The report should be submitted to AMO for review
prior to the construction phase. |
|
Shek Lei Pui
Northeast Dam Valve House (Grade II) IRTS-05 |
Although no adverse impacts are
expected, conducting a condition survey prior to the construction phase of the
project as a precautionary mitigation measure is recommended. The survey shall check the state of
the valve house and provide the most up-to-date information of the condition
of the structure; and advise any other additional protective measures are required
during the construction period. The report should be submitted to AMO for
review prior to the construction phase. |
|
Shek Lei Pui
Southwest Dam (Grade II) IRTS-06 |
Although no adverse impacts are expected,
conducting a condition survey prior to the construction phase of the project
as a precautionary mitigation measure is recommended. The survey shall check the state of
the dam and provide the most up-to-date information of the condition of the
structure; and advise any other additional protective measures are required
during the construction period. The report should be submitted to AMO for
review prior to the construction phase. |
|
Kowloon Reservoir Dam (Grade I) IRTS-07 |
No mitigation will be required for
the identified structures. |
Note: * The dam is referred to as Lower Shing Mun Reservoir Dam within WSD while it is named as Shing Mun Reservoir (Jubilee) Lower
Reservoir Pineapple Pass Dam on AMO’s list of graded historic buildings
Requirements of the Condition Survey
10.7.2 The condition survey must be carried out by an approved qualified building surveyor who is a member of the Hong Kong Institution of Surveyors in the Building Surveying division or equivalent and an approved qualified engineer who is a member of the Hong Kong Institution of Engineers in the Civil or Structural Division or equivalent. The condition survey should also make reference (if appropriate) to the Practice Notes No. 289 issued by the Buildings Department of the Hong Kong SAR Government.
10.7.3 The condition survey report must be submitted to the Engineer and the Antiquities and Monuments Office (AMO) for review before the commencement of works and must contain the following:
· An appraisal of the state of the existing historic building and structures including location and condition of all signs of defect (including suitably referenced and catalogued photographs);
· An appraisal of their various types of construction, including foundations;
· Recommendations of monitoring measures to be taken and locations of proposed monitoring points (if required);
· Recommendations for reading frequency of the monitoring equipment (if required); and
· Recommendations of the necessity to conduct a separate assessment report.
10.7.4 A separate assessment report may be produced based on findings of this condition survey report to recommend the following:
· Setting of a safe limit for vibration levels for each historic structure (if required)
· The likely effect that the contractors method of working would have on the existing historic buildings and structures (including the structural stability of the structure);
· Recommendations of any other protective measures to be taken during the construction and/ or operational phases (if required).
10.7.5 If required, monitoring measures and protective measures must be implemented by the contractor and can include, but are not limited to; fixing approved tell tales and tilting markers to monitoring points to the structures and buildings and monitoring them on the schedule recommended in the condition survey report. It should be noted that that for the installation of monitoring measures disturbances to identified historic items should be kept to an absolute minimum and that after removal of such measures, the affected area should be restored to match the original condition. The results of the monitoring must be submitted to the engineer (in an agreed format) within two days of each monitoring undertaken. If the monitoring measurements exceed the safe limits for any of the monitored structures, the Contractor shall take immediate corrective action as necessary, to bring vibration levels within compliance. The monitoring results should be submitted to AMO only if there is significant effect on the historic items.
10.8.1 The Cultural Heritage Impact Assessment for the project has identified that there are sensitive historical structures in the vicinity of the proposed works and that mitigation in the form of vibration monitoring may be required during the construction period. Although no adverse impacts on the historical structures are anticipated, conducting a condition survey prior to the construction phase as a precautionary mitigation measure is recommended and the survey report shall be submitted to AMO for review prior to the commencement of the construction phase.
AMO Files
AM94-0568 Shek Lei Pui Reservoir Northeast Dam (01)
AM94-0568 Shek Lei Pui Reservoir Southwest
Dam (02)
AM94-0568 Shek Lei Pui Reservoir Northeast Dam Valve House (03)
AM94-0572(03)
Shing Mun (Jubilee)
AM94-0567
AM94-0570
(01)
AM94-0570
(02)
Water
Supplies Department 1996 “
11.1.1 The implementation schedules for the recommended mitigation measures for each environmental aspect covered in this EIA are given in the following tables.
Table 11‑1 Air Quality Impact – Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended
Environmental Protection Measures/ Mitigation Measures |
Objectives of
the recommended measures & main concerns to address |
Who to implement
the measures? |
Location /
Timing of implementation of Measures |
What
requirements or standards for the measures to achieve? |
Construction Phase |
||||||
S.3.5.9 |
S.3.2.2 |
All the dust control
measures as recommended in the Air Pollution Control (Construction Dust)
Regulation, where applicable, should be implemented. Typical dust control
measures include: |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
At all construction areas
of the site during the entire construction period |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
The works area for site
clearance shall be sprayed with water before, during and after the operation
so as to maintain the entire surface wet |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
Restricting heights from which materials are to be
dropped, as far as practicable to minimise the fugitive dust arising from
unloading/ loading |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
Immediately before leaving a construction site, all
vehicles shall be washed to remove any dusty materials from the bodies and
wheels. However, all spraying of
materials and surfaces should avoid excessive water usage |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
Where a vehicle leaving a construction site is carrying
a load of dusty materials, the load shall be covered entirely by clean
impervious sheeting to ensure that the dusty materials will not leak from the
vehicle |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
Erection of hoarding of not less than 2.4 m high from
ground level along the site boundary, where appropriate |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
Any stockpile of dusty materials shall be covered
entirely by impervious sheeting; and/or placed in an area sheltered on the
top and 4 sides |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
S.3.5.9 |
S.3.2.2 |
§
All dusty materials shall be sprayed with water
immediately prior to any loading, unloading or transfer operation so as to
maintain the dusty materials wet |
Air Quality (fugitive
dust) Control during Construction Phase |
Contractors |
Ditto |
EIAO -TM, Air Pollution
Control (Construction Dust) Regulation |
Operational Phase |
||||||
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 11‑2 Noise Impact – Implementation Schedule
of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Environmental Protection Measures/
Mitigation Measures |
Objectives of the recommended measures & main
concerns to address |
Who to implement the measures? |
Location / Timing of implementation of Measures |
What requirements or standards for the measures
to achieve? |
Construction Phase |
||||||
S.4.8.2 |
S.4.8.1 |
§
The Contractor shall adopt
the Code of Practice on Good Management Practice to Prevent Violation of the
Noise Control Ordinance (Chapter 400) (for Construction Industry) published
by EPD |
Noise control during
construction |
Contractors |
At all construction areas
of the site during the entire construction period |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
The Contractor shall observe and comply with the
statutory and non-statutory requirements and guidelines |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
Before commencing any work, the Contractor shall
submit to the Engineer Representative for approval the method of working,
equipment and noise mitigation measures intended to be used at the site |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
The Contractor shall devise and execute working
methods to minimise the noise impact on the surrounding sensitive uses, and
provide experienced personnel with suitable training to ensure that those
methods are implemented |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
Noisy equipment and noisy activities should be
located as far away from the NSRs as is practical |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
Unused equipment should be turned off. PME should be
kept to a minimum and the parallel use of noisy equipment / machinery should
be avoided |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
Regular maintenance of all plant and equipment |
Noise control during
construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
S.4.8.2 |
S.4.8.1 |
§
Material stockpiles and other structures should be
effectively utilised as noise barriers, where practicable |
Noise control during construction |
Contractors |
Ditto |
Annex 5 of EIAO-TM |
Operational Phase |
||||||
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 11‑3 Water Quality Impact – Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Environmental Protection Measures/
Mitigation Measures |
Objectives of the recommended measures & main
concerns to address |
Who to implement the measures? |
Location / Timing of implementation of Measures |
What requirements or standards for the measures
to achieve? |
Construction Phase |
||||||
S.5.10.1 -5.10.2 |
S.5.8.2 -5.8.3 |
Construction for the
desilting facilities at intake and outfall
portals should be carried out behind a temporary cofferdam which is
watertight enclosure built in the reservoirs and pumped dry to expose the
bottom. |
Point Pollution Control |
Contractors |
Before construction of intake
and outfall portals and remain on site until completion of intake
and outfall portals and tunnel construction |
Water Pollution Control
Ordinance |
S.5.10.3 |
S.5.8.4 |
The cofferdams should be
regularly inspected and maintained to ensure no spillage of waste or
wastewater into the reservoirs. |
Point Pollution Control |
Contractors |
Before construction of intake
and outfall portals and remain on site until completion of intake
and outfall portals and tunnel construction |
Water Pollution Control
Ordinance |
S. 5.10.4 |
S. 5.8.5 |
Construction of desilting
facilities within works areas capable of controlling discharge of SS to
comply with WPCO/TM-DSS |
Point and |
Contractors |
At all construction areas
of the site during the entire construction period |
Water Pollution Control
Ordinance |
S.5.10.5 |
S.5.8.6 |
Construction runoff will
be managed as per the Practice Note for Professional Persons ProPECC PN1/94 -
Construction Site Drainage and the conditions of working within Water
Gathering Grounds stipulated by WSD |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance Water Gathering Ground control
by WSD |
S.5.10.6 |
S. 5.8.7 |
A Drainage Management Plan
should be prepared by the Contractor for approval by the Engineer for each of
the works areas, detailing the facilities and measures to manage pollution
arising from surface runoff from those works areas |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance Water Gathering Ground control by WSD |
S. 5.10.7 |
S. 5.8.8 |
An Emergency Contingency
Plan should also be prepared by the Contractor, detailing the response and
procedures to contain and remove any accidental spillage along the temporary
and permanent roads and at the site at short notice to prevent or minimize
the quantities of contaminants from reaching the reservoirs and local streams
leading to the reservoirs. The Emergency Contingency Plan should be submitted
to the Engineer for approval |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance Water Gathering Ground control by WSD |
S. 5.10.8 |
S. 5.8.9 |
§
Surface run-off and
effluent from the construction sites at the intake at Kowloon Byewash
Reservoir and outfall at the Lower Shing Mun Reservoir will be directed
towards adequately designed sand/silt removal facilities such as sand/silt
traps and sediment basins to remove sand/silt particles from runoff to meet
the requirements of the TM standards under the WPCO before discharging to
discharge points downstream of the Kowloon Byewash Reservoir Dam and Lower
Shing Mun Reservoir Dam respectively. The design of efficient silt removal
facilities should be based on the guidelines in Appendix A1 of ProPECC PN
1/94, which states that the retention time for silt/sand traps should be 5
minutes under maximum flow conditions. Sizes may vary depending upon the flow
rate, but for a flow rate of 0.1m3/s a sedimentation basin of 30m3
would be required and for a flow rate of 0.5m3/s the basin would
be 150m3. The detailed design of the sand/silt traps should be
undertaken by the contractor prior to the commencement of construction |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Channels,
earth bunds or sand bag barriers will be provided on-site to properly direct
stormwater to the above-mentioned facilities |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Existing on-site silt
removal facilities, channels and manholes, if any, will be maintained and the
deposited silt and grit will be removed regularly, at the onset of and after
each rainstorm to ensure that these facilities are functioning properly at
all times |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Other
manholes, if any, including any newly constructed ones will be adequately
covered and temporarily sealed so as to prevent silt, construction materials
or debris from getting into the drainage system |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Open
stockpiles of materials on site will be avoided within water gathering
grounds as far as practicable. All surplus spoil will be removed from water
gathering grounds as soon as possible
Measures will be taken to prevent the washing away of construction
materials, soil, silt or debris |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Where
possible, works entailing soil excavation will be minimized during the rainy
season (i.e. April to September). If excavation in soil could not be avoided
in these months or at any time of year when rainstorms are likely, for the
purpose of preventing soil erosion, temporary exposed slope surfaces should
be covered e.g. by tarpaulin, and temporary access roads should be protected
by crushed stone or gravel, as excavation proceeds. Intercepting channels
should be provided (e.g. along the crest/edge of excavation) to prevent storm
runoff from washing across exposed soil surfaces. Arrangements should always
be in place to ensure that adequate surface protection measures can be safely
carried out well before the arrival of a rainstorm |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Where
applicable, final earthworks surfaces/ slopes will be well compacted and
hydro-seeded following completion to prevent erosion |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Where surface runoff or
construction effluent is likely to be contaminated with oil, properly
designed and maintained petrol interceptor will be provided to meet the
WPCO/TM-DSS requirements. Oil leakage or spillage shall be contained and
cleaned up immediately. Detailed design of the petrol interceptor shall be
provided by the Contractor before commencement of construction |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Sewage
arising from the construction workers on site should be collected by
temporary sanitary facilities e.g. portable chemical toilets. Portable
toilets should be used coupled with tankering away services provided by a
licensed collector |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
All
site discharges within Inland Waters Group A must comply with the terms and
conditions of a valid discharge licence issued by EPD |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Vehicle
wheel washing facilities should be provided, where applicable, at the site
exit such that mud, debris, etc. deposited onto the vehicle wheels or body
can be washed off before the vehicles are leaving the site area |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Section
of the road between the wheel washing bay and the public road should be paved
with backfill to reduce vehicle tracking of soil and to prevent site run-off
from entering public road drains |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Vehicle
washing facilities should be drained into desilting facilities before
discharge. The water should be recycled on site wherever possible. It is
suggested that the wash water from the wheel wash basin is either reused for
site watering or pumped to the on-site desilting facilities for treatment |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
․
Desilting
facilities should be checked and the deposited silt and grit should be
removed regularly to ensure they are working properly at all times |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
․
To
minimize water quality impact, recycled water should be used at the cutter
face for cooling purposes. Used water should be collected and discharged to
settling tank for settlement |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
․
Excess
water from the settling tank would be transferred to the desilting facilities
for treatment before discharge. The Contractor should ensure that the
discharge water from the desilting facilities and treated spent effluent arising
from tunnel boring from the desilting facilities comply with the WPCO/TM-DSS
requirements before discharge |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Existing on-site silt
removal facilities, channels and manholes, if any, would be maintained such
that the deposited silt and grit will be removed regularly, at the onset of
and after each rainstorm to ensure that these facilities are functioning
properly at all times; |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
Desilting facilities
should be checked and the deposited silt and grit should be removed regularly
to ensure they are working properly at all times; |
Stormwater and |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
The
project may occasionally involve the handling of fuel and generates chemical
wastes. It must be ensured that all
fuel tanks and chemical storage are sited on sealed and bunded areas,
provided with locks and located outside water gathering grounds as far as
practicable |
Protection Against Accidental Spillage |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
§
The
storage areas will be surrounded by bunds with a capacity equal to 110% of
the storage capacity of the largest tank to prevent accidentally spilled oil,
fuel or chemicals from reaching the receiving waters |
Protection Against
Accidental Spillage |
Contractors |
Ditto |
Water Pollution Control
Ordinance |
S. 5.10.8 |
S. 5.8.9 |
․
Oil
and grease removal facilities will be provided where appropriate, for
example, in area near plant workshop/ maintenance areas, if any |
Protection Against Accidental Spillage |
Contractors |
Ditto |
Water Pollution Control Ordinance |
S. 5.10.8 |
S. 5.8.9 |
․
Chemical
waste arising from the site should be properly stored, handled, treated and
disposed of in compliance with the requirements stipulated under the Waste
Disposal (Chemical Waste) (General) Regulation |
Protection Against Accidental Spillage |
Contractors |
Ditto |
Waste Disposal (Chemical Waste) (General) Regulation |
Operational Phase |
||||||
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 11‑4 Waste Management Implication –
Implementation Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Environmental Protection Measures/
Mitigation Measures |
Objectives of the recommended measures & main
concerns to address |
Who to implement the measures? |
Location/ Timing of implementation of Measures |
What requirements or standards for the measures
to achieve? |
Construction Phase |
||||||
S.6.7.1 |
S. 6.2.2 |
Given the potential for
secondary environmental impacts (dust, noise, water quality and visual
impacts), mitigation measures are required to ensure proper handling,
storage, transportation and disposal of materials at the outset and
throughout the construction phase of the project: |
Waste management during construction |
Contractors |
At all construction areas
of the site during the entire construction period |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
An on-site environmental
co-ordinator employed by the Contractor should be identified at the outset of
the works. The co-ordinator shall
prepare a Waste Management Plan (“WMP”) in accordance with the requirements
set out in the ETWB TCW No. 19/2005, Waste Management on Construction
Sites. The WMP shall include monthly
and yearly Waste Flow Tables (“WFT”) that indicate the amounts of waste
generated, recycled and disposed of (including final disposal site), and
which should be regularly updated |
Waste management during construction |
Contractors |
Ditto |
ETWB TCW No. 19/2005, Waste Management on Construction Sites |
S.6.7.2 |
S. 6.2.5 |
§
The reuse/ recycling of
all materials on site shall be investigated and exhausted prior to treatment/
disposal off-site |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
Good site practices shall
be adopted from the commencement of works to avoid the generation of waste,
reduce cross contamination of waste and to promote waste minimisation |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
All waste materials shall
be sorted on-site into inert and non-inert C&D materials, and where the
materials can be recycled or reused, they shall be further segregated. Inert material, or public fill will comprise
stone, rock, concrete and soil which is suitable for land reclamation and
site formation whilst non-inert materials include all other wastes generated
from the construction process such as plastic packaging and vegetation (from
site clearance) |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
The Contractor shall be responsible for identifying
what materials can be recycled/ reused, whether on-site or off-site. In the event of the latter, the Contractor
shall make arrangements for the collection of the recyclable materials. Any remaining non-inert waste shall be
collected and disposed of to the public fill reception facilities whilst any
inert C&D materials shall be re-used on site as far as possible. Alternatively, if no use of the inert
material can be found on-site, the materials can be delivered to public fill
reception facilities after obtaining the appropriate licence |
Waste management during
construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
In order to monitor the
disposal of C&D material and solid wastes at public fill reception
facilities and landfills, and control fly-tipping, a trip-ticket system shall
be implemented by the Contractor, in accordance with the contract and the
requirements of WBTC 31/2004 “Trip Ticket System for Disposal of Construction
and Demolition Material” |
Waste management during construction |
Contractors |
Ditto |
WBTC 31/2004 “Trip Ticket System for Disposal of Construction and
Demolition Material” |
S.6.7.2 |
S. 6.2.5 |
§
Under the Waste Disposal
(Chemical Waste) (General) Regulation, the Contractor shall register as a
Chemical Waste Producer if chemical wastes such as spent lubricants and
paints are generated on site. Only
licensed chemical waste collectors shall be employed to collect any chemical
waste generated at site. The handling,
storage, transportation and disposal of chemical wastes shall be conducted in
accordance with the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes and A Guide to the Chemical Waste Control Scheme both
published by EPD |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal (Chemical Waste) (General) Regulation |
S.6.7.2 |
S. 6.2.5 |
§
A sufficient number of
covered bins shall be provided on site for the containment of general refuse
to prevent visual impacts and nuisance to the sensitive surroundings. These bins shall be cleared daily and the
collected waste disposed of to the refuse transfer station. Further to the issue of ETWB TCW No.
6/2002A, Enhanced Specification for Site Cleanliness and Tidiness, the
Contractor is required to maintain a clean and hygienic site throughout the
project works |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
All chemical toilets, if
any, shall be regularly cleaned and the night-soil collected and transported
by a licensed contractor to a Government Sewage Treatment Works facility for
disposal |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
Toolbox talks should be
provided to workers about the concepts of site cleanliness and appropriate
waste management procedures, including waste reduction, reuse and recycling |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
S.6.7.2 |
S. 6.2.5 |
§
The Contractor shall
comply with all relevant statutory requirements and guidelines and their
updated versions that may be issued during the course of project construction |
Waste management during construction |
Contractors |
Ditto |
Waste Disposal Ordinance |
Operational Phase |
||||||
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Table 11‑5 Ecological Impact – Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Environmental Protection Measures/
Mitigation Measures |
Objectives of the recommended measures & main
concerns to address |
Who to implement the measures? |
Location/ Timing of implementation of Measures |
What requirements or standards for the measures
to achieve? |
Construction Phase |
||||||
S 8.8 |
N/A |
Minimise the habitat loss
of secondary woodland / plantation and grassland as far as possible. |
Reduce habitat and
vegetation loss |
Contractors |
At all construction areas
of the site during the entire construction period |
Annex 16 of EIAO-TM |
S 8.8 |
N/A |
Disturbed secondary woodland / plantation and grassland should be
reinstated after the completion of works |
Reinstate disturbed habitats |
Contractors |
Worksite areas at the two portals / after completion of construction
works |
Annex 16 of EIAO-TM |
S 8.8 |
N/A |
Provide clear definition of site boundary |
Prevent impact on offsite
habitats |
Contractors |
At all construction areas
of the site during the entire construction period |
Annex 16 of EIAO-TM |
S 8.8 |
N/A |
Protect the protected plant Pavetta
hongkongensis on its existing location; Transplant the Pavetta
hongkongensis to other suitable location if onsite protection is not
feasible. |
Preserve the protected
plant species |
Contractors |
On the vegetated slope
along the existing vehicle access at worksite area at Lower Shing Mun
Reservoir / Construction period |
Annex 16 of EIAO-TM |
S 8.8 |
N/A |
Carry out compensatory planting if the individual of Artocarpus hypargyreus cannot be
retained onsite |
Mitigate the tree removal |
Contractors |
worksite area at Kwoloon
Byewash Reservoir / Construction Period |
ETWB TCW No. 3/2006 |
S 8.8 |
N/A |
Workers should avoid eating and leave food in works area and avoid
feeding the wildlife; Fishes observed remaining at the proposed works area during the
draining down process should be translocated to the portion of the reservoir
outside the cofferdam. |
Avoidance of injury to
wildlife |
Contractors |
At all construction areas
of the site during the entire construction period |
Annex 16 of EIAO-TM |
S 8.8 |
N/A |
Implement standard good site practices for dust suppression |
Avoid dust deposition on
vegetation |
Contractors |
At all construction areas
of the site during the entire construction period |
EIAO -TM, Air Pollution Control (Construction Dust) Regulation |
S 8.8 |
N/A |
Implement standard good site practices for water quality control |
Avoid site runoff to
nearby habitats |
Contractors |
At all construction areas
of the site during the entire construction period |
Water Pollution Control Ordinance |
S 8.8 |
N/A |
Workers shall not disturb
birds and other wildlife; Litter shall not be burned
on-site but shall be removed off-site; Machinery not in use
should be switched off to minimize the noise nuisance; No fishing is allowed in
the reservoir without permission. |
Avoid disturbance to wildlife |
Contractors |
At all construction areas of the site during the entire construction
period |
Annex 16 of EIAO-TM |
Operational Phase |
||||||
S 8.8 |
N/A |
Compensate the habitat loss (grassland and
woodland) by restoration of same type of habitats to be lost. The
compensatory ratio should not be less than 1:1 in terms of area. |
Mitigate the temporary
habitat loss |
Contractors |
|
Annex 16 of EIAO-TM |
Table 11‑6 Landscape & Visual Impact –
Implementation Schedule of Recommended Mitigation Measures
Id No. |
Landscape and Visual |
Location |
Funding |
Implementation/ |
Relevant Standard |
Implementation
Stage* |
Timing of |
Objectives of the Recommended |
||
D |
C |
O |
||||||||
LMM1 |
Topsoil, where identified, should be stripped |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To provide a viable growing medium suited to the
existing conditions and reduce the need for the importation of top soil |
LMM2 |
Existing Trees to be retained on site should |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To ensure the success of the |
LMM3 |
Compensatory tree planting should be provided to
compensate for felled trees |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout design and construction phase |
The planting proposal seeks to compensate for the
predicted tree loss resulting form the construction, visually integrate the
proposals within its existing landscape framework and provide an improved
visual amenity |
LMM4 |
Erection of decorative screen hoarding compatible
with surrounding setting |
Site |
WSD |
Contractor |
TM-EIA |
|
√ |
|
Throughout construction phase |
To integrate the construction site with the
existing environment |
LMM5 |
Locations of the site office, storage or
workshops should be carefully adjusted to areas out of tree protection zones. |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To avoid unnecessary felling of trees |
LMM6 |
Selection of intake and outfall portals to areas
enclosed by existing topography or vegetation |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To preserve the existing topography and as many
as trees as possible |
LMM7 |
Appearance of the water intake and outfall
structures |
Site |
WSD |
Contractor |
TM-EIA |
√ |
|
|
Throughout design phase |
To reduce the apparent visual mass of water
intake and outfall structures |
LMM8 |
Reinstatement of disturbed vegetation at both
portal areas |
Site |
WSD |
Contractor |
TM-EIA |
|
|
√ |
After the completion of construction works |
To mitigate disturbance to vegetation arising
from the proposed construction |
Table 11‑7 Cultural Heritage – Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Environmental Protection Measures/
Mitigation Measures |
Objectives of the recommended measures & main
concerns to address |
Who to implement the measures? |
Location/ Timing of implementation of Measures |
What requirements or standards for the measures
to achieve? |
Construction Phase |
||||||
S 10.7 |
S8.1.2 |
Condition Survey for the
identified historic items and monitoring of vibration levels if required. |
Prevention of structural
damage to the identified historic items |
Contractors |
Condition survey to be
undertaken prior to the construction phase and vibration monitoring to be
undertaken during the construction phase if required. |
None |
Operational Phase |
||||||
N/A |
N/A |
None |
None |
None |
None |
None |
12.1.1 This project, which the EIA concerns, is about the construction and operation of an Inter-Reservoirs Transfer Scheme (“IRTS”) – Water Tunnel between Kowloon Byewash Reservoir and Lower Shing Mun Reservoir. The Project falls within the Kam Shan Country Parks is therefore a designated project under Item Q.1 of Part I, Schedule 2 of the EIA Ordinance.
12.1.2 An application for an EIA study brief under section 5(1) of the EIAO was submitted by the Water Supplies Department on 29 September 2006 with a Project Profile.
12.1.3 An EIA Study Brief was issued by EPD to the project proponent – Water Supplies Department for the carrying out of the EIA.
12.1.4 In fact, the alignment adopted for the IRTS differs from the original one outlined in the project profile due to various design constraints, benefits and environmental considerations.
12.1.5 The environmental implications of this Project have been addressed and presented in the foregoing sections and summarised in the sections below.
12.2.1 A review of the site environs and the construction of the Project have suggested that the main sources of air pollution during the construction phase will mainly be fugitive dust emissions which are expected to be controllable.
12.2.2 Through proper implementation of dust control measures as required under the Air Pollution Control (Construction Dust) Regulation, construction dust can be controlled at source to acceptable levels and hence no unacceptable impacts are anticipated.
12.2.3 During the operational phase, the project itself is not a source of air pollution.
12.2.4 As the project does not require large-scale site formation or other major activities that could generate significant amount of fugitive dust, no specific construction dust monitoring is considered necessary, though on-site environmental audit is recommended to ensure proper implementation of dust control measures during the construction phase.
12.3 Construction Noise Impact
12.3.1 The construction noise impact assessment has been based on a best estimate of the construction sequence and machines inventory. TBM is expected to operate 24 hours a day to maximise the resources and to complete the works under a tight schedule, while other construction activities at both portals will cease during the restricted hours unless the contractor can obtain a construction noise permit (“CNP”) from the Authority to extent the works into the restricted hours.
12.3.2 The potential noise impact that could arise from daytime construction activities of the Project has been evaluated. The assessment results show no exceedances of construction noise criteria at both the intake and outfall end were predicted in the unmitigated scenario. Hence, no residual noise impact has been predicted.
12.3.3 Potential ground-borne noise impacts during the construction phase have also been assessed. Results indicated that the noise levels predicted can satisfactorily meet the derived noise criteria for the daytime and nighttime period. No mitigation measures are considered necessary.
12.3.4 The Contractor shall, from time to time, be aware of the noise impacts on the surrounding NSRs through adequate noise monitoring during the works so that adjustments could be made to control the construction noise levels. These requirements should be triggered by an Event and Action Plan as part of the EM&A which should be incorporated into the works contract in order to make it enforceable.
12.3.5 As part of the EM&A, baseline monitoring is necessary given an existing tranquil environment in the vicinity of the work site and the local noise sensitive uses on either ends of the IRTS and the envisaged 24-hour tunnelling works.
12.3.6 Impact monitoring will be carried out at monitoring stations defined in the EM&A Manual at a weekly basis to cover working session including the following: -
a) 1 no. of Leq (30 min) noise measurements between 0700-1900 hours on any normal weekdays
b) 3 nos. of consecutive Leq (5 min) noise measurements between 0700-1900 hours on general holidays or Sundays (if work is undertaken)
c) 3 nos. of consecutive Leq (5 min) noise measurements between 1900-2300 hours (if evening activities are undertaken)
d) 3 nos. of consecutive Leq (5 min) noise measurements between 2300-0700 hours next day (if there are nighttime activities).
12.4.1 This Project involves the construction of a water tunnel linking both the Kowloon Byewash and Lower Shing Mun Reservoirs. Although the tunnel will be entirely underground, the portals and construction sites on either side will fall within the water gathering grounds of both reservoirs, which are water sensitive receivers. Water quality impact will be a key concern during the construction phase.
12.4.2 Surface run-off and effluent from the construction sites will be directed towards adequately designed sand/silt removal facilities such as sand/silt traps and sediment basins to remove sand/silt particles from runoff to meet the requirements of the TM standards under the WPCO before discharging.
12.4.3 It is envisaged that the best practicable pollution control measures recommended for the construction phases should be effective to control the potential water quality impacts resulting from stormwater runoff into receiving waters, usually water sensitive receivers.
12.4.4 With the implementation of the recommended mitigation measures and management practices, it is anticipated that the impacts upon the WSRs during the construction phase of the Project would be temporary and minimal. An EM&A programme in respect of water quality issues during the construction phase of the Project would be carried out to monitor compliance with acceptable levels of water quality indicators and to ensure the proposed mitigation measures are effective and implemented.
12.5.1 The potential impacts of wastes arising from the construction and operational phases of the project have been assessed. The construction activities associated with the proposed works will generate a variety of wastes including vegetation from site clearance, excavated materials, and construction wastes, chemical and municipal wastes.
12.5.2 The largest amount of waste expected would be inert C&D materials, which will be generated by tunnelling works during Month 12-17 for around 6 months. The total inert C&D materials expected for the entire project are about 43,800 m3 and that due to tunnelling is estimated as 37,000 m3. 43,650 m3 of the total inert C&D materials will be disposed of at the nearest public fill reception facilities.
12.5.3 In view of the Government policy towards promotion recycling and due to the clear environmental benefits this will provide, recycling and waste reduction by site staff/ contractors (construction phase) should be encouraged whenever it is possible.
12.5.4 While an estimate has been made on the likely volumes and types of waste to be generated from the construction of the project, the Contractor should regularly update and submit the monthly Waste Flow Table (“WFT”) which would provide a more accurate estimate on volumes of waste generation on-site. This WFT shall form part of the Waste Management Plan (“WMP”) to be submitted as part of the EM&A requirements and in accordance with ETWB Technical Circular (Works) No. 19/2005, Waste Management on Construction Sites.
12.5.5 Provided that the waste management practices outlined are put in place, potential impacts on the environment associated with waste generated during the construction phases of the Project should be well under controlled.
12.6.1 The Project work site will potentially be affected by two major sources of hazards, viz.: -
· Possible use of explosives for tunnelling works
· Transport, storage and use of chlorine for disinfection of water at the Shek Lei Pui Water Treatment Works (“SLPWTW”) – a PHI defined by the CCPHI
12.6.2 As outlined in Section 2.6.3, the use of explosives has been ruled out due to proximity of the tunnelling works to the Lower Shing Mun Reservoir dam.
12.6.3 Due to construction requirements, the Shek Lei Pui WTW will be temporarily taken out of service as the construction of the intake portal and TBM retrieving would require the water at the Kowloon Reception Reservoir and the Kowloon Byewash Reservoir to be temporarily drawn down.
12.6.4 Suspension of water treatment at the SLPWTW will be accompanied by relocation of all chlorine drums and hence remove hazard due to transport, storage and use of chlorine at SLPWTW.
12.6.5 Because of the above, no hazard to life assessment is considered necessary as the two hazard sources will be removed.
12.7.1 An Ecological Impact Assessment (EcoIA) has been conducted for the proposed IRTS Water Tunnel between Kowloon Byewash Reservoir and Lower Shing Mun Reservoir. Ecological surveys were carried out in September 2007 to February 2008 which covered both wet and dry seasons.
12.7.2 Six types of habitats were identified within the study area, including reservoir, secondary woodland / plantation, grassland, stream, drainage channel and developed area / bare ground. The habitats inside the boundaries of the proposed worksite areas were not of high ecological value.
12.7.3
The dominant faunal species recorded in
12.7.4 As whole water tunnel will be constructed underground, the scale of surface construction works is limited in nature. The ecological impact with the implementation of recommended mitigation measures should be within acceptable level.
12.8 Landscape and Visual Impact
Landscape Impact
12.8.1 The landscape impacts on the landscape resources and landscape character areas of LR1 Mixed Woodland, LR2 Modified Water Course, LCA1 Kowloon Reservoir Group and LCA2 Lower Shing Mun Reservoir are predicted to be moderate to slight adverse due to modification of existing artificial topography and loss of existing trees. The incorporation of landscape mitigation measures through responsive site planning, retention of vegetations by compensatory planting of trees and planting of shrubs would lessen the landscape impacts to acceptable level.
12.8.2 Since there will be no construction activity outside the works area, the landscape impacts on the landscape resources and landscape character areas of LR3 Developed Area, LCA3 Sha Tin Height Urban Fringe, LCA4 Cheung Sha Wan Urban Fringe are predicted to be insubstantial.
Visual Impact
12.8.3 The unmitigated visual impact of the Project on all identified Visual Sensitive Receivers (VSRs), R1 Residents at Lakeview Garden, R2 Residents of No. 8 Caldecott Road Former Government Apartment, T1 Visitors in Kam Shan Country Park and T2 Trail Walkers in Lower Shing Mun Reservoir are predicted to be moderate adverse due to the appearance of new water intake or outfall structures together with the loss of surrounding vegetations. Through the mitigation measures by enhancing the appearance of the structures, compensatory planting of trees as well as restoration of shrubs at the works areas, it is expected to reduce the visual impacts after mitigation to slight adverse impacts.
12.8.4 Overall, the proposed water tunnel portals with water intake and outfall structures in the Project is considered to be acceptable with the implementation of mitigation measures recommended in the EIA.
12.9.1 The Cultural Heritage Impact Assessment for the project has identified that there are sensitive historical structures in the vicinity of the proposed works and that mitigation in the form of vibration monitoring may be required during the construction phase at Intake A. Although no adverse impacts on the historical structures are anticipated, conducting a condition survey prior to the construction phase as a precautionary mitigation measure is recommended and the survey report shall be submitted to AMO for review prior to the commencement of the construction phase.
12.10.1 This EIA has provided information on the nature and extent of environmental impacts arising from the construction and operation of the project and has revealed no insurmountable environmental issues.
Appendices
Appendix B Construction Program, Envisaged Activities and Inventory of PME
Appendix C Unmitigated Construction Noise Impact
(Air-borne)
Table C‑1 Plant Inventory and the SWL at Intake End (Portal A)
Table C‑3 Plant Inventory and SWL at Outfall End (Portal D)
Table C‑4 Plant Inventory and SWL at Outfall end (Portal D)
Table C‑5 Plant Inventory and SWL along Tunnel by TBM
Appendix D (Not Used)
Appendix E Ground-borne Noise Impact
Table E‑2 Conversion Factors from Floor Vibration Levels to Indoor Reverberant Noise Levels
Table E‑3 Coupling Loss Calculation from Bedrock to Piles
Table E‑4 Sample Calculation of Ground-borne
Noise Impact (TBM),
Table E‑5 Sample Calculation of Ground-borne
Noise Impact (TBM),
Table E‑6 Sample Calculation of Ground-borne Noise Impact (TBM), Golden Time Villas
Table E‑7 Sample Calculation of Ground-borne Noise Impact (TBM), Village House
Table E‑8 Sample Calculation of Ground-borne
Noise Impact (Construction Equipment),
Table E‑9 Sample Calculation of Ground-borne
Noise Impact (Construction Equipment),
Table E‑10 Sample Calculation of Ground-borne Noise Impact (Construction Equipment), Golden Time Villas
Table E‑11 Sample Calculation of Ground-borne Noise Impact (Construction Equipment), Village House
Appendix F Baseline Raw Water Quality at
Appendix G Ecological Survey Results
Table G‑1a Status and Relative Abundance of Plant
Species Recorded within Worksite Area at the
Scientist
Name |
Native
to HK |
Habit
(1) |
Status
(2) |
Secondary
|
Achyranthes aspera |
Y |
H |
- |
+ |
Acronychia pedunculata |
Y |
T |
- |
+++ |
Adiantum flabellulatum |
Y |
H |
- |
+ |
Alangium chinense |
Y |
T |
- |
+ |
Alocasia odora |
Y |
H |
- |
++ |
Antidesma ghaesembilla |
Y |
T |
- |
+ |
Antirhea chinensis |
Y |
T |
- |
+ |
Aporusa dioica |
Y |
T |
- |
++ |
Archidendron lucidum |
Y |
T |
- |
+ |
Ardisia crenata |
Y |
S |
- |
+ |
Artocarpus hypargyreus |
Y |
T |
(c) (f)VU |
+ |
Bauhinia variegata |
Y |
T |
- |
+ |
Bidens alba |
N |
H |
- |
++ |
Bridelia tomentosa |
Y |
S |
- |
+ |
Cansjera rheedii |
Y |
C |
- |
+ |
Carallia brachiata |
Y |
T |
- |
++ |
Celtis sinensis |
Y |
T |
- |
++ |
Cratoxylum cochinchinense |
Y |
T |
- |
++ |
Cynodon dactylon |
Y |
H |
- |
++ |
Dalbergia benthamii |
Y |
C |
- |
+ |
Dalbergia millettii |
Y |
C |
- |
+ |
Daphniphyllum calycinum |
Y |
T |
- |
+ |
Desmodium tortuosum |
N |
H |
- |
+ |
Desmos chinensis |
Y |
S |
- |
++ |
Dianella ensifolia |
Y |
H |
- |
++ |
Dimocarpus longan |
N |
T |
- |
+ |
Embelia ribes |
Y |
C |
- |
+ |
Eucalyptus robusta |
N |
T |
- |
+ |
Eurya nitida |
Y |
S |
- |
+ |
Ficus hirta |
Y |
S |
- |
++ |
Ficus hispida |
Y |
S |
- |
++ |
Ficus variolosa |
Y |
S |
- |
+ |
Garcinia oblongifolia |
Y |
T |
- |
++ |
Gardenia jasminoides |
Y |
S |
- |
+ |
Glochidion hirsutum |
Y |
S |
- |
+ |
Gnetum luofuense |
Y |
C |
- |
+++ |
Gordonia
axillaris |
Y |
T |
- |
+ |
Hypserpa nitida |
Y |
C |
- |
+ |
Ilex asprella |
Y |
S |
- |
++ |
Ilex memecylifolia |
Y |
T |
- |
+ |
Ipomoea cairica |
N |
C |
- |
++ |
Lantana camara |
N |
S |
- |
++ |
Lasianthus chinensis |
Y |
S |
- |
+ |
Liriope spicata |
Y |
H |
- |
++ |
Litchi chinensis |
N |
T |
- |
+ |
Litsea rotundifolia |
Y |
S |
- |
++ |
Lonicera macrantha |
Y |
C |
- |
+ |
Lophatherum gracile |
Y |
H |
- |
++ |
Lygodium flexuosum |
Y |
C |
- |
+ |
Machilus chekiangensis |
Y |
T |
- |
+ |
Malvaviscus arboreus |
N |
S |
- |
+ |
Microcos paniculata |
Y |
S |
- |
++ |
Mikania micrantha |
N |
C |
- |
++ |
Millettia dielsiana |
Y |
C |
- |
+ |
Miscanthus floridulus |
Y |
H |
- |
+ |
Neyraudia reynaudiana |
Y |
H |
- |
+ |
Ormosia semicastrata |
Y |
T |
- |
+ |
Paederia scandens |
Y |
C |
- |
++ |
Pandanus tectorius |
Y |
S |
- |
+ |
Phyllanthus cochinchinensis |
Y |
S |
- |
++ |
Psychotria asiatica |
Y |
S |
- |
+++ |
Rhus succedanea |
Y |
S |
- |
++ |
Rourea microphylla |
Y |
C |
- |
+ |
Sageretia thea |
Y |
S |
- |
++ |
Schefflera heptaphylla |
Y |
T |
- |
+++ |
Schizostachyum dumetorum |
Y |
S |
- |
++ |
Smilax glabra |
Y |
C |
- |
+ |
Stachytarpheta jamaicensis |
N |
S |
- |
+ |
Sterculia lanceolata |
Y |
T |
- |
+++ |
Strychnos angustiflora |
Y |
C |
- |
++ |
Synedrella nodiflora |
N |
H |
- |
+ |
Tetracera asiatica |
Y |
C |
- |
+ |
Trema tomentosa |
Y |
S |
- |
+ |
Tylophora ovata |
Y |
C |
- |
+ |
(1) Habit: T=Tree;
S=Shrub / Bamboo; H=Herb; C=Climber.
(2) Status: (a)
listed species in Forestry Regulation (Cap.96 sub. Leg.);
(b)
listed species in Protection of Endangered Species of Animals and Plants
Ordinance (Cap 586);
(c)
listed species in AFCD’s Rare and Precious Plants of Hong Kong;
(d)
rare species listed in Corlett’s study Hong Kong Vascular Plants: Distribution
and Status;
(e) listed in China Red Data Book: (e)EX:
Extinct; (e)EW: Extinct in the wild; (e)CR: Critically Endangered; (e)EN: Endangered; (e)VU: Vulnerable; (e)NT:
Near Threatened; (e)LC: Least Concern;
(f) listed in IUCN 2008: (f)EX: Extinct; (f)EW:
Extinct in the wild; (f)CR: Critically Endangered; (f)EN: Endangered; (f)VU: Vulnerable; (f)NT:
Near Threatened; (f)LC: Least Concern.
(3) Abundance: +++=abundant;
++=fairly abundant; +=low abundance
(4)
As the drainage channel within the site is a concrete structure while developed
area / bare ground is of negligible ecological value, weed species growing on
cracks of these two habitats were thus excluded from the list.
Table G‑1b Status and Relative Abundance of Plant
Species Recorded within Worksite Area at the
Scientist
Name |
Native
to HK |
Habit
(1) |
Status
(2) |
Grassland
(3) |
Reservoir
(3) (4) |
Acacia confusa |
N |
T |
- |
|
+++ |
Acronychia pedunculata |
Y |
T |
- |
|
++ |
Ageratum conyzoides |
N |
H |
- |
|
+++ |
Alangium chinense |
Y |
T |
- |
|
++ |
Aporusa dioica |
Y |
T |
- |
|
++ |
Bidens alba |
N |
H |
- |
++ |
+++ |
Brachiaria mutica |
N |
H |
- |
+ |
++ |
Breynia fruticosa |
Y |
S |
- |
+ |
++ |
Byttneria aspera |
Y |
C |
- |
+ |
|
Centella asiatica |
Y |
H |
- |
+ |
+ |
Conyza bonariensis |
N |
H |
- |
+ |
+ |
Crotalaria pallida |
N |
H |
- |
|
+ |
Cyclea hypoglauca |
Y |
C |
- |
|
+ |
Cyclosorus acuminatus |
Y |
H |
- |
+ |
+ |
Cynodon dactylon |
Y |
H |
- |
+ |
++ |
Cyperus rotundus |
Y |
H |
- |
|
+ |
Cyrtococcum accrescens |
Y |
H |
- |
|
++ |
Dendrotrophe frutescens |
Y |
C |
- |
|
+ |
Desmos chinensis |
Y |
S |
- |
|
+ |
Dianella ensifolia |
Y |
H |
- |
|
++ |
Dicranopteris pedata |
Y |
H |
- |
|
++ |
Digitaria longiflora |
Y |
H |
- |
+ |
++ |
Eclipta prostrata |
Y |
H |
- |
|
+ |
Elephantopus tomentosus |
Y |
H |
- |
|
+ |
Eleusine indica |
Y |
H |
- |
+ |
++ |
Embelia ribes |
Y |
C |
- |
|
++ |
Emilia sonchifolia |
Y |
H |
- |
+ |
+ |
Eriocaulon sexangulare |
Y |
H |
- |
|
+ |
Ficus hirta |
Y |
S |
- |
|
+ |
Ficus hispida |
Y |
T |
- |
+ |
+ |
Ficus
variegata |
Y |
T |
- |
+ |
|
Glochidion wrightii |
Y |
S |
- |
|
+ |
Glochidion zeylanicum |
Y |
T |
- |
|
+ |
Gnetum luofuense |
Y |
C |
- |
+ |
++ |
Hedyotis acutangula |
Y |
H |
- |
|
++ |
Hedyotis auricularia |
Y |
H |
- |
|
+ |
Hedyotis hedyotidea |
Y |
S |
- |
|
+ |
Hypericum japonicum |
Y |
H |
- |
|
+ |
Ilex asprella |
Y |
S |
- |
|
++ |
Ipomoea cairica |
N |
C |
- |
+ |
++ |
Ipomoea triloba |
Y |
H |
- |
|
+ |
Lantana camara |
N |
S |
- |
+ |
+ |
Leucaena leucocephala |
N |
T |
- |
|
++ |
Ligustrum sinense |
Y |
S |
- |
+ |
+ |
Liriope spicata |
Y |
H |
- |
|
+ |
Litsea glutinosa |
Y |
T |
- |
|
+ |
Litsea cubeba |
Y |
T |
- |
+ |
++ |
Litsea rotundifolia |
Y |
S |
- |
|
++ |
Lophatherum gracile |
Y |
H |
- |
|
+ |
Ludwigia octovalvis |
Y |
H |
- |
|
+ |
Lygodium japonicum |
Y |
C |
- |
+ |
+ |
Macaranga tanarius |
Y |
T |
- |
+ |
++ |
Maesa perlarius |
Y |
S |
- |
++ |
++ |
Mallotus paniculatus |
Y |
T |
- |
++ |
+++ |
Melastoma candidum |
Y |
S |
- |
|
++ |
Melastoma sanguineum |
Y |
S |
- |
|
++ |
Melia azedarach |
N |
T |
- |
+ |
+ |
Melicope pteleifolia |
Y |
S |
- |
|
+ |
Microcos paniculata |
Y |
S |
- |
|
+ |
Microstegium ciliatum |
Y |
H |
- |
+++ |
+ |
Mikania micrantha |
N |
C |
- |
++ |
+++ |
Mimosa pudica |
N |
H |
- |
+ |
+ |
Miscanthus sinensis |
Y |
H |
- |
+++ |
+ |
Mussaenda pubescens |
Y |
S |
- |
+ |
+ |
Neyraudia reynaudiana |
Y |
H |
- |
+ |
++ |
Paederia scandens |
Y |
C |
- |
|
++ |
Panicum brevifolium |
Y |
H |
- |
|
++ |
Panicum maximum |
N |
H |
- |
++ |
+++ |
Panicum repens |
Y |
H |
- |
|
+ |
Paspalum conjugatum |
N |
H |
- |
|
++ |
Paspalum orbiculare |
Y |
H |
- |
|
++ |
Pavetta hongkongensis |
Y |
S |
(a) |
|
+ |
Pennisetum polystachyon |
N |
H |
- |
|
++ |
Phyllanthus emblica |
Y |
T |
- |
|
+ |
Polygonum hydropiper |
Y |
H |
- |
|
+ |
Polygonum perfoliatum |
Y |
H |
- |
|
+ |
Psychotria asiatica |
Y |
S |
- |
|
++ |
Psychotria serpens |
Y |
C |
- |
|
+ |
Pteris semipinnata |
Y |
H |
- |
|
++ |
Pueraria lobata |
Y |
C |
- |
|
+ |
Rhus hypoleuca |
Y |
S |
- |
|
++ |
Rhus succedanea |
Y |
T |
- |
|
+ |
Rhynchelytrum repens |
N |
H |
- |
+ |
++ |
Rhynchospora rubra |
Y |
H |
- |
|
+ |
Rubus leucanthus |
Y |
C |
- |
+ |
+ |
Rubus reflexus |
Y |
C |
- |
++ |
++ |
Sageretia thea |
Y |
S |
- |
|
++ |
Sapium discolor |
Y |
T |
- |
|
++ |
Sarcandra glabra |
Y |
S |
- |
+ |
+ |
Schefflera heptaphylla |
Y |
T |
- |
+ |
+++ |
Schima
superba |
Y |
T |
- |
|
+ |
Scoparia dulcis |
N |
H |
- |
|
++ |
Setaria glauca |
Y |
H |
- |
|
+ |
Smilax china |
Y |
C |
- |
|
+ |
Solanum nigrum |
Y |
H |
- |
|
++ |
Sphenomeris chinensis |
Y |
H |
- |
|
+ |
Stachytarpheta jamaicensis |
N |
S |
- |
|
+++ |
Stephania longa |
Y |
C |
- |
+ |
+ |
Synedrella nodiflora |
N |
H |
- |
|
+ |
Tetracera asiatica |
Y |
C |
- |
|
+ |
Trema tomentosa |
Y |
S |
- |
+ |
+ |
Tylophora ovata |
Y |
C |
- |
|
+ |
Urena lobata |
Y |
H |
- |
|
+ |
Zanthoxylum avicennae |
Y |
T |
- |
|
+ |
(1) Habit: T=Tree;
S=Shrub / Bamboo; H=Herb; C=Climber.
(2) Status: (a)
listed species in Forestry Regulation (Cap.96 sub. Leg.);
(b)
listed species in Protection of Endangered Species of Animals and Plants
Ordinance (Cap 586);
(c)
listed species in AFCD’s Rare and Precious Plants of Hong Kong;
(d)
rare species listed in Corlett’s study Hong Kong Vascular Plants: Distribution
and Status;
(e) listed in China Red Data Book: (e)EX:
Extinct; (e)EW: Extinct in the wild; (e)CR: Critically Endangered; (e)EN: Endangered; (e)VU: Vulnerable; (e)NT:
Near Threatened; (e)LC: Least Concern;
(f) listed in IUCN 2008: (f)EX: Extinct; (f)EW:
Extinct in the wild; (f)CR: Critically Endangered; (f)EN: Endangered; (f)VU: Vulnerable; (f)NT:
Near Threatened; (f)LC: Least Concern.
(3) Abundance: +++=abundant;
++=fairly abundant; +=low abundance
(4) Species were recorded on slopes and exposed areas
of the reservoir.
Table G‑1c Status and Relative Abundance of Plant Species Recorded within the Study Area (21, 24, 25 September 2007; 25, 29, 31 October 2007; 2, 15, 16 November 2007; 5, 14, 17 December 2007; 3, 4, 7 January 2008; 5, 6, 12 February 2008)
Scientist
Name |
Native
to HK |
Habit
(1) |
Status
(2) |
Grass- land
(3) |
Secondary (3) |
Stream
/ Drainage Channel (3) |
Reservoir
(3) |
Acacia
confusa |
N |
T |
- |
|
+++ |
|
+++ |
Acacia mangium |
N |
T |
- |
|
+ |
|
|
Achyranthes aspera |
Y |
H |
- |
|
+ |
|
|
Acronychia pedunculata |
Y |
T |
- |
|
+++ |
|
+++ |
Actinidia latifolia |
Y |
S |
- |
|
+ |
|
|
Adenosma glutinosum |
Y |
H |
- |
|
+ |
|
|
Adiantum flabellulatum |
Y |
H |
- |
|
++ |
|
|
Adina pilulifera |
Y |
T |
- |
|
+++ |
+++ |
|
Ageratum conyzoides |
N |
H |
- |
|
|
+ |
+++ |
Ageratum houstonianum |
N |
H |
- |
|
|
+ |
+ |
Alangium chinense |
Y |
T |
- |
|
++ |
+ |
++ |
Albizia corniculata |
Y |
S |
- |
|
+ |
|
|
Albizia lebbeck |
N |
T |
- |
|
+ |
|
|
Alchornea trewioides |
Y |
S |
- |
|
++ |
|
|
Allamanda cathartica |
N |
S |
- |
|
+ |
|
|
Alleizettella leucocarpa |
Y |
S |
- |
|
+ |
|
|
Alocasia odora |
Y |
H |
- |
|
+ |
|
|
Alpinia hainanensis |
Y |
H |
- |
|
+ |
|
|
Alpinia oblongifolia |
Y |
H |
- |
|
+ |
|
|
Alpinia stachyodes |
Y |
H |
- |
|
+ |
|
|
Alysicarpus vaginalis |
Y |
H |
- |
|
+ |
|
|
Alyxia sinensis |
T |
C |
- |
|
+ |
|
|
Amaranthus viridis |
Y |
H |
- |
|
+ |
|
|
Ampelopsis cantoniensis |
Y |
C |
- |
|
+ |
|
|
Antidesma ghaesembilla |
Y |
T |
- |
|
+ |
|
|
Antidesma japonicum |
Y |
T |
- |
|
+ |
|
|
Antidesma venosum |
Y |
T |
- |
|
+ |
|
|
Antirhea chinensis |
Y |
S |
- |
|
+++ |
+ |
++ |
Apluda mutica |
Y |
H |
- |
|
+ |
|
|
Aporusa dioica |
Y |
T |
- |
|
+++ |
+++ |
+++ |
Aquilaria sinensis |
Y |
T |
(c), (e)VU, (f)VU |
|
+++ |
+ |
+ |
Archidendron clypearia |
Y |
T |
- |
|
++ |
+ |
+ |
Archidendron
lucidum |
Y |
T |
- |
|
++ |
|
+ |
Ardisia crenata |
Y |
S |
- |
|
++ |
|
|
Ardisia lindleyana |
Y |
S |
- |
|
+ |
|
|
Ardisia quinquegona |
Y |
S |
- |
|
+ |
|
|
Artemisia capillaries |
Y |
H |
- |
|
|
|
+ |
Artocarpus hypargyreus |
Y |
T |
(c), (f)VU |
|
+++ |
|
++ |
Artocarpus macrocarpon |
N |
T |
- |
|
+ |
|
|
Arundinaria hindsii |
Y |
S |
- |
|
++ |
+ |
+ |
Asparagus cochinchinensis |
Y |
H |
- |
|
+ |
|
+ |
Aster baccharoides |
Y |
H |
- |
|
+ |
|
|
Baeckea frutescens |
Y |
T |
- |
|
+++ |
|
|
Bauhinia championii |
Y |
C |
- |
|
+ |
|
|
Bauhinia purpurea |
N |
T |
- |
|
+ |
|
|
Bauhinia variegata |
Y |
T |
- |
|
+ |
|
|
Berchemia floribunda |
Y |
C |
- |
|
++ |
|
|
Bidens alba |
N |
H |
- |
++ |
+ |
|
+++ |
Bischofia javanica |
Y |
T |
- |
|
+ |
|
|
Blechnum orientale |
Y |
H |
- |
|
+ |
|
+ |
Blumea megacephala |
Y |
C |
- |
|
+ |
|
+ |
Bothriochloa bladhii |
Y |
H |
- |
|
+ |
|
|
Bougainvillea spectabilis |
N |
S |
- |
|
+ |
|
|
Brachiaria mutica |
N |
H |
- |
+ |
+ |
|
++ |
Breynia fruticosa |
Y |
S |
- |
+ |
+++ |
+ |
++ |
Bridelia tomentosa |
Y |
T |
- |
|
++ |
|
+ |
Byttneria aspera |
Y |
C |
- |
+ |
+ |
+ |
+ |
Caesalpinia crista |
Y |
C |
- |
|
++ |
++ |
+ |
Caesalpinia vernalis |
Y |
C |
- |
|
+ |
+ |
|
Cajanus scarabaeoides |
Y |
C |
- |
|
+ |
|
|
Callicarpa nudiflora |
Y |
S |
- |
|
+ |
+ |
|
Campsis grandiflora |
N |
C |
- |
|
+ |
|
|
Canarium album |
N |
T |
- |
|
+ |
|
|
Cansjera rheedii |
Y |
C |
- |
|
+ |
|
|
Canthium dicoccum |
Y |
T |
- |
|
++ |
|
|
Carallia brachiata |
Y |
T |
- |
|
++ |
++ |
++ |
Cassytha filiformis |
Y |
C |
- |
|
+ |
+ |
+ |
Castanopsis carlesii |
Y |
T |
(d) |
|
+ |
|
|
Castanopsis fabri |
Y |
T |
- |
|
+ |
|
|
Castanopsis fissa |
Y |
T |
- |
|
++ |
|
|
Casuarina equisetifolia |
N |
T |
- |
|
+ |
|
+ |
Celtis sinensis |
Y |
T |
- |
|
++ |
|
+ |
Centella asiatica |
Y |
H |
- |
+ |
+ |
+ |
+ |
Centotheca lappacea |
Y |
H |
- |
|
+ |
+ |
+ |
Choerospondias axillaris |
Y |
T |
- |
|
+ |
|
|
Chrysopogon aciculatus |
Y |
H |
- |
|
+ |
|
|
Cibotium barometz |
Y |
H |
(b) (c) |
|
+++ |
++ |
+ |
Cinnamomum camphora |
Y |
T |
- |
|
++ |
|
+ |
Cinnamomum parthenoxylon |
Y |
T |
- |
|
+ |
|
|
Citrus maxima |
N |
T |
- |
|
+ |
|
|
Citrus reticulata |
N |
T |
- |
|
+ |
|
|
Cleistocalyx operculatus |
Y |
T |
- |
|
++ |
+++ |
+++ |
Clematis meyeniana |
Y |
C |
- |
|
++ |
+ |
+ |
Clerodendrum chinense |
Y |
S |
- |
|
+ |
|
|
Clerodendrum fortunatum |
Y |
S |
- |
|
+ |
|
+ |
Cocculus orbiculatus |
Y |
C |
- |
|
+ |
+ |
+ |
Codonacanthus pauciflorus |
Y |
H |
- |
|
+ |
|
|
Coix lacryma-jobi |
Y |
H |
- |
|
+ |
|
|
Conyza bonariensis |
N |
H |
- |
+ |
+ |
|
+ |
Cordia dichotoma |
Y |
T |
- |
|
+ |
|
|
Cordyline fruticosa |
N |
S |
- |
|
+ |
|
|
Crateva unilocularis |
N |
T |
- |
|
+ |
|
|
Cratoxylum cochinchinense |
Y |
T |
- |
|
+++ |
++ |
+++ |
Crotalaria pallida |
N |
H |
- |
|
|
|
+ |
Cyclea hypoglauca |
Y |
C |
- |
|
+ |
+ |
+ |
Cyclosorus acuminatus |
Y |
H |
- |
+ |
+ |
+ |
+ |
Cyclosorus interruptus |
Y |
H |
- |
|
+ |
+ |
+ |
Cynodon dactylon |
Y |
H |
- |
+ |
+ |
|
+ |
Cyperus rotundus |
Y |
H |
- |
|
+ |
+ |
+ |
Cyrtococcum accrescens |
Y |
H |
- |
|
++ |
+ |
++ |
Daemonorops margaritae |
Y |
C |
- |
|
+ |
|
|
Dalbergia benthamii |
Y |
C |
- |
|
++ |
++ |
+ |
Dalbergia hancei |
Y |
C |
- |
|
++ |
++ |
++ |
Dalbergia millettii |
Y |
C |
- |
|
+ |
+ |
+ |
Daphniphyllum calycinum |
Y |
T |
- |
|
+ |
|
|
Delonix regia |
N |
T |
- |
|
+ |
|
|
Dendranthema indicum |
Y |
H |
- |
|
+ |
|
|
Dendrotrophe frutescens |
Y |
C |
- |
|
++ |
+ |
++ |
Desmodium heterocarpon |
Y |
S |
- |
|
+ |
|
|
Desmodium tortuosum |
N |
H |
- |
|
+ |
|
+ |
Desmos chinensis |
Y |
S |
- |
|
+++ |
++ |
++ |
Dianella ensifolia |
Y |
H |
- |
|
+++ |
+ |
+ |
Dichrocephala integrifolia |
Y |
H |
- |
|
+ |
|
|
Dicranopteris pedata |
Y |
H |
- |
|
++ |
++ |
++ |
Digitaria longiflora |
Y |
H |
- |
+ |
+ |
|
|
Dimocarpus longan |
N |
T |
- |
|
+ |
|
|
Dioscorea benthamii |
Y |
C |
- |
|
+ |
|
|
Diospyros eriantha |
Y |
S |
- |
|
++ |
|
|
Diospyros
morrisiana |
Y |
T |
- |
|
+++ |
+ |
+ |
Diospyros vaccinioides |
Y |
S |
- |
|
++ |
+ |
|
Diploclisia glaucescens |
Y |
C |
- |
|
+ |
+ |
|
Diplospora dubia |
Y |
S |
- |
|
++ |
++ |
|
Dracaena marginata |
N |
S |
- |
|
+ |
|
|
Dracaena reflexa |
N |
S |
- |
|
+ |
|
|
Drosera spathulata |
Y |
H |
- |
|
+ |
+ |
|
Duranta erecta |
N |
S |
- |
|
+ |
|
|
Eclipta prostrate |
Y |
H |
- |
|
|
|
+ |
Elaeocarpus chinensis |
Y |
T |
- |
|
++ |
|
|
Elephantopus scaber |
Y |
H |
- |
|
+ |
|
|
Elephantopus tomentosus |
Y |
H |
- |
|
+ |
|
+ |
Eleusine indica |
Y |
H |
- |
+ |
+ |
|
+ |
Eleutherococcus trifoliatus |
Y |
S |
- |
|
++ |
++ |
++ |
Embelia laeta |
Y |
C |
- |
|
++ |
+ |
+ |
Embelia ribes |
Y |
C |
- |
|
+++ |
++ |
++ |
Emilia sonchifolia |
Y |
H |
- |
+ |
+ |
|
+ |
Enkianthus quinqueflorus |
Y |
S |
(a) |
|
++ |
|
|
Eragrostis tenella |
Y |
H |
- |
|
+++ |
++ |
+ |
Eriobotrya japonica |
N |
T |
- |
|
+ |
|
|
Eriocaulon sexangulare |
Y |
H |
- |
|
|
|
+ |
Erythrina variegata |
N |
T |
- |
|
+ |
|
|
Eucalyptus robusta |
N |
T |
- |
|
+ |
|
|
Eucalyptus torelliana |
N |
T |
- |
|
+ |
|
|
Euphorbia hirta |
N |
H |
- |
|
+ |
|
|
Euphorbia prostrata |
N |
H |
- |
|
+ |
|
|
Euphorbia thymifolia |
Y |
H |
- |
|
+ |
|
|
Eurya macartneyi |
Y |
S |
- |
|
++ |
+ |
|
Eurya nitida |
Y |
S |
- |
|
++ |
++ |
++ |
Ficus fistulosa |
Y |
T |
- |
|
++ |
+++ |
+ |
Ficus hirta |
Y |
S |
- |
|
+++ |
++ |
+ |
Ficus hispida |
Y |
T |
- |
+ |
++ |
++ |
+ |
Ficus microcarpa |
Y |
T |
- |
|
+ |
|
|
Ficus religiosa |
N |
T |
- |
|
+ |
|
|
Ficus superba |
Y |
T |
- |
|
+ |
|
++ |
Ficus
variegata |
Y |
T |
- |
+ |
++ |
|
+ |
Ficus variolosa |
Y |
S |
- |
|
++ |
|
|
Ficus virens |
Y |
T |
- |
|
+ |
|
|
Gahnia tristis |
Y |
H |
- |
|
+ |
|
|
Garcinia oblongifolia |
Y |
T |
- |
|
++ |
+ |
+ |
Gardenia jasminoides |
Y |
S |
- |
|
++ |
|
|
Glochidion eriocarpum |
Y |
S |
- |
|
+++ |
++ |
++ |
Glochidion hirsutum |
Y |
S |
- |
|
+ |
|
|
Glochidion lanceolarium |
Y |
T |
- |
|
+ |
|
|
Glochidion wrightii |
Y |
S |
- |
|
++ |
+ |
++ |
Glochidion zeylanicum |
Y |
T |
- |
|
+ |
+ |
+ |
Gnetum luofuense |
Y |
C |
- |
|
+++ |
+++ |
+++ |
Gordonia
axillaris |
Y |
T |
- |
|
+++ |
|
+++ |
Graphistemma pictum |
Y |
C |
- |
|
+ |
|
|
Gymnema sylvestre |
Y |
C |
- |
|
+ |
|
|
Hedyotis acutangula |
Y |
H |
- |
|
++ |
|
+ |
Hedyotis auricularia |
Y |
H |
- |
|
+ |
|
+ |
Hedyotis corymbosa |
Y |
H |
- |
|
+ |
+ |
+ |
Hedyotis hedyotidea |
Y |
S |
- |
|
+ |
|
|
Helicteres angustifolia |
Y |
S |
- |
|
+++ |
|
|
Heterosmilax japonica |
Y |
S |
- |
|
+ |
|
|
Hippeastrum vittatum |
N |
H |
- |
|
+ |
|
|
Homalium cochinchinensis |
Y |
T |
- |
|
++ |
|
|
Hymenocallis littoralis |
N |
H |
- |
|
+ |
|
|
Hypericum japonicum |
Y |
H |
- |
|
+ |
+ |
+ |
Hypserpa nitida |
Y |
C |
- |
|
+ |
|
|
Ilex asprella |
Y |
S |
- |
|
+++ |
+ |
++ |
Ilex graciliflora |
Y |
T |
- |
|
+ |
|
|
Ilex memecylifolia |
Y |
T |
- |
|
++ |
|
+ |
Ilex pubescens |
Y |
S |
- |
|
+++ |
+ |
+ |
Y |
T |
- |
|
+ |
|
|
|
Indocalamus sinicus |
Y |
S |
- |
|
+ |
|
|
Ipomoea batatas |
N |
H |
- |
|
+ |
|
|
Ipomoea cairica |
N |
C |
- |
+ |
+ |
|
+ |
Ipomoea triloba |
Y |
H |
- |
|
|
|
+ |
Itea chinensis |
Y |
T |
- |
|
+++ |
|
|
Ixonanthes reticulata |
Y |
T |
(c), (e)VU |
|
+++ |
|
|
Ixora chinensis |
Y |
S |
- |
|
+ |
|
|
Lagerstroemia speciosa |
N |
T |
- |
|
+ |
|
|
Lantana camara |
N |
S |
- |
+ |
+ |
|
+ |
Lasianthus chinensis |
Y |
S |
- |
|
+ |
|
|
Lepidosperma chinense |
Y |
H |
- |
|
++ |
|
|
Leucaena leucocephala |
N |
T |
- |
|
+ |
|
+ |
Ligustrum sinense |
Y |
S |
- |
+ |
++ |
|
+ |
Lindera aggregata |
Y |
S |
- |
|
+ |
|
|
Lindernia crustacean |
Y |
H |
- |
|
+ |
|
|
Lindsaea orbiculata |
Y |
H |
- |
|
++ |
|
|
Liparis nervosa |
Y |
H |
(a) (b) |
|
+ |
+ |
+ |
Liriope spicata |
Y |
H |
- |
|
+++ |
++ |
|
Litchi chinensis |
N |
T |
- |
|
+ |
|
|
Lithocarpus corneus |
Y |
T |
- |
|
+ |
|
|
Litsea cubeba |
Y |
T |
- |
+ |
+++ |
+ |
++ |
Litsea glutinosa |
Y |
T |
- |
|
+++ |
+ |
+++ |
Litsea rotundifolia |
Y |
S |
- |
|
+++ |
+++ |
+++ |
Livistona chinensis |
N |
T |
- |
|
+ |
|
|
Lonicera confusa |
Y |
C |
- |
|
+ |
|
|
Lonicera macrantha |
Y |
C |
- |
|
+ |
|
|
Lophatherum gracile |
Y |
H |
- |
|
+ |
|
+ |
Lophostemon confertus |
N |
T |
- |
|
++ |
|
++ |
Ludwigia octovalvis |
Y |
H |
- |
|
+ |
|
+ |
Ludwigia perennis |
Y |
H |
- |
|
|
|
+ |
Lygodium japonicum |
Y |
C |
- |
+ |
+ |
|
+ |
Lygodium scandens |
Y |
C |
- |
|
+ |
|
+ |
Macaranga tanarius |
Y |
T |
- |
+ |
+ |
|
+ |
Machilus chekiangensis |
Y |
T |
- |
|
++ |
|
|
Machilus velutina |
Y |
T |
- |
|
+ |
|
|
Maesa japonica |
Y |
S |
- |
|
++ |
|
+ |
Maesa perlarius |
Y |
S |
- |
++ |
+++ |
|
++ |
Mallotus paniculatus |
Y |
T |
- |
++ |
+++ |
|
+++ |
Malvastrum coromandelianum |
Y |
S |
- |
|
+ |
|
|
Malvaviscus arboreus |
N |
S |
- |
|
+ |
|
|
Mangifera indica |
N |
T |
- |
|
+ |
|
|
Manihot esculenta |
N |
S |
- |
|
+ |
|
|
Melaleuca quinquenervia |
N |
T |
- |
|
++ |
|
++ |
Melastoma candidum |
Y |
S |
- |
|
+++ |
|
++ |
Melastoma dodecandrum |
Y |
S |
- |
|
++ |
|
+ |
Melastoma sanguineum |
Y |
S |
- |
|
+++ |
|
++ |
Melia azedarach |
N |
T |
- |
+ |
+ |
|
+ |
Melicope pteleifolia |
Y |
S |
- |
|
++ |
|
+ |
Melodinus suaveolens |
Y |
C |
- |
|
++ |
|
++ |
Merremia umbellate |
Y |
C |
- |
|
+ |
|
|
Michelia alba |
N |
T |
- |
|
+ |
|
|
Microcos paniculata |
Y |
S |
- |
|
++ |
|
++ |
Microstegium ciliatum |
Y |
H |
- |
+++ |
|
|
+ |
Mikania micrantha |
N |
C |
- |
++ |
+ |
++ |
+ |
Millettia dielsiana |
Y |
C |
- |
|
++ |
+ |
+ |
Millettia nitida |
Y |
S |
- |
|
+ |
|
|
Millettia speciosa |
Y |
C |
- |
|
+ |
|
|
Mimosa pudica |
N |
H |
- |
+ |
+ |
+ |
+ |
Miscanthus floridulus |
Y |
H |
- |
|
+ |
+ |
+ |
Miscanthus sinensis |
Y |
H |
- |
+++ |
+ |
|
+ |
Morinda parvifolia |
Y |
C |
- |
|
+ |
|
+ |
Morinda umbellata |
Y |
C |
- |
|
+++ |
+ |
|
Murraya paniculata |
N |
T |
- |
|
+ |
|
+ |
Musa x paradisiaca |
N |
H |
- |
|
+ |
|
|
Mussaenda pubescens |
Y |
S |
- |
+ |
+++ |
+ |
+ |
Myrica rubra |
Y |
T |
- |
|
++ |
|
|
Myrsine seguinii |
Y |
S |
- |
|
+ |
|
|
Neyraudia reynaudiana |
Y |
H |
- |
+ |
+ |
+ |
++ |
Ormosia emarginata |
Y |
T |
- |
|
+ |
|
|
Ormosia semicastrata |
Y |
T |
- |
|
+ |
|
|
Osmanthus fragrans |
N |
S |
- |
|
+ |
|
|
Osmunda japonica |
Y |
H |
- |
|
+ |
|
|
Oxalis corniculata |
Y |
H |
- |
|
+ |
|
|
Pachira macrocarpa |
N |
T |
- |
|
+ |
|
|
Paederia scandens |
Y |
C |
- |
|
+ |
+ |
+ |
Palhinhaea cernua |
Y |
H |
- |
|
+ |
+ |
+ |
Pandanus tectorius |
Y |
S |
- |
|
+ |
+ |
+ |
Panicum brevifolium |
Y |
H |
- |
|
++ |
|
+ |
Panicum maximum |
N |
H |
- |
++ |
+ |
+ |
++ |
Panicum repens |
Y |
H |
- |
|
+ |
|
+ |
Paraixeris denticulata |
Y |
H |
- |
|
+ |
|
|
Paspalum conjugatum |
N |
H |
- |
|
|
|
+ |
Paspalum orbiculare |
Y |
H |
- |
|
+ |
|
+ |
Pavetta hongkongensis |
Y |
S |
(a) |
|
+++ |
+ |
+ |
Pennisetum polystachyon |
N |
H |
- |
|
|
|
+ |
Pennisetum purpureum |
N |
H |
- |
|
|
+ |
+ |
Pentasachme caudatum |
Y |
H |
- |
|
|
++ |
|
Peristylus tentaculatus |
Y |
H |
(a) (b) |
|
+ |
+ |
|
|
Y |
T |
- |
|
+ |
|
|
Phyllanthus cochinchinensis |
Y |
S |
- |
|
++ |
+ |
|
Phyllanthus emblica |
Y |
T |
- |
|
+++ |
|
+ |
Phyllodium pulchellum |
Y |
S |
- |
|
+ |
|
|
Pilea microphylla |
N |
H |
- |
|
+ |
|
|
Pinus elliottii |
N |
T |
- |
|
+ |
|
|
Pinus massoniana |
Y |
T |
- |
|
++ |
|
|
Podocarpus macrophyllus |
Y |
T |
- |
|
+ |
|
|
Pogonatherum crinitum |
Y |
H |
- |
|
+ |
|
|
Polygonum chinense |
Y |
H |
- |
|
|
++ |
+ |
Polygonum hydropiper |
Y |
H |
- |
|
|
+ |
+ |
Polygonum perfoliatum |
Y |
H |
- |
|
|
|
+ |
Pothos chinensis |
Y |
H |
- |
|
+ |
|
|
Pouzolzia zeylanica |
Y |
H |
- |
|
+ |
|
|
Pronephrium simplex |
Y |
H |
- |
|
++ |
|
|
Psidium guajava |
N |
T |
- |
|
+ |
|
|
Psychotria asiatica |
Y |
S |
- |
|
+++ |
+++ |
+++ |
Psychotria serpens |
Y |
C |
- |
|
+ |
+ |
+ |
Pteridium aquilinum |
Y |
H |
- |
|
+ |
|
|
Pteris ensiformis |
Y |
H |
- |
|
++ |
++ |
++ |
Pteris semipinnata |
Y |
H |
- |
|
++ |
++ |
++ |
Pteris vittata |
Y |
H |
- |
|
+ |
|
|
Pueraria lobata |
Y |
C |
- |
|
+ |
|
+ |
Pyrrosia adnascens |
Y |
H |
- |
|
+ |
|
|
Reevesia thyrsoidea |
Y |
T |
- |
|
++ |
|
|
Rhaphiolepis indica |
Y |
S |
- |
|
++ |
|
|
Rhodomyrtus tomentosa |
Y |
S |
- |
|
+++ |
|
+++ |
Rhus hypoleuca |
Y |
S |
- |
|
++ |
|
+ |
Rhus succedanea |
Y |
T |
- |
|
++ |
|
+ |
Rhynchelytrum repens |
N |
H |
- |
+ |
+ |
|
+ |
Rhynchospora rubra |
Y |
H |
- |
|
|
|
+ |
|
Y |
C |
- |
|
+ |
|
|
Rourea microphylla |
Y |
C |
- |
|
++ |
+ |
+ |
Rubus leucanthus |
Y |
C |
- |
+ |
++ |
|
|
Rubus reflexus |
Y |
C |
- |
++ |
++ |
|
+ |
Sabia limoniacea |
Y |
C |
- |
|
+ |
+ |
+ |
Sageretia thea |
Y |
S |
- |
|
++ |
+ |
+ |
Sansevieria trifasciata |
N |
H |
- |
|
+ |
|
|
Sapindus saponaria |
Y |
T |
- |
|
+ |
|
|
Sapium discolour |
Y |
T |
- |
|
+++ |
|
+ |
Sarcandra glabra |
Y |
S |
- |
+ |
+++ |
|
+ |
Saurauia tristyla |
Y |
T |
- |
|
++ |
+++ |
+ |
Schefflera heptaphylla |
Y |
T |
- |
+ |
+++ |
+++ |
+++ |
Schima superba |
Y |
T |
- |
|
+++ |
+++ |
+++ |
Schizostachyum dumetorum |
Y |
S |
- |
|
++ |
+ |
+ |
Scleria ciliaris |
Y |
H |
- |
|
+ |
|
|
Scolopia saeva |
Y |
S |
- |
|
+ |
|
|
Scoparia dulcis |
N |
H |
- |
|
+ |
|
+ |
Scutellaria indica |
Y |
H |
- |
|
+ |
|
|
Selaginella biformis |
Y |
H |
- |
|
+ |
|
|
Senecio scandens |
Y |
H |
- |
|
+ |
|
|
Setaria glauca |
Y |
H |
- |
|
|
|
+ |
Setaria palmifolia |
Y |
H |
- |
|
+ |
|
|
Severinia buxifolia |
Y |
S |
- |
|
++ |
|
+ |
Sida rhombifolia |
Y |
S |
- |
|
+ |
|
|
Sinosideroxylon wightianum |
Y |
T |
- |
|
+ |
|
|
Smilax china |
Y |
C |
- |
|
+ |
|
|
Smilax glabra |
Y |
C |
- |
|
+ |
|
|
Smilax lanceifolia |
Y |
C |
- |
|
+ |
|
|
Solanum nigrum |
Y |
H |
- |
|
+ |
|
|
Solanum torvum |
N |
S |
- |
|
+ |
|
|
Solena amplexicaulis |
Y |
C |
- |
|
+ |
|
|
Spathodea campanulata |
N |
T |
- |
|
+ |
|
|
Sphaerocaryum malaccense |
Y |
H |
- |
|
+ |
+ |
+ |
Sphenomeris chinensis |
Y |
H |
- |
|
+ |
|
+ |
Sporobolus fertilis |
Y |
H |
- |
|
+ |
|
|
Stachytarpheta jamaicensis |
N |
S |
- |
|
+ |
|
++ |
Stauntonia obovata |
Y |
C |
- |
|
+ |
|
|
Stephania longa |
Y |
C |
- |
+ |
+ |
|
+ |
Sterculia lanceolata |
Y |
T |
- |
|
+++ |
+++ |
+++ |
Strophanthus divaricatus |
Y |
C |
- |
|
+++ |
+ |
+ |
Strychnos angustiflora |
Y |
C |
- |
|
+++ |
++ |
+++ |
Strychnos cathayensis |
Y |
C |
- |
|
+ |
|
|
Styrax suberifolius |
Y |
T |
- |
|
++ |
|
|
Synedrella nodiflora |
N |
H |
- |
|
+ |
|
|
Syzygium jambos |
N |
T |
- |
|
+ |
|
|
Tadehagi triquetrum |
Y |
S |
- |
|
++ |
|
|
Tainia hongkongensis |
Y |
H |
(a) (b) |
|
+ |
+ |
|
Tarenna attenuata |
Y |
S |
- |
|
+ |
|
|
Telosma cordata |
N |
C |
- |
|
+ |
|
|
Ternstroemia gymnanthera |
Y |
T |
- |
|
+ |
|
|
Tetracera asiatica |
Y |
C |
- |
|
++ |
+ |
+ |
Tetradium glabrifolium |
Y |
T |
- |
|
+ |
|
+ |
Thevetia peruviana |
N |
T |
- |
|
+ |
|
|
Thysanolaena agrostis |
Y |
H |
- |
|
+ |
|
|
Toddalia asiatica |
Y |
S |
- |
|
+ |
|
+ |
Trema tomentosa |
Y |
S |
- |
+ |
+ |
|
+ |
Tylophora ovata |
Y |
C |
- |
|
++ |
|
+ |
Uraria crinita |
Y |
S |
- |
|
+ |
|
|
Urena lobata |
Y |
H |
- |
|
+ |
+ |
+ |
Utricularia caerulea |
Y |
H |
- |
|
+ |
+ |
|
Uvaria macrophylla |
Y |
C |
- |
|
+++ |
|
++ |
Ventilago leiocarpa |
Y |
C |
- |
|
+ |
|
|
Vernonia cinerea |
Y |
H |
- |
|
+ |
|
|
Viburnum sempervirens |
Y |
S |
- |
|
+ |
|
|
Viola diffusa |
Y |
H |
- |
|
+ |
|
|
Vitex negundo |
Y |
S |
- |
|
+ |
|
|
Vitex quinata |
Y |
T |
- |
|
+ |
|
|
Wedelia trilobata |
N |
H |
- |
|
|
+ |
+ |
Wikstroemia indica |
Y |
S |
- |
|
++ |
|
|
Wikstroemia nutans |
Y |
S |
- |
|
++ |
|
|
Zanthoxylum avicennae |
Y |
T |
- |
|
++ |
++ |
++ |
Zanthoxylum nitidum |
Y |
C |
- |
|
++ |
+ |
+ |
Zanthoxylum scandens |
Y |
C |
- |
|
+ |
|
|
(1) Habit: T=Tree;
S=Shrub / Bamboo; H=Herb; C=Climber.
(2) Status: (a)
listed species in Forestry Regulation (Cap.96 sub. Leg.);
(b)
listed species in Protection of Endangered Species of Animals and Plants
Ordinance (Cap 586);
(c)
listed species in AFCD’s Rare and Precious Plants of Hong Kong;
(d)
rare species listed in Corlett’s study Hong Kong Vascular Plants: Distribution
and Status;
(e) listed in China Red Data Book: (e)EX:
Extinct; (e)EW: Extinct in the wild; (e)CR: Critically Endangered; (e)EN: Endangered; (e)VU: Vulnerable; (e)NT:
Near Threatened; (e)LC: Least Concern;
(f) listed in IUCN 2008: (f)EX: Extinct; (f)EW:
Extinct in the wild; (f)CR: Critically Endangered; (f)EN: Endangered; (f)VU: Vulnerable; (f)NT:
Near Threatened; (f)LC: Least Concern.
(3) Abundance: +++=abundant;
++=fairly abundant; +=low abundance
(4) Species were recorded on slopes and exposed areas
of the reservoir
Table G‑2 Status of Mammals Recorded within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
Status^ |
Distribution* |
Protection* |
Rhesus Macaque |
Macaca mulatta |
Common |
Widely distributed |
Cap.170; Cap.586; IUCN - Lower Risk/Near
Threatened; |
East Asian Porcupine |
Hystrix brachyura |
Very Common |
Widely distributed |
Cap.170; IUCN - Vulnerable |
Note:
^Status
follows Shek, C.T., Chan, C.S.M. and Wan, Y.F. (2007). Camera Trap Survey of
*Distribution
and Protection follows Shek, C.T. (2006). A Field Guide to the Terrestrial
Mammals of
(Cap.170
- Wild Animals Protection Ordinance; Cap. 586 - Protection of Endangered
Species of Animals and Plants Ordinance; CRDB -
Table G‑3a Bird Species Recorded within
Common Name |
Scientific Name |
Wet Season |
Dry Season |
Conservation Status / Level of Concern |
Cattle Egret |
Bubulcus ibis |
√ |
|
Local Concern |
Black Kite |
Milvus migrans |
√ |
|
Regional Concern |
Spotted Dove |
Streptopelia chinensis |
√ |
√ |
|
Grey Wagtail |
Motacilla alba |
√ |
|
|
Crested Bulbul |
Pycnonotus jocosus |
√ |
√ |
|
Chinese Bulbul |
Pycnonotus sinensis |
√ |
√ |
|
Violet Whilsting Thrush |
Myiophoneus caeruleus |
√ |
|
|
Yellow-bellied Warbler |
Phylloscopus inornatus |
√ |
√ |
|
Long-tailed Tailor Bird |
Orthotomus sutorius |
√ |
|
|
Hawamei |
Garrulax canorus |
√ |
|
|
Grest Tit |
Parus major |
√ |
√ |
|
Japanese White Eye |
Zosterops japonica |
√ |
√ |
|
Flower Pecker spp |
Diaeum spp. |
√ |
|
|
Large-billed Crow |
Corvus macrohynchus |
√ |
|
|
Common Tailor Bird |
Orthotomus sutorius |
|
√ |
|
Tree Sparrow |
Passer montanus |
|
√ |
|
Black-faced Laughingthrush |
Garrulax perspicillatus |
|
√ |
|
Blue magpie |
Urocissa erythrorhy |
|
√ |
|
Magpie |
Pica pica |
|
√ |
|
Greater Coucal |
Centropus sinensis |
|
√ |
Listed as Vulnerable in |
Grey-backed Thrush |
Turdus hortulorum |
|
√ |
|
Fork-tailed Sunbird |
Aethopyga christinae |
|
√ |
|
Buzzard |
Buteo buteo |
|
√ |
|
Rufous-backed Shrike |
Lanius schach |
|
√ |
|
Table G‑3b Status and Abundance of Bird Species Recorded within the Point Count Location (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
WL |
GL |
S |
R |
DA |
Principal Status^ |
Conservation Status / Level of Concern |
Commonness and |
Black Kite |
Milvus migrans |
5 |
|
|
|
|
W, R |
Regional
Concern |
CW |
Spotted Dove |
Streptopelia chinensis |
20 |
|
|
|
|
R |
|
CW |
Yellow Wagtail |
Motacilla flava |
|
|
|
1 |
|
M,W |
|
CL |
White Wagtail |
Motacilla alba |
|
|
|
10 |
2 |
W, R |
|
CW |
Red-whiskered Bulbul |
Pycnonotus jocosus |
29 |
|
|
|
6 |
R |
|
CW |
Chinese Bulbul |
Pycnonotus sinensis |
23 |
|
|
|
|
R |
|
CW |
Long-tailed Shrike |
Lanius schach |
|
|
|
1 |
|
R |
|
CW |
Oriental Magpie Robin |
Copsychus saularis |
1 |
|
|
|
1 |
R |
|
CW |
Black-throated Laughingthrush |
Garrulax chinensis |
3 |
|
|
|
|
R |
|
R |
Hwamei |
Garrulax canorus |
4 |
|
|
|
|
R |
|
CL |
Yellow-bellid Prinia |
Prinia flaviventris |
1 |
|
|
|
|
R |
|
CW |
Pale-legged Leaf Warbler |
Phylloscopus tenellipes |
11 |
|
|
|
|
AM |
|
R |
Red-throated Flycatcher |
Ficedula albicilla |
2 |
|
|
|
|
AM, W |
|
R |
Great Tit |
Parus major |
2 |
|
|
|
|
R |
|
CW |
Japanese White-eye |
Zosterops japonica |
2 |
|
|
|
|
R, ?W |
|
CW |
Large-billed Crow |
Corvus macrohynchus |
3 |
1 |
|
|
|
R |
|
CW |
|
|
|
|
|
|
|
|
|
|
Total Birds |
|
106 |
1 |
0 |
12 |
9 |
|
|
|
Total
Species |
|
13 |
1 |
0 |
3 |
3 |
|
|
|
^ Principal Status: R - Resident; W - Winter
visitor; Su - Summer; M - Migrant; AM - Autumn migrant; P - Present all year,
exact compostion unknown; ?W - Increased number in winter.
Principal status follows: Carey, G.J.,
Chalmers, M.L., Diskin, D.A., Kennerley, P.R., Leader, P.J., Leven, M.R.,
Lewthwaite, R.W., Melville, D.S., Turnbull, M., and Yound, L.(2001): The
Avifauna of Hong Kong. Hong Kong Bird Watching Society,
* Commonness and Distribution: CW - Common
and widespread; CL - Local but not uncommon; R - Very local or rare
Habitats: WL - Secondary
Table G‑3c Bird Species Recorded in Each Location within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
Location |
Principal Status^ |
Conservation
Status / Level of Concern |
Commonness
and |
Common Kingfisher |
Alcedo atthis |
KBR |
AM,P |
|
CW |
Common Teal |
Anas crecca |
KRR |
W |
Regional
Concern |
CL |
Oriental Magpie Robin |
Copsychus saularis |
KSCP, KS-1 |
R |
|
CW |
Large-billed Crow |
Corvus macrohynchus |
LSM-2, LSM-6, KS-2,
KS-5, KBR |
R |
|
CW |
Black Drongo |
Dicrurus macrocercus |
KBR |
M,Su |
|
CW |
Red-throated Flycatcher |
Ficedula albicilla |
KS-1 |
AM,W |
|
R |
Hwamei |
Garrulax canorus |
LSM-2, LSM-3, KS-3, KBR |
R |
|
CL |
Black-throated Laughingthrush |
Garrulax chinensis |
KS-3 |
R |
|
R |
Masked Laughingthrush |
Garrulax perspicillatus |
KSCP |
R |
|
CW |
Long-tailed Shrike |
Lanius schach |
LSM-4, LSMR |
R |
|
CW |
Black Kite |
Milvus migrans |
LSM-2, KS-2, KS-4,
KS-5, KSCP, KBR |
W,R |
Regional
Concern |
CW |
White Wagtail |
Motacilla alba |
LSM-1, LSM-4, LSM-5, KBR |
W,R |
|
CW |
Grey Wagtail |
Motacilla cinerea |
KBR |
W |
|
CW |
Yellow Wagtail |
Motacilla flava |
LSM-4 |
M,W |
|
CL |
Asian Brown Flycatcher |
Muscicapa dauurica |
KBR |
M,W |
|
CL |
Common Tailorbird |
Orthotomus sutorius |
KBR |
R |
|
CW |
Great Tit |
Parus major |
KS-1 |
R |
|
CW |
Pale-legged Leaf Warbler |
Phylloscopus tenellipes |
LSM-2, LSM-3, LSM-7, KS-4, LSMR |
AM |
|
R |
Yellow-bellid Prinia |
Prinia flaviventris |
KS-4 |
R |
|
CW |
Red-whiskered Bulbul |
Pycnonotus jocosus |
KS-1, KS-2, KS-5, LSM-3, LSM-6, LSMR, KBR, KSCP |
R |
|
CW |
Chinese Bulbul |
Pycnonotus sinensis |
LSM-4, LSM-7, KS-1, KS-2, KS-4, LSMR, KBR, KSCP |
R |
|
CW |
Rufous-capped Babbler |
Stachyris ruficeps |
KSCP |
R |
Local
Concern |
Scarce
resident of |
Spotted Dove |
Streptopelia chinensis |
KS-1, KS-2, KS-5, LSM-3, KBR, KSCP, LRCP |
R |
|
CW |
Japanese White-eye |
Zosterops japonica |
KS-2, KSCP, LSMR |
R,?W |
|
CW |
^ Principal Status: R - Resident; W - Winter
visitor; Su - Summer; M - Migrant; AM - Autumn migrant; P - Present all year,
exact composition unknown; ?W - Increased number in winter.
Principal status follows: Carey, G.J.,
Chalmers, M.L., Diskin, D.A., Kennerley, P.R., Leader, P.J., Leven, M.R.,
Lewthwaite,
R.W., Melville, D.S., Turnbull, M., and Young, L.(2001): The Avifauna of Hong
Kong. Hong Kong Bird Watching Society,
* Commonness and Distribution: CW - Common
and widespread; CL - Local but not uncommon; R - Very local or rare
Location: LSMR - Lower Shing Mun Reservoir;
KSCP - Kam Shan Country Park; KBR - Kowloon Byewash Reservoir; KRR - Kowloon
Reception Reservoir; LRCP - Lion Rock Country Park.
Table G‑4a Herpetofauna Recorded within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
Location |
Conservation
Status/ Level of Concern |
Commonness
and |
Chinese Gecko |
Gekko chinensis |
|
|
VC |
Grass Lizard |
Takydromus sexlineatus ocellatus |
|
|
UC |
Red-eared Slider |
Trachemys scripta elegans |
|
|
Introduced
species well established in several reservoirs |
Asian Common Toad |
Bufo melanostictus |
|
|
A |
Lesser Spiny Frog |
Rana exillispinosa |
KS-5, |
Potential
Global Concern |
C |
* Commonness and Distribution: A - Abundant;
VC - Very Common; C - Common; UC - Uncommon (Karsen et al., 1998)
Table G‑4b Status and Abundance of Herpetofauna Recorded within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
WL |
GL |
S |
R |
DA |
Conservation
Status/ Level of Concern |
Commonness
and |
Chinese Gecko |
Gekko chinensis |
|
|
|
|
3 |
|
VC |
Grass Lizard |
Takydromus sexlineatus ocellatus |
|
|
|
|
1 |
|
UC |
Red-eared Slider |
Trachemys scripta elegans |
|
|
|
3 |
|
|
Introduced
species well established in several reservoirs |
Asian Common Toad |
Bufo melanostictus |
|
|
|
|
18 |
|
A |
Lesser Spiny Frog |
Rana exillispinosa |
|
|
27 |
|
|
Potential
Global Concern |
C |
|
|
|
|
|
|
|
|
|
Total Herpetofauna |
|
0 |
0 |
27 |
3 |
22 |
|
|
Total Species |
|
0 |
0 |
1 |
1 |
3 |
|
|
* Commonness and Distribution: A - Abundant;
VC - Very Common; C - Common; UC - Uncommon (Karsen et al., 1998)
Habitats: WL - Secondary
Table G‑5a Abundance and Commonness of Butterfly Species Recorded within the Point Count Location (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
WL |
GL |
S |
R |
DA |
Commonness
and |
Conservation Status / Level of Concern |
Hesperiidae |
||||||||
Tree Flitter |
Hyarotis adrastus |
|
1 |
|
|
|
UC |
-- |
Papilionidae |
||||||||
Common Mormon |
Papilio polytes |
11 |
5 |
1 |
2 |
|
VC |
-- |
Great Mormon |
Papilio memnon |
1 |
3 |
1 |
|
|
VC |
-- |
|
Papilo paris |
5 |
1 |
|
|
|
VC |
-- |
Pieridae |
||||||||
Red-base Jezebel |
Delias pasithoe |
99 |
14 |
23 |
18 |
8 |
VC |
-- |
Indian Cabbage White |
Pieris canidia |
1 |
|
2 |
1 |
1 |
VC |
-- |
Common Grass Yellow |
Eurema hecabe |
10 |
6 |
13 |
11 |
2 |
VC |
-- |
Lycaenidae |
||||||||
Slate Flash |
Rapala manea |
|
|
|
|
1 |
C |
-- |
Common Hedge Blue |
Acytolepis puspa |
|
|
|
|
4 |
C |
-- |
Riodinidae |
||||||||
Punchinello |
Zemeros flegyas |
|
1 |
|
|
|
C |
-- |
|
Abisara echerius |
|
2 |
3 |
1 |
|
VC |
-- |
Banded Tree Brown |
Lethe confusa |
|
1 |
|
|
|
VC |
-- |
Dark Brand Bush Brown |
Mycalesis mineus |
1 |
4 |
12 |
|
|
VC |
-- |
Common Five-ring |
Ypthima baldus |
|
2 |
|
|
|
VC |
-- |
Straight Five-ring |
Ypthima lisandra |
1 |
|
|
1 |
|
C |
-- |
Amathusiidae |
||||||||
Large Faun |
Faunis eumeus |
1 |
|
|
|
|
C |
-- |
Nymphalidae |
||||||||
Rustic |
Cupha erymanthis |
2 |
2 |
4 |
|
|
VC |
-- |
Great Eggfly |
Hypolimnas bolina |
1 |
3 |
|
1 |
|
VC |
|
Common Sailer |
Neptis hylas |
6 |
2 |
1 |
1 |
|
VC |
-- |
Southern Sullied Sailer |
Neptis clinia |
|
2 |
|
|
|
C |
-- |
Staff Sergeant |
Athyma selenophora |
1 |
1 |
|
|
|
C |
-- |
Common Mapwing |
Cyrestis thyodamas |
|
|
1 |
|
|
C |
-- |
Danaidae |
||||||||
Glassy Tiger |
Parantica aglea |
|
2 |
5 |
|
|
VC |
-- |
|
Ideopsis similis |
5 |
|
6 |
12 |
|
VC |
-- |
Common Tiger |
Danaus genutia |
|
2 |
|
12 |
|
VC |
-- |
Blue Spotted Crow |
Euploea midamus |
2 |
2 |
4 |
6 |
|
VC |
-- |
Common Indian Crow |
Euploea core |
|
|
|
1 |
|
VC |
-- |
|
|
|
|
|
|
|
|
|
Total
Butterflies |
|
43 |
33 |
41 |
29 |
4 |
|
|
Total
Species |
|
11 |
13 |
8 |
7 |
3 |
|
|
Habitats: WL - Secondary
* Commonness and Distribution: UC -
Uncommon; C - Common; VC - Very Common (Young and Yiu, 2002)
Table G‑5b Butterfly Species Recorded in each Location within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
Location |
Commonness and |
Conservation Status / Level of Concern |
Hesperiidae |
||||
Tree Flitter |
Hyarotis adrastus |
LSM-2 |
UC |
-- |
Formosan Swift |
Borbo cinnara |
KSCP |
C |
-- |
Papilionidae |
||||
Common Mime |
Chilasa clytia |
KBR |
C |
-- |
Common Mormon |
Papilio polytes |
KS-1, KS-2, KS-4, LSM-2, LSM-3, |
VC |
-- |
Great Mormon |
Papilio memnon |
LSM-2, LSM-6, LSM-7 |
VC |
-- |
|
Papilo paris |
KS-1, KS-4, LSM-2, LSM-6, LSM-7, |
VC |
-- |
Pieridae |
||||
Red-base Jezebel |
Delias pasithoe |
KS-1, KS-2, KS-3, KS-4, KS-5, |
VC |
-- |
Indian Cabbage White |
Pieris canidia |
LSM-1, LSM-3, LSM-4, LSM-5, |
VC |
-- |
Common Grass Yellow |
Eurema hecabe |
KS-1, KS-3, KS-4, KS-5, LSM-1, LSM-2, LSM-3,
LSM-4 LSM-5, |
VC |
-- |
Lycaenidae |
||||
Slate Flash |
Rapala manea |
LSM-1 |
C |
-- |
Pale Grass Blue |
Zizeeria maha |
KBR |
C^ |
|
Common Hedge Blue |
Acytolepis puspa |
LSM-1 |
C |
-- |
Riodinidae |
||||
Punchinello |
Zemeros flegyas |
LSM-2 |
C |
-- |
|
Abisara echerius |
LSM-2, LSM-3, LSM-5, LSM-6, KSCP, LSMR |
VC |
-- |
Banded Tree Brown |
Lethe confusa |
LSM-2 |
VC |
-- |
Bamboo Tree Brown |
Lethe europa |
KSCP |
C |
-- |
Dark-brand Bush Brown |
Mycalesis mineus |
LSM-2, LSM-6, LSM-7, KS-5 |
VC |
-- |
Common Five-ring |
Ypthima baldus |
LSM-2 |
VC |
-- |
Straight Five-ring |
Ypthima lisandra |
KS-1, KS-4, KSCP, LSMR |
C |
-- |
Amathusiidae |
||||
Large Faun |
Faunis eumeus |
KS-2, KSCP |
C |
-- |
Nymphalidae |
||||
Rustic |
Cupha erymanthis |
LSM-2, LSM-6 |
VC |
-- |
Great Eggfly |
Hypolimnas bolina |
LSM-2, LSM-5, LSM-6 |
VC |
-- |
Common Sailer |
Neptis hylas |
LSM-2, LSM-3, LSM-6, KS-2, KS-4 |
VC |
-- |
Southern Sullied Sailer |
Neptis clinia |
LSM-2 |
C |
-- |
Staff Sergeant |
Athyma selenophora |
LSM-2, KS-1 |
C |
-- |
Common Mapwing |
Cyrestis thyodamas |
LSM-6, LSMR |
C |
-- |
Danaidae |
||||
Glassy Tiger |
Parantica aglea |
LSM-2, LSM-6 |
VC |
-- |
|
Ideopsis similis |
LSM-3, LSM-4, LSM-5, LSM-6, |
VC |
-- |
Common Tiger |
Danaus genutia |
LSM-2, LSM-3, LSM-4, LSM-5 |
VC |
-- |
Blue Spotted Crow |
Euploea midamus |
LSM-2, LSM-3, LSM-4, LSM-5, |
VC |
-- |
Common Indian Crow |
Euploea core |
LSM-5, LSMR |
VC |
-- |
* Commonness and Distribution: UC -
Uncommon; C - Common; VC - Very Common
(Young and Yiu, 2002)
^ Status follows AFCD Hong Kong Biodiversity
Database: <http://www.afcd.gov.hk/english/conservation/hkbiodiversity/database/search.asp>
Location: LSMR - Lower Shing Mun Reservoir;
KSCP - Kam Shan Country Park; KBR - Kowloon Byewash Reservoir; KRR - Kowloon
Reception Reservoir; LRCP - Lion Rock Country Park.
Table G6a Abundance and Commonness of Dragonfly Species Recorded within the Point Count Location (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
WL |
GL |
S |
R |
DA |
Commonness
and |
Crimson Darter |
Crocothemis servilla servilla |
|
|
|
|
5 |
A |
Common Blue Skimmer |
Orthetrum glaucum |
1 |
|
6 |
2 |
|
A |
Wandering Glider |
Pantala flavescens |
32 |
8 |
2 |
8 |
8 |
A |
Black Threadtail |
Prodasineura autumnalis |
|
|
1 |
|
|
A |
Saddlebag Glider |
Tramea virginia |
|
|
2 |
|
|
C |
Crimson Dropwing |
Trithemis aurora |
|
|
|
8 |
|
A |
Indigo Dropwing |
Trithemis festiva |
|
|
5 |
|
|
A |
Total
Dragonflies |
|
33 |
8 |
16 |
18 |
13 |
|
Total species |
|
2 |
1 |
5 |
3 |
2 |
|
*
Commonness and Distribution: A - Abundent; C - Common (
Habitats:
WL - Secondary
Table G6b Dragonfly Species Recorded in each Location within the Study Area (25, 31 October 2007; 3, 5, 14 December 2007; 11, 15 January 2008)
Common Name |
Scientific Name |
Location |
Commonness and |
Crimson Darter |
Crocothemis servilla servilla |
LSM-1 |
A |
Common Blue Skimmer |
Orthetrum glaucum |
LSM-4, LSM-5, KS-1, KBR, KSCP |
A |
Wandering Glider |
Pantala flavescens |
LSM-1, LSM-2, LSM-3, LSM-4, LSM-5, LSM-7, KS-4, KS-5, KBR,
LSCP |
A |
Black Threadtail |
Prodasineura autumnalis |
LSM-5 |
A |
Saddlebag Glider |
Tramea virginia |
LSM-5 |
C |
Crimson Dropwing |
Trithemis aurora |
LSM-4 |
A |
Indigo Dropwing |
Trithemis festiva |
LSM-5, LSM-6 |
A |
*
Commonness and Distribution: A - Abundent; C - Common (Wilson et al., 2003)
Location:
LSMR - Lower Shing Mun Reservoir; KSCP - Kam Shan Country Park; KBR - Kowloon
Byewash Reservoir; KRR - Kowloon Reception Reservoir; LRCP - Lion Rock Country
Park.
Table G7a Status and Abundance of Aquatic Fauna Recorded within the Survey Point (Stream tributaries: 25, 31 October and 3, 14 December 2007; Reservoirs: 13 November and 17 December 2007)
Common Name |
Scientific Name |
S |
R |
Conservation
Status / Level of Concern |
Commonness
and |
Freshwater Shrimp |
Caridina cantonensis |
5 |
|
|
C^ |
Water Skater |
Ptilomera tigrina |
3 |
|
|
C^ |
Mosquito Fish |
Gambusia affinis |
|
23 |
|
C* |
Jewel Fish |
Hemichromis stellifer |
|
129 |
|
Aquarium
fish occurs in large number in a few local reservoirs* |
|
Oreochromis niloticus |
|
1 |
|
C* |
Flat-headed Loach |
Oreonectes platycephalus |
15 |
|
|
C* |
Predaceous Chub |
Parazacco spilurus |
|
37 |
Listed as
Vulnerable in |
C* |
Chinese Half-striped |
Puntius semifasciolatus |
|
2 |
|
C* |
Rose Bitterling |
Rhodeus ocellatus |
|
2 |
Local
Concern |
R* |
Tilapia Joka |
Tilapia joka |
|
4 |
|
Introduced
species* |
Redbelly Tilapia |
Tilapia zillii |
|
140 |
|
C* |
Total
Aquatic Fauna |
23 |
338 |
|
|
|
Total
species |
3 |
8 |
|
|
Commonness
and Distribution: C - Common; R - Rare (*Lee et al., 2004; ^Dudgeon, 2003)
Habitats:
S - Stream / Drainage Channel; R - Reservoir
Table G7b Aquatic Fauna Recorded in each Location within the Study Area (Stream tributaries: 25, 31 October and 3, 14 December 2007; Reservoirs: 13 November and 17 December 2007)
Common Name |
Scientific Name |
Location |
Conservation
Status / Level of Concern |
Commonness
and |
Freshwater Shrimp |
Caridina cantonensis |
AF-3, AF-7 |
|
C^ |
Water Skater |
Ptilomera tigrina |
AF-2 |
|
C^ |
Freshwater Mussel |
Anodonta woodiana |
AF-6 |
|
-- |
Mosquito fish |
Gambusia affinis |
AF-6, AF-8, AF-9 |
|
C* |
Jewel fish |
Hemichromis stellifer |
AF-4, AF-5, AF-6, AF-8, AF-9 |
|
Aquarium
fish occurs in large number in a few local reservoirs* |
|
Oreochromis niloticus |
AF-5 |
|
C* |
Flat-headed Loach |
Oreonectes platycephalus |
AF-7 |
|
C* |
Predaceous Chub |
Parazacco spilurus |
AF-6, AF-8, AF-9 |
Listed as Vulnerable in |
C* |
Chinese Half-striped |
Puntius semifasciolatus |
AF-8 |
|
C* |
Rose Bitterling |
Rhodeus ocellatus |
AF-6 |
Local Concern |
R* |
Tilapia Joka |
Tilapia joka |
AF-4, AF-5 |
|
Introduced
species* |
Redbelly tilapia |
Tilapia zillii |
AF-5, AF-6, AF-8 |
|
C* |
Commonness
and Distribution: C - Common; R - Rare (*Lee et al., 2004; ^Dudgeon, 2003)
Location:
AF-1 to AF-9 = Aquatic Fauna survery locations within the Study Area, shown in Figure 8.1.
Appendix H Plates
Plate
8.1 Secondary |
Plate 8.2
Grassland |
Plate
8.3 Stream / Drainage Channel |
Plate 8.4
Reservoir |
Plate 8.5 Developed Area / Bare Ground |
Plate 8.6 Rhesus Macaque
recorded in Kam Shan Country Park |
|
|
Plate 8.7
Scat of East Asian Porcupine |
Plate 8.8
Chinese Gecko |
|
|
Plate 8.9
Asian Common Toad |
Plate 8.10 Red-eared Slider
stained with red
paint |
|
|
Plate 8.11 Tadpole of Lesser Spiny Frog |
Plate 8.12 Emergence of adult
Red-base Jezebel from pupa |
|
|
Plate 8.13 Dead mussel Anodonta woodiana |
|
Appendix J Catalogue
Table J1 Dam
Project: Inter reservoir Transfer
Scheme Title: Dam |
Location: Map Ref: Figure 10-1 |
Ref # IRTS-01 |
Originally Recorded:
03.03.08 |
Updated
On: N/A |
|
Original
Usage: Dam |
Current
Usage: Dam |
|
Orientation:
The dam runs from the southeast to the northwest |
Address:
N/A |
|
Construction
Date: 1931 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Stone arched dam with single lane road across the top with concrete
balustrade. |
||
Inscriptions:
None |
||
Additional
Notes: Grade II Historic Structure |
Table J2 Valve House
Project: Inter reservoir Transfer
Scheme Title: Valve House |
Location: Map Ref: Figure 10-1 |
Ref # IRTS-02 |
Originally Recorded:
03.03.08 |
Updated
On: N/A |
|
Original
Usage: Valve House |
Current
Usage: Valve House |
|
Orientation:
the valve house faces southwesterly |
Address:
N/A |
|
Construction
Date: 1931 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Rectangular stone and concrete structure.
Windows have been sealed up. Flat roof with concrete moulding around
edges. |
||
Inscriptions: 1929 HKWW 1931 on lintel above the entrance
door |
||
Additional
Notes: Grade II Historic Structure |
Table J3
Project: Inter reservoir Transfer
Scheme Title: |
Location: Map Ref: Figure 10-2 |
Ref # IRTS-03 |
Originally Recorded:
03.03.08 |
Updated
On: N/A |
|
Original
Usage: Dam |
Current
Usage: Dam |
|
Orientation:
The dam runs from the southeast to the northwest |
Address:
N/A |
|
Construction
Date: 1965 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Vegetation covered dam wall with single lane road across the top. |
||
Inscriptions:
None |
||
Additional
Notes: Grade I Historic Structure |
Table J4 Northeast Dam
Project: Inter reservoir Transfer
Scheme Title: Northeast Dam |
Location: Shek Lei Pui Reservoir Map Ref: Figure 10-3 |
Ref # IRTS-04 |
Originally Recorded:
19.07.08 |
Updated
On: N/A |
|
Original
Usage: Dam |
Current
Usage: Dam |
|
Orientation:
The dam runs from south to north |
Address:
N/A |
|
Construction
Date: 1925 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Cut stone curved surface. No
walkway across dam. |
||
Inscriptions:
None |
||
Additional
Notes: Grade II Historic Structure |
Table J5 Northeast Dam Valve House
Project: Inter reservoir Transfer
Scheme Title: Northeast Dam Valve House |
Location: Shek Lei Pui Reservoir Map Ref: Figure 10-3 |
Ref # IRTS-05 |
Originally Recorded:
19.07.08 |
Updated
On: N/A |
|
Original
Usage: Valve House |
Current
Usage: Dam |
|
Orientation:
the valve house faces easterly |
Address:
N/A |
|
Construction
Date: 1925 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Concrete square structure, sealed up. Exterior has concrete moulded to
resemble stone work. Flat roof. |
||
Inscriptions:
None |
||
Additional
Notes: Grade II Historic Structure |
Table J6 Southwest Dam
Project: Inter reservoir Transfer
Scheme Title: Southwest Dam |
Location: Shek Lei Pui Reservoir Map Ref: Figure 10-1 |
Ref # IRTS-06 |
Originally Recorded:
19.07.08 |
Updated
On: N/A |
|
Original
Usage: Dam |
Current
Usage: Dam |
|
Orientation:
The dam runs from the southeast to the northwest |
Address:
N/A |
|
Construction
Date: 1925 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Very high cut stone and concrete structure with walkway on the top surface
across the dam. Metal railings |
||
Inscriptions:
None |
||
Additional
Notes: Grade II Historic Structure |
Table J7 Dam
Project: Inter reservoir Transfer
Scheme Title: Dam |
Location: Map Ref: Figure 10-1 |
Ref # IRTS-07 |
Originally Recorded:
19.07.08 |
Updated
On: N/A |
|
Original
Usage: Dam |
Current
Usage: Dam |
|
Orientation:
The dam runs from the southeast to the northwest |
Address:
N/A |
|
Construction
Date: 1910 |
Ownership:
HKSAR Government |
|
Setting:
Reservoir |
Historical
Associations: None |
|
Condition:
Good |
Degree of
Modification: Low |
|
Architectural
Significance: Moderate |
Cultural
Significance: Moderate |
|
Description:
Long curved cut stone dam structure with road and metal railing on the top. |
||
Inscriptions:
None |
||
Additional
Notes: Grade I Historic Structure |
[i]
Working Paper No. 1 –
Evaluation of Alternative Portal Locations/ Tunnel Alignments under Agreement
No. CE 54/2006 (WS) – Inter-reservoirs Transfer Scheme (IRTS) Water Tunnel between
Kowloon Byewash Reservoir and Lower Shing Mun Reservoir – August 2007 by Black
& Veatch Hong Kong Limited.
[ii]
Working Paper No. 3 –
Evaluation of Construction Methods for the Water Transfer Tunnel under
Agreement No. CE 54/2006 (WS) – Inter-reservoirs Transfer Scheme (IRTS) Water
Tunnel between Kowloon Byewash Reservoir and Lower Shing Mun Reservoir –
January 2008 by Black & Veatch Hong Kong Limited.